Temporary site services risk assessment and method statement

## RAMS review

[Check a RAMS](https://complyonsite.com/tools/rams-review)

![A RAMS page with passages highlighted and numbered review comments beside them](https://complyonsite.com/art/rams-review-highlight.webp)

## Temporary site services RAMS template

A blank temporary site services RAMS to fill in: job details, method statement, risk assessment and briefing record.

Risk assessment and method statement

Temporary site services RAMS

- **Company**: left blank to fill in
- **Site and work area**: left blank to fill in
- **Planned dates**: left blank to fill in
- **In charge on site**: left blank to fill in
- **Team**: left blank to fill in

Method statement

1. 1
2. 2
3. 3
4. 4
5. 5
6. 6

Risk assessment

| Hazard | Who might be harmed and how | Controls in place | Further action |
| --- | --- | --- | --- |
|  |  |  |  |
|  |  |  |  |
|  |  |  |  |
|  |  |  |  |

[Download the templatePDF, 4 pages](https://complyonsite.com/rams/samples/temporary-site-services-rams-template.pdf)

## Temporary site services RAMS example

The same RAMS, filled in for one job.

Risk assessment and method statement

Temporary site services, Ground and first floor, 14 Mill Street, Stockport: refurbishment site

Risk assessment

- People entering the work area or tripping over materials
  Workers, occupants and visitors
  Mark or barrier the active work area. Store tools and materials away from access routes.
- Electric shock, fire or a failed temporary supply
  Electrical workers and everyone on site
  Keep electrical work with the competent contractor. Do not improvise a temporary board or connection.
- An overloaded circuit overheats, trips or starts a fire
  Everyone using or near the temporary supply
  Do not add equipment beyond the agreed load. Stop and get the contractor to check any new load.
- A live source is connected, altered or removed without safe isolation
  The electrical contractor and everyone nearby
  Keep the isolation point accessible and labelled. Do not connect an unidentified source or generator.
- Breathing asbestos fibres from old boards, sheets or lagging you drill into
  The installer and everyone using the building
  Do not cut, drill or break any material until it is confirmed asbestos free. Licensed work is not for this method; hand it to a licensed contractor.
- Hitting a live cable or gas pipe causes shock, fire or gas escape
  The person doing the work and everyone nearby
  Check again wherever the work moves. If you hit something, stop, keep clear and report it.
- Electric shock or fire from a fault in the temporary supply
  Workers using the service and people nearby
  Test and inspect the protection as required before use. Take damaged leads, plugs and sockets out of service.
- Cable damage, trips, electric shock or fire
  Workers, drivers and visitors
  Protect every crossing and keep connections off wet ground. Inspect cables after plant, vehicles or materials move nearby.
- Carbon monoxide poisoning, fire or fuel spill from a generator
  Workers, visitors and people in nearby buildings
  Keep fuel in suitable labelled containers away from ignition sources. Stop the generator and report leaks, fumes or a blocked exhaust.
- A damaged or leaking temporary service stays in use and injures people
  Everyone using or near the temporary services
  Repeat the check after moving equipment, severe weather or a change to the service. Keep access to isolation points clear at all times.
- Electric shock from a fault or damaged temporary supply
  Workers using site equipment and people nearby
  Test and inspect the protection as required. Take damaged leads, plugs and sockets out of use.
- Trips, falls or contact with tools in poor light
  Everyone on site
  Remove failed lights promptly. Check the lighting at the start of each shift and after moving it.
- Falls or delayed escape after the primary lighting fails
  Workers and visitors using the route
  Keep the emergency route clear and marked. Do not rely on a light that has not been tested.
- Debris, tools or unfinished work left in the area
  Workers, occupants and visitors
  Remove waste by the agreed route. Record and protect any unfinished work.

Temporary site services, Ground and first floor, 14 Mill Street, Stockport: refurbishment site

- **Company**: Hollins & Reed Contracting Ltd
- **Site and work area**: Ground and first floor, 14 Mill Street, Stockport: refurbishment site
- **Planned dates**: 12 to 14 October 2026
- **In charge on site**: Dan Hollins
- **Team**: Two operatives: Dan Hollins leads and checks the generator, board, cables and lights each morning; Priya Shah works with him. The electrical contractor installs and removes the temporary board.

Method statement

1. 1 Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active work area. Keep entrances and escape routes clear.
2. 2 Use a competent electrical contractorHave a competent electrical contractor design, install, maintain and remove the temporary distribution. Keep permanent installation work outside this temporary-services method.
3. 3 Match the supply to the loadsList the tools, cabins, welfare equipment and lights that the temporary supply will feed. Check the board, cables and protection are rated for the connected loads before use.
4. 4 Confirm the source and isolation pointMark the source and isolation point before connecting the temporary cables. The contractor proves the supply is isolated before altering or removing any connection.
5. 5 Check for asbestos before you drill or fixIn a building put up or done up before 2000, ask for the asbestos survey before you drill, chase or clip anything. Read what it says about the ceilings, risers, ducts and boarding your cables or pipes run through. No survey, or a board you do not recognise: stop and get it checked.
6. 6 Find and isolate hidden servicesFind cables and pipes before you disturb anything: drawings, then a detector. Mark what you find. Not sure what is there? Turn the supply off, or do not start. Have cables and gas isolated by the right person and prove them dead before you start.
7. 7 Use 110 V and RCD protectionUse 110 V centre-tapped supplies and RCD protection for temporary site equipment. Keep the board dry, guarded and easy to isolate.
8. 8 Route and protect temporary cablesRoute cables overhead or under suitable ramps so vehicles, water and sharp edges cannot damage them. Keep cables out of work areas, access routes and escape routes.
9. 9 Control generator fuel and fumesPlace generators in a ventilated position with exhaust fumes away from people, doors and air intakes. Store and handle fuel safely, and never refuel a hot or running generator.
10. 10 Complete daily temporary-service checksAt the start of each shift check cables, sockets, lights, generator fumes, hoses, tanks and drains. Record defects, isolate unsafe equipment and report repairs before the service is used.
11. 11 Use protected site socketsUse the specified temporary board and RCD-protected sockets for site equipment. Keep boards and connections dry, guarded and accessible for isolation.
12. 12 Light work areas and routesProvide artificial lighting where natural light is not enough for work or movement. Keep work areas, access routes and escape routes lit while they are in use.
13. 13 Provide emergency lightingProvide emergency lighting where a failed primary light could make work or an escape route unsafe. Test it before the route is used and after changes to the temporary supply.
14. 14 Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell the customer or whoever runs the site when the work is complete.

[Download the examplePDF, 4 pages](https://complyonsite.com/rams/samples/temporary-site-services-rams-example.pdf)

## What a temporary site services RAMS covers

110 V supply, lighting, generators, temporary water and drainage for the length of the job. Not covered: the permanent electrical installation.

- Temporary electrical and lighting
- Temporary water and drainage

## Suggested steps and hazards for temporary site services

Suggested for temporary electrical and lighting before any questions are answered.

1. ### Use a competent electrical contractor
   - Have a competent electrical contractor design, install, maintain and remove the temporary distribution.
   - Keep permanent installation work outside this temporary-services method.
   Hazard
   Electric shock, fire or a failed temporary supply
   Who might be harmed and how
   Electrical workers and everyone on site
   Controls in place
   - Keep electrical work with the competent contractor.
   - Do not improvise a temporary board or connection.
   Temporary distribution needs electrical competence from setup through removal.
   [Electrical safety on construction sites](https://www.hse.gov.uk/pubns/priced/hsg141.pdf)
2. ### Check for asbestos before you drill or fix
   - In a building put up or done up before 2000, ask for the asbestos survey before you drill, chase or clip anything.
   - Read what it says about the ceilings, risers, ducts and boarding your cables or pipes run through.
   - No survey, or a board you do not recognise: stop and get it checked.
   Hazard
   Breathing asbestos fibres from old boards, sheets or lagging you drill into
   Who might be harmed and how
   The installer and everyone using the building
   Controls in place
   - Do not cut, drill or break any material until it is confirmed asbestos free.
   - Licensed work is not for this method; hand it to a licensed contractor.
   Temporary services get run through the old ceilings and risers where asbestos board is left.
   [HSE: The duty to manage asbestos in buildings: Arrange an asbestos survey](https://www.hse.gov.uk/asbestos/duty/arrange-asbestos-survey.htm)
3. ### Use 110 V and RCD protection
   - Use 110 V centre-tapped supplies and RCD protection for temporary site equipment.
   - Keep the board dry, guarded and easy to isolate.
   Hazard
   Electric shock or fire from a fault in the temporary supply
   Who might be harmed and how
   Workers using the service and people nearby
   Controls in place
   - Test and inspect the protection as required before use.
   - Take damaged leads, plugs and sockets out of service.
   Reduced voltage and RCD protection limit the harm from a temporary electrical fault.
   [Electrical safety on construction sites](https://www.hse.gov.uk/pubns/priced/hsg141.pdf)

## What the builder asks about temporary site services

Your answers decide which steps, hazards and controls it suggests.

The job

- What will this supply power?
- What water is needed?

Where

- Where will the power come from?
- Where will wastewater go?
- What happens if normal lighting fails?
- What pipes or cables run where you will fix or run the temporary services?

How it’s done

- What will you stand on to reach the work?
- Could the water supply stand unused?

## What your temporary site services RAMS includes

### Method statement

The work in order, step by step.

### Risk assessment

Each hazard, who could be harmed, the controls in place and any further action.

### PDF

The method statement and risk assessment in one A4 PDF. Your logo on Pro and Team.

- ### [Strip out RAMS](https://complyonsite.com/tools/rams-builder?job=strip-out)
- ### [Temporary works RAMS](https://complyonsite.com/tools/rams-builder?job=temporary-works)
- ### [Manual handling RAMS](https://complyonsite.com/tools/rams-builder?job=manual-handling)
- ### [Loading and unloading RAMS](https://complyonsite.com/tools/rams-builder?job=loading-and-unloading)
- ### [Lifting RAMS](https://complyonsite.com/tools/rams-builder?job=lifting)
- ### [Crane lifting RAMS](https://complyonsite.com/tools/rams-builder?job=crane-lifting)
- [All trades and tasks](https://complyonsite.com/tools/rams-builder)

## What the law asks for

### What a RAMS is

A risk assessment and method statement. The risk assessment records what could cause harm on the job, who could be harmed and how, and the controls that keep the risk down. The method statement sets out how the work will be done, step by step, in the order it happens.

A client or main contractor will usually ask for one before you start. RAMS is a site term, not a legal one: the law asks for the risk assessment and for the work to be planned, and a method statement is the usual way to show that plan for one job.

### What the law asks for

- Employers, and self-employed people doing construction work, must make a suitable and sufficient assessment of the risks to their own people and to anyone else affected by the work ([Management of Health and Safety at Work Regulations 1999, regulation 3](https://www.legislation.gov.uk/uksi/1999/3242/regulation/3)).
- An employer with five or more employees must record the significant findings and any group of employees it finds especially at risk. The assessment must be reviewed if there is reason to think it is no longer valid, or the work has changed significantly.
- Every contractor must plan, manage and monitor its work so that, so far as is reasonably practicable, it is done without risks to health and safety, and must give its workers the information and instructions they need, including the hazards the risk assessment found ([Construction (Design and Management) Regulations 2015, regulation 15](https://www.legislation.gov.uk/uksi/2015/51/regulation/15)).

HSE guidance: [the steps to manage risk](https://www.hse.gov.uk/simple-health-safety/risk/steps-needed-to-manage-risk.htm) and [what contractors must do under CDM](https://www.hse.gov.uk/construction/cdm/2015/contractors.htm). This is the law in Great Britain; Northern Ireland has its own equivalent regulations.

### What the builder does

You choose the work and answer questions about how the job will be done, such as what you will stand on and what else is going on nearby. Your answers decide which steps, hazards and controls it suggests.

Many suggestions link to the HSE guidance they draw on. Your work is kept in this browser and, signed in, on your account with its photos; the PDF is made on your device. A briefing you send to phones goes through your account.

### Separate documents

A COSHH assessment, lifting plan, permit to work, asbestos survey and the principal contractor’s construction phase plan are separate from the RAMS.