How to write a RAMS

Write the job down in the order it will be done. Beside each step, who it could harm and how. Put each control before the work it protects.

One job, a duct trench across a car park verge, in six stages. Step through them to see each one written in the method statement and the risk assessment.

The trench job at stage 1, get the plans.Owner’s planPaint marksLocatorSignal generatorBarrierFootpathMini excavatorHand digLow-voltage cableEmpty ductCovered by handPlate compactorFilled in layersReleased

Method statement, step 1

Get the service information first

Get the current plans from each service owner. Keep them with the RAMS.

Risk assessment, step 1

Hazard
Striking an unrecorded cable, gas pipe or water main
Who
The locating team and the people who dig next
Controls
  • Contact the service owners before intrusive work.
  • Treat missing records as an unresolved risk.

Method statement

  1. Get the service information first Get the current plans from each service owner. Keep them with the RAMS.
  2. Survey and mark the whole area A competent person sweeps the whole route with a locator and signal generator. They mark every indication where the dig team will see it.
  3. Barrier the open excavation Barrier the route and the footpath end before the first bucket. Set out the dig against the marks.
  4. Dig to the marks, by hand near services Excavator away from the marks. Hand dig where the cable is marked until it is exposed. Spoil set back from the edge.
  5. Record the as-laid route Lay and join the duct to the drawing, clear of the cable. Record the route, ends and depth before it is covered.
  6. Get the excavation released Inspect and record before anything goes back in. Bed and cover the duct and cable by hand, then fill and compact in layers.

Risk assessment

StepHazardWhoControls
1Striking an unrecorded cable, gas pipe or water mainThe locating team and the people who dig next
  • Contact the service owners before intrusive work.
  • Treat missing records as an unresolved risk.
2A service route being missed, misread or not passed to the digging teamThe locating team and anyone working near the marks
  • Survey before the work is planned and set out.
  • Record areas that could not be scanned.
3A person falling into the open excavationThe dig team, other trades and people passing
  • Check the barrier after work or weather changes.
  • Do not leave an open excavation unprotected.
4Hitting a buried cable or gas pipe causes shock, burns or a gas escapeThe person doing the work and everyone nearby
  • Use hand exposure where the planned work is near an assumed service.
A moving excavator striking or trapping a personThe operator, dig team and people passing
  • Keep pedestrians out of the operating area.
  • Stop the machine before anyone enters its working area.
5A duct being lost or installed differently from the recordThe duct team and whoever uses the duct later
  • Record what was actually laid, not just the design.
  • Keep the handover record with the job file.
6Burying faulty work or losing the evidence needed to repair itThe backfill team and the service owner
  • Use this job’s release arrangement.
  • Keep the inspection record with the RAMS.

Say exactly which job it covers

“Groundworks” is a trade, not a job. Name the place, the work and what is already known about the site.

Groundworks RAMS

Where
Not said
Work
Not said
Known
Not said
Nearby
Not said
Plant
Not said

Duct trench across the car park verge

Where
Car park verge, from the building to the footpath, about 15 m
Work
Dig a shallow trench, lay an empty duct, backfill
Known
A low-voltage cable crosses the route on the owner’s plan
Nearby
Public footpath at the east end
Plant
Mini excavator, hand tools, plate compactor

Then list the stages in the order they happen, as in the six above.

Name who each stage could harm, and how

Write who could be hurt and how before any controls. Not only your own team. Here is the dig.

The dig, with the person hand digging ringed.Owner’s planPaint marksLocatorSignal generatorBarrierFootpathMini excavatorHand digLow-voltage cableEmpty ductCovered by handPlate compactorFilled in layersReleasedIn the trench

From HSE, Steps needed to manage risk and Management of Health and Safety at Work Regulations 1999, regulation 3.

Put each control before the work it protects

A control is a step someone does, placed before the work it protects. “Take care” cannot go anywhere in the order, because nobody can do it.

The trench job before work starts.Owner’s planPaint marksLocatorSignal generatorBarrierFootpathMini excavatorHand digLow-voltage cableEmpty ductCovered by handPlate compactorFilled in layersReleased

This draft came back from site. Play it and stop where something has to happen first.

  1. Get the service plans
  2. Dig the trench
  3. Lay and join the duct
  4. Backfill and compact

The order, corrected

  1. Survey and mark the whole area before digging the trenchThe dig is set out against the marks, so the marks have to exist first.
  2. Barrier the open excavation before digging the trenchThe hole is open from the first bucket, so the barrier goes up before it.
  3. Get the excavation released before backfilling and compactingOnce it is buried nobody can check it, so the release comes before the fill.
  4. Bed and cover the duct and cable by hand before backfilling and compactingThe cover protects the services from the fill and the plate, so it goes in by hand first.

From HSE, Avoiding danger from underground services (HSG47) and HSE, Excavations.

The finished RAMS

One document, two parts, linked by step number. It only works when the crew is told what it says and the work is done as written.

Duct trench across the car park verge

Where
Car park verge, from the building to the footpath, about 15 m
Work
Dig a shallow trench, lay an empty duct, backfill
Known
A low-voltage cable crosses the route on the owner’s plan
Nearby
Public footpath at the east end
Plant
Mini excavator, hand tools, plate compactor

Method statement

  1. Get the service information first Get the current plans from each service owner. Keep them with the RAMS.
  2. Survey and mark the whole area A competent person sweeps the whole route with a locator and signal generator. They mark every indication where the dig team will see it.
  3. Barrier the open excavation Barrier the route and the footpath end before the first bucket. Set out the dig against the marks.
  4. Dig to the marks, by hand near services Excavator away from the marks. Hand dig where the cable is marked until it is exposed. Spoil set back from the edge.
  5. Record the as-laid route Lay and join the duct to the drawing, clear of the cable. Record the route, ends and depth before it is covered.
  6. Get the excavation released Inspect and record before anything goes back in. Bed and cover the duct and cable by hand, then fill and compact in layers.

Risk assessment

StepHazardWhoControls
1Striking an unrecorded cable, gas pipe or water mainThe locating team and the people who dig next
  • Contact the service owners before intrusive work.
  • Treat missing records as an unresolved risk.
2A service route being missed, misread or not passed to the digging teamThe locating team and anyone working near the marks
  • Survey before the work is planned and set out.
  • Record areas that could not be scanned.
3A person falling into the open excavationThe dig team, other trades and people passing
  • Check the barrier after work or weather changes.
  • Do not leave an open excavation unprotected.
4Hitting a buried cable or gas pipe causes shock, burns or a gas escapeThe person doing the work and everyone nearby
  • Use hand exposure where the planned work is near an assumed service.
A moving excavator striking or trapping a personThe operator, dig team and people passing
  • Keep pedestrians out of the operating area.
  • Stop the machine before anyone enters its working area.
5A duct being lost or installed differently from the recordThe duct team and whoever uses the duct later
  • Record what was actually laid, not just the design.
  • Keep the handover record with the job file.
6Burying faulty work or losing the evidence needed to repair itThe backfill team and the service owner
  • Use this job’s release arrangement.
  • Keep the inspection record with the RAMS.

Briefed to

NameSignatureDate

What the law asks

  • Employers must assess the risks to their employees and to anyone else affected by the work. With five or more employees they must record the significant findings. Regulation 3
  • Contractors must plan, manage and monitor their work, and give workers the information and instructions they need. CDM 2015, regulation 15
  • For most work a method statement is not required by law. HSE calls it an effective way to plan, manage and monitor the work and to give employees information. HSE

Writing it down is one part. The crew has to be told what it says, and the work done as written.

Where the first step looks different

The rule is the same in every trade. What has to come first changes with the work.

Check yourself

Five questions. Answer each in your head, then open it.

A RAMS is headed “Groundworks”. What is missing?

The place, the work and what is already known about the site. “Groundworks” is a trade, not a job.

Who could the trench harm who is not on the dig team?

Someone on the footpath, who could fall into the open excavation.

Where does finding and marking the services go?

Before any digging. The dig is set out against the marks.

Why is “Take care near services” not a control?

Nobody can do it. A control says who does what, so you can tell whether it was done.

The RAMS is signed but the crew has not been told what it says. Is the work planned?

Not yet. The people doing the work must be given the information on the risks and the controls.

Write the RAMS for this trench

The builder opens on groundworks. Choose the parts of this job and it suggests the same steps, hazards and controls, in this order.