Welding hot work permit example
Completed permits for common jobs: both sheets, filled in and cancelled. Read one, download it, then issue your own from the blank.
Get the blankChoose a permit
- Torch-on felt on a flat roofA propane torch on the roof of an occupied office, with a fire watch to the two-hour check.2 pages, checked 2 November 2026
- Welding a steel beam in a basementMIG welding during a refurbishment, with fume extraction and the office above checked too.2 pages, checked 2 November 2026
- A new drain in a yard, near live servicesHand digging near a cable and a gas pipe, over two days, with inspections after rain.2 pages, checked 2 November 2026
- Entering a foul manhole to join a drainTwo people in a 2.4 m manhole, with gas tests, a top person and a winch at the surface.2 pages, checked 2 November 2026
- A night fit-out in a bank branchA shopfitting team replacing a reception desk and two partitions after closing, with one intruder alarm zone off and security on site.2 pages, checked 2 November 2026
- A roof survey behind a barrierA surveyor and an assistant on a large flat felt roof with roof lights and an open edge, inside a barrier set and struck on the same permit, with wind readings throughout.2 pages, checked 2 November 2026
- Changing a sub-main boardA board with two incomers and a generator inlet, with both firms locked on through a lock-out box, proved dead before the permit was issued.2 pages, checked 2 November 2026
Welding hot work permit example
Welding a steel beam in a basement
MIG welding during a refurbishment, with fume extraction and the office above checked too.
What to change
- Your site and exact location
- The precautions that do not apply, and why
- Who issues it and who accepts it
Sources
Checked
The same sheet as text
Worked example of a made-up job. Not a permit.
Sheet 1: Hot Work Permit
Hollins & Reed Contracting Ltd
- Permit no.HR-0418
- SiteUnit 3, Canal Side Business Park
- Exact locationBasement, beam at grid line C4
Details
- ContractorHollins & Reed
- Issued toPriya Shah
- Valid from13/10/26 08:00
- Valid to13/10/26 17:00
- RAMS refHR-RAMS-08
- Fire risk refHR-FRA-03
The work
- Hot work to be doneWeld two stiffener plates to the existing steel beam, to the engineer’s drawing S-04.
- MethodOld bracket ground off. MIG welding with argon-mix gas. One welder, one fire watcher.
- Why cold methods failThe drawing calls for welded plates. Bolts need holes the flange cannot take.
Hazards
- Combustibles in 10 mYes
- Openings and voidsYes
- Flammables nearbyNo
- Dust or lintNo
- Roof or wall liningsNo
- Below, behind wallsYes
- Sprinklers, alarmsYes
- Occupied buildingYes
Precautions
- Combustibles removed or coveredDone: yes. By: Reece Ollerton
- Floors swept, combustible floors coveredDone: yes. By: Reece Ollerton
- Openings and voids sealedDone: yes. By: Reece Ollerton
- Non-combustible screens upDone: yes. By: Reece Ollerton
- Detectors isolated: who restores themDone: yes. By: Dan Hollins, zone 1 only
- Gas cylinders secured and checkedDone: yes. By: Priya Shah
- Two extinguishers within reach: typeDone: yes. By: CO2 and dry powder
- Fire watcher named, breaks coveredDone: yes. By: Reece Ollerton
- How to raise the alarmDone: yes. By: Break glass, ring 999
- Hot work ends 2 hours before day endDone: yes
- Others shielded from arc and sparksDone: yes. By: Priya Shah, screens
- Fume: LEV or RPEDone: yes. By: LEV and RPE, both
- Permit shown at the workDone: yes
Equipment
- ExtinguishersYes
- Fire blanketYes
- Hose reelNo
- Gas detectorNo
- Thermal cameraYes
- Welding screensYes
Other conditions
- No flammable gas below ground. Extraction at the weld, ducted outside. Welder wears RPE as well.
- Riser boarded. Watcher checks the office above and behind the riser wall. Site office 0161 496 0142.
Sign-off
- Issued: precautions checkedName: Dan Hollins. Signature: signed. Date: 13/10/26. Time: 07:50
- Accepted: permit understoodName: Priya Shah. Signature: signed. Date: 13/10/26. Time: 07:55
Sheet 2: Hot Work Permit
Hollins & Reed Contracting Ltd
- Permit no.HR-0418
- SiteUnit 3, Canal Side Business Park
- Exact locationBasement, beam at grid line C4
Fire watch: continuous for 1 hour, then a check at 2 hours
- During breaksTime: 12:00 to 12:30. By: Reece Ollerton. Result: Stopped for the break. Watched basement and riser. Nothing found.
- End of hot workTime: 14:30. By: Reece Ollerton. Result: Welding finished. Continuous watch started.
- 1 hour after the endTime: 15:30. By: Reece Ollerton. Result: Watch kept the whole hour. Office above and riser checked.
- 2 hours after the endTime: 16:30. By: Dan Hollins. Result: Basement, riser and office above checked. Nothing found.
Cancellation
- Work stopped at14:30 on 13 October. Plates welded.
- Area checked, images keptWalked at 16:30. Two thermal images of the riser in the job file.
- Detectors restored byDan Hollins. Back on 12:00, off again 12:30, back on 14:35. Panel normal.
- Equipment removedWelder, cylinder and screens out by 15:00. Riser boards stay.
Handback
- Area returned toDan Hollins, for the next trade
- NotesWelds to be inspected by the engineer. Not part of this permit.
Sign-off
- Extended: new end timeName: Not extended
- Cancelled: area checkedName: Dan Hollins. Signature: signed. Date: 13/10/26. Time: 16:35
- Handed back: area returnedName: Dan Hollins. Signature: signed. Date: 13/10/26. Time: 16:40
What a completed permit shows
- Who issued it and who accepted
- What was checked first, and what did not apply
- The record while it ran (fire watch, gas tests, inspections)
- How it was cancelled and handed back
Two ways to run your permits
Keep the day’s record
Note each permit issued and cancelled in Site Diary, with photos of the area.
Open Site DiaryPermit to work example questions
Are these real permits?
No. Every job, company, person and address here is made up, and so is every reading. They show what goes in each box.
Can I issue one of these as it is?
No. A permit is written for one job, one place, one time. Issue your own from the blank, after checking the place yourself.
What makes a permit invalid?
It covers only the job, the place and the time written on it. If the time runs out or the work changes, stop, then extend it or issue a new one once it is checked as safe. HSE: HSG250.
How long does a hot work fire watch last?
At least an hour of continuous watching after the hot work ends, then at least one more check two hours after the end. HSE: HSG168.
Where is the blank?
On the permit to work template page. Add your logo, then print it or download it.