# How to write a RAMS

> Write the job in the order it will be done, name who each step could harm, and put each control before the work it protects. One trench job, worked through.
> Web page: https://complyonsite.com/rams/how-to

Write the job down in the order it will be done. Beside each step, who it could harm and how. Put each control before the work it protects.

One job, a duct trench across a car park verge, in six stages. Step through them to see each one written in the method statement and the risk assessment.

Method statement, step 1

Get the service information first

Get the current plans from each service owner. Keep them with the RAMS.

Risk assessment, step 1

- **Hazard**: Striking an unrecorded cable, gas pipe or water main
- **Who**: The locating team and the people who dig next
- **Controls**: Contact the service owners before intrusive work.Treat missing records as an unresolved risk.

### Method statement

1. **Get the service information first** Get the current plans from each service owner. Keep them with the RAMS.
2. **Survey and mark the whole area** A competent person sweeps the whole route with a locator and signal generator. They mark every indication where the dig team will see it.
3. **Barrier the open excavation** Barrier the route and the footpath end before the first bucket. Set out the dig against the marks.
4. **Dig to the marks, by hand near services** Excavator away from the marks. Hand dig where the cable is marked until it is exposed. Spoil set back from the edge.
5. **Record the as-laid route** Lay and join the duct to the drawing, clear of the cable. Record the route, ends and depth before it is covered.
6. **Get the excavation released** Inspect and record before anything goes back in. Bed and cover the duct and cable by hand, then fill and compact in layers.

### Risk assessment

| Step | Hazard | Who | Controls |
| --- | --- | --- | --- |
| 1 | Striking an unrecorded cable, gas pipe or water main | The locating team and the people who dig next | - Contact the service owners before intrusive work. - Treat missing records as an unresolved risk. |
| 2 | A service route being missed, misread or not passed to the digging team | The locating team and anyone working near the marks | - Survey before the work is planned and set out. - Record areas that could not be scanned. |
| 3 | A person falling into the open excavation | The dig team, other trades and people passing | - Check the barrier after work or weather changes. - Do not leave an open excavation unprotected. |
| 4 | Hitting a buried cable or gas pipe causes shock, burns or a gas escape | The person doing the work and everyone nearby | - Use hand exposure where the planned work is near an assumed service. |
| A moving excavator striking or trapping a person | The operator, dig team and people passing | - Keep pedestrians out of the operating area. - Stop the machine before anyone enters its working area. |  |
| 5 | A duct being lost or installed differently from the record | The duct team and whoever uses the duct later | - Record what was actually laid, not just the design. - Keep the handover record with the job file. |
| 6 | Burying faulty work or losing the evidence needed to repair it | The backfill team and the service owner | - Use this job’s release arrangement. - Keep the inspection record with the RAMS. |

## [Say exactly which job it covers](https://complyonsite.com/rams/how-to#the-job)

**“Groundworks” is a trade, not a job.** Name the place, the work and what is already known about the site.

Groundworks RAMS

- **Where**: Not said
- **Work**: Not said
- **Known**: Not said
- **Nearby**: Not said
- **Plant**: Not said

Duct trench across the car park verge

- **Where**: Car park verge, from the building to the footpath, about 15 m
- **Work**: Dig a shallow trench, lay an empty duct, backfill
- **Known**: A low-voltage cable crosses the route on the owner’s plan
- **Nearby**: Public footpath at the east end
- **Plant**: Mini excavator, hand tools, plate compactor

Then list the stages in the order they happen, as in the six above.

## [Name who each stage could harm, and how](https://complyonsite.com/rams/how-to#who-could-be-harmed)

**Write who could be hurt and how before any controls.** Not only your own team. Here is the dig.

From [HSE, Steps needed to manage risk](https://www.hse.gov.uk/simple-health-safety/risk/steps-needed-to-manage-risk.htm) and [Management of Health and Safety at Work Regulations 1999, regulation 3](https://www.legislation.gov.uk/uksi/1999/3242/regulation/3).

## [Put each control before the work it protects](https://complyonsite.com/rams/how-to#control-before-work)

**A control is a step someone does, placed before the work it protects.** “Take care” cannot go anywhere in the order, because nobody can do it.

This draft came back from site. Play it and stop where something has to happen first.

1. Get the service plans
2. Dig the trench
3. Lay and join the duct
4. Backfill and compact

### The order, corrected

1. **Survey and mark the whole area** before **digging the trench** The dig is set out against the marks, so the marks have to exist first.
2. **Barrier the open excavation** before **digging the trench** The hole is open from the first bucket, so the barrier goes up before it.
3. **Get the excavation released** before **backfilling and compacting** Once it is buried nobody can check it, so the release comes before the fill.
4. **Bed and cover the duct and cable by hand** before **backfilling and compacting** The cover protects the services from the fill and the plate, so it goes in by hand first.

From [HSE, Avoiding danger from underground services (HSG47)](https://www.hse.gov.uk/pubns/priced/hsg47.pdf) and [HSE, Excavations](https://www.hse.gov.uk/construction/safetytopics/excavations.htm).

## [The finished RAMS](https://complyonsite.com/rams/how-to#the-finished-rams)

**One document, two parts, linked by step number.** It only works when the crew is told what it says and the work is done as written.

Duct trench across the car park verge

- **Where**: Car park verge, from the building to the footpath, about 15 m
- **Work**: Dig a shallow trench, lay an empty duct, backfill
- **Known**: A low-voltage cable crosses the route on the owner’s plan
- **Nearby**: Public footpath at the east end
- **Plant**: Mini excavator, hand tools, plate compactor

### Method statement

1. **Get the service information first** Get the current plans from each service owner. Keep them with the RAMS.
2. **Survey and mark the whole area** A competent person sweeps the whole route with a locator and signal generator. They mark every indication where the dig team will see it.
3. **Barrier the open excavation** Barrier the route and the footpath end before the first bucket. Set out the dig against the marks.
4. **Dig to the marks, by hand near services** Excavator away from the marks. Hand dig where the cable is marked until it is exposed. Spoil set back from the edge.
5. **Record the as-laid route** Lay and join the duct to the drawing, clear of the cable. Record the route, ends and depth before it is covered.
6. **Get the excavation released** Inspect and record before anything goes back in. Bed and cover the duct and cable by hand, then fill and compact in layers.

### Risk assessment

| Step | Hazard | Who | Controls |
| --- | --- | --- | --- |
| 1 | Striking an unrecorded cable, gas pipe or water main | The locating team and the people who dig next | - Contact the service owners before intrusive work. - Treat missing records as an unresolved risk. |
| 2 | A service route being missed, misread or not passed to the digging team | The locating team and anyone working near the marks | - Survey before the work is planned and set out. - Record areas that could not be scanned. |
| 3 | A person falling into the open excavation | The dig team, other trades and people passing | - Check the barrier after work or weather changes. - Do not leave an open excavation unprotected. |
| 4 | Hitting a buried cable or gas pipe causes shock, burns or a gas escape | The person doing the work and everyone nearby | - Use hand exposure where the planned work is near an assumed service. |
| A moving excavator striking or trapping a person | The operator, dig team and people passing | - Keep pedestrians out of the operating area. - Stop the machine before anyone enters its working area. |  |
| 5 | A duct being lost or installed differently from the record | The duct team and whoever uses the duct later | - Record what was actually laid, not just the design. - Keep the handover record with the job file. |
| 6 | Burying faulty work or losing the evidence needed to repair it | The backfill team and the service owner | - Use this job’s release arrangement. - Keep the inspection record with the RAMS. |

### Briefed to

| Name | Signature | Date |
| --- | --- | --- |
|  |  |  |
|  |  |  |
|  |  |  |

### What the law asks

- Employers must assess the risks to their employees and to anyone else affected by the work. With five or more employees they must record the significant findings. [Regulation 3](https://www.legislation.gov.uk/uksi/1999/3242/regulation/3)
- Contractors must plan, manage and monitor their work, and give workers the information and instructions they need. [CDM 2015, regulation 15](https://www.legislation.gov.uk/uksi/2015/51/regulation/15)
- For most work a method statement is not required by law. HSE calls it an effective way to plan, manage and monitor the work and to give employees information. [HSE](https://www.hse.gov.uk/construction/safetytopics/admin.htm)

Writing it down is one part. The crew has to be told what it says, and the work done as written.

## [Where the first step looks different](https://complyonsite.com/rams/how-to#other-work)

**The rule is the same in every trade.** What has to come first changes with the work.

- ### Electrical work
  Isolate, lock off and prove dead before anyone works on it.
  From [HSE, Electricity at work: safe working practices (HSG85)](https://www.hse.gov.uk/pubns/priced/hsg85.pdf).
  [Write an electrical RAMS](https://complyonsite.com/tools/rams-builder?job=electrical)
- ### Roofing
  Edge protection in place, and fragile surfaces avoided or covered, before anyone goes on the roof.
  From [HSE, Roof work](https://www.hse.gov.uk/construction/safetytopics/roofwork.htm) and [Work at Height Regulations 2005, regulation 9](https://www.legislation.gov.uk/uksi/2005/735/regulation/9).
  [Write a roofing RAMS](https://complyonsite.com/tools/rams-builder?job=roofing)
- ### Hot work
  Combustibles cleared from the area first. A fire watch for at least an hour after, then a later check.
  From [HSE, Fire safety in construction (HSG168)](https://www.hse.gov.uk/pubns/priced/hsg168.pdf).
  [Write a hot work RAMS](https://complyonsite.com/tools/rams-builder?job=hot-works)

## [Check yourself](https://complyonsite.com/rams/how-to#check-yourself)

Five questions. Answer each in your head, then open it.

**A RAMS is headed “Groundworks”. What is missing?**

The place, the work and what is already known about the site. “Groundworks” is a trade, not a job.

**Who could the trench harm who is not on the dig team?**

Someone on the footpath, who could fall into the open excavation.

**Where does finding and marking the services go?**

Before any digging. The dig is set out against the marks.

**Why is “Take care near services” not a control?**

Nobody can do it. A control says who does what, so you can tell whether it was done.

**The RAMS is signed but the crew has not been told what it says. Is the work planned?**

Not yet. The people doing the work must be given the information on the risks and the controls.

## Write the RAMS for this trench

The builder opens on groundworks. Choose the parts of this job and it suggests the same steps, hazards and controls, in this order.

[Open the RAMS builder on this job](https://complyonsite.com/tools/rams-builder?job=groundworks) [Start from your own job](https://complyonsite.com/tools/rams-builder)

## Sources

- [HSE, Steps needed to manage risk](https://www.hse.gov.uk/simple-health-safety/risk/steps-needed-to-manage-risk.htm)
- [HSE, Construction administration: method statements](https://www.hse.gov.uk/construction/safetytopics/admin.htm)
- [Management of Health and Safety at Work Regulations 1999, regulation 3](https://www.legislation.gov.uk/uksi/1999/3242/regulation/3)
- [Management of Health and Safety at Work Regulations 1999, regulation 10](https://www.legislation.gov.uk/uksi/1999/3242/regulation/10)
- [Construction (Design and Management) Regulations 2015, regulation 15](https://www.legislation.gov.uk/uksi/2015/51/regulation/15)
- [HSE, Avoiding danger from underground services (HSG47)](https://www.hse.gov.uk/pubns/priced/hsg47.pdf)
- [HSE, Excavations](https://www.hse.gov.uk/construction/safetytopics/excavations.htm)
- [HSE, Electricity at work: safe working practices (HSG85)](https://www.hse.gov.uk/pubns/priced/hsg85.pdf)
- [HSE, Roof work](https://www.hse.gov.uk/construction/safetytopics/roofwork.htm)
- [Work at Height Regulations 2005, regulation 9](https://www.legislation.gov.uk/uksi/2005/735/regulation/9)
- [HSE, Fire safety in construction (HSG168)](https://www.hse.gov.uk/pubns/priced/hsg168.pdf)

Checked against HSE’s pages and legislation.gov.uk on 15 November 2026.