Progress report
12 to 16 October 2026
Example project
Summary
Block A first-floor slab poured on Friday. Two days behind on the scaffold to the north elevation.
Work done this period
Wed 14/10
Formwork to Block A first floor
Rebar fixed to grid lines 1 to 4
Fri 16/10
Block A: first-floor slab poured, 42 m³
External works: drainage laid from manhole 3 to manhole 4
Delays and problems
1Scaffold tie missing at gable end. Example Scaffolding. 15/10: Pat Placeholder to refix Friday
3Revised bracket detail still to come. Client.
Help needed from the client
Revised bracket detail, by 21/10
Weather
Wed 14/10: dry
Fri 16/10: light rain, strong wind