Construction progress report

A report for the client or the office, for any dates. Type it, or fill it from your diary days and edit.

Example

Progress report

12 to 16 October 2026

Example project

BehindPrepared by Sam Sample, Supervisor · 16/10/2026

Summary

Block A first-floor slab poured on Friday. Two days behind on the scaffold to the north elevation.

Work done this period

Wed 14/10

Formwork to Block A first floor

Rebar fixed to grid lines 1 to 4

Fri 16/10

Block A: first-floor slab poured, 42 m³

External works: drainage laid from manhole 3 to manhole 4

Delays and problems

1Scaffold tie missing at gable end. Example Scaffolding. 15/10: Pat Placeholder to refix Friday

3Revised bracket detail still to come. Client.

Help needed from the client

Revised bracket detail, by 21/10

Weather

Wed 14/10: dry

Fri 16/10: light rain, strong wind

Photos

Fri 16/10 · Block A first-floor slab
Fri 16/10 · Drainage, manhole 3 to 4
Site Progress Report on a phone for 12 to 14 October 2026. Filled from 3 diary days, status Behind, and the summary and work done sections with their first lines.

A weekly progress report, filled from your diary

Pick the dates and tap Fill from the days. Work done, weather, labour and next steps come in under anything you typed.

The first page of a progress report PDF for 12 to 14 October 2026. Status Behind, summary, work done by day, delays and problems by issue number, weather, next period and labour on site.

A construction progress report the client can read

Send makes the PDF and copies the email text, ready to paste. Earlier reports keep the PDF exactly as it was sent.

Download a sample progress report (PDF, 2 pages)

Progress report questions

Is it free?

Yes. The report, the PDF and the email text are free, with or without an account.

Do I need the site diary?

No. Type the report yourself. With a site diary kept for the same project, Fill from the days writes the first draft.

Will filling it again write over my words?

No. Filling adds what the diary days have under what you typed. Nothing you wrote is changed.

Can I write a monthly report?

Yes. Pick This month, or Other dates for any start and end date.

Is a progress report a legal requirement?

Usually the contract or the client asks for it. Where there is a principal contractor, CDM 2015 regulation 13 says they must plan, manage and monitor the construction phase, and the diary days behind the report are part of that record.

Where do the delays come from?

From Site Issues. Each issue is listed by its number, and days with rain or wind are offered for you to add.