| 1 | Striking an unrecorded cable, gas pipe or water main | The locating team and the people who dig next | - Contact the service owners before intrusive work.
- Treat missing records as an unresolved risk.
|
|---|
| 2 | A service route being missed, misread or not passed to the digging team | The locating team and anyone working near the marks | - Survey before the work is planned and set out.
- Record areas that could not be scanned.
|
|---|
| 3 | A person falling into the open excavation | The dig team, other trades and people passing | - Check the barrier after work or weather changes.
- Do not leave an open excavation unprotected.
|
|---|
| 4 | Hitting a buried cable or gas pipe causes shock, burns or a gas escape | The person doing the work and everyone nearby | - Use hand exposure where the planned work is near an assumed service.
|
|---|
| A moving excavator striking or trapping a person | The operator, dig team and people passing | - Keep pedestrians out of the operating area.
- Stop the machine before anyone enters its working area.
|
| 5 | A duct being lost or installed differently from the record | The duct team and whoever uses the duct later | - Record what was actually laid, not just the design.
- Keep the handover record with the job file.
|
|---|
| 6 | Burying faulty work or losing the evidence needed to repair it | The backfill team and the service owner | - Use this job’s release arrangement.
- Keep the inspection record with the RAMS.
|
|---|