Electrical RAMS example Worked examples for common jobs, written with our builder. Read, download, adapt.
Build your own Choose a job Search jobs All Electrical Plumbing and ventilation Painting Roofing Groundworks and landscaping Carpentry and glazing Interiors Brickwork Access and lifting Demolition and strip out Welding Cleaning
Electrical second fix and testing in a house refurbishment Lived-in 1970s house, accessories and consumer unit fitted, one circuit dead at a time, tested dead then live before handover. 7 pages, checked 2 November 2026 Hot works: cutting and welding in an occupied warehouse Steel brackets cut out and replaced on a live bay, with a permit for each shift and a separate fire watcher. 7 pages, checked 2 November 2026 Erecting an independent tied scaffold on a two-storey house Independent tube and fitting scaffold to a TG20 compliance sheet, family at home, rescue kit on the wagon. 6 pages, checked 2 November 2026 Stripping and re-tiling a pitched roof from a scaffold Lived-in house, tiles, battens and underlay off, one section made weathertight each day. 8 pages, checked 2 November 2026 Digging a 1.2 m trench for strip footings and a drain Beside a lived-in house, services located first, excavator then hand tools, trench sheets and props before anyone goes in. 7 pages, checked 2 November 2026 Repainting occupied offices Water-based paint from a podium, walls filled and sanded first, one bay screened off at a time while staff work on. 5 pages, checked 2 November 2026 Bathroom first and second fix in a lived-in house Only bathroom replaced, press-fit pipework under the floor and in a duct, tested before anyone closes it up, suite fitted after tiling. 8 pages, checked 2 November 2026 Tarmac resurfacing on a car park that stays partly open Old surface tested and planed off, private retail car park, laid bay block by bay block with shoppers around. 5 pages, checked 2 November 2026 Unloading a builders’ merchant delivery with a lorry loader Packs of blocks and plasterboard landed on a small building site, on a standing lift plan reviewed for this site. 6 pages, checked 2 November 2026 Cleaning the outside of a two-storey office with a water-fed pole All from the ground, in an open office set back behind its own car park, on cold November mornings. 4 pages, checked 2 November 2026 MIG welding a pump frame in a plant room MIG welding bare mild steel at floor level in a closed plant room, with on-torch extraction, while the retail park keeps trading. 5 pages, checked 2 November 2026 Stripping out a vacant single-storey workshop Office ceiling, partitions, carpet and benches out by hand, building empty, every service including the fire alarm disconnected on a certificate, lit by roof lights and a 110 V string. 7 pages, checked 2 November 2026 Skimming and patching walls in an occupied house Ground floor living room of a 2006 house, family at home, plaster mixed in the room with the door shut, from a hop-up. 5 pages, checked 2 November 2026 Building a garden wall in blockwork and facing brick A 5 m long, 1 m high wall, one brick thick, on a foundation already in, laid from the ground. 6 pages, checked 2 November 2026 Core drilling a flue hole through a cavity blockwork wall One 125 mm wet core, rig fixed to the inner leaf, through an external wall of a single-storey extension, with the core caught outside. 5 pages, checked 2 November 2026 Replacing damaged ceiling tiles and grid in an occupied office, out of hours Like-for-like tiles and tees on the existing hangers, from a podium, with the offices empty and the fire alarm left live. 4 pages, checked 2 November 2026 Clearing gutters on a bungalow from a ladder Eight ladder positions of under 15 minutes each, one hand on the ladder, with a stand-off keeping it clear of the gutter. 4 pages, checked 2 November 2026 Laying a block paved patio in a lived-in garden Dug out by hand to 250 mm, sub-base compacted, blocks laid on sand and cut wet, family at home. 6 pages, checked 2 November 2026 Hanging office doors in existing linings, out of hours in a working building Six heavy non-fire meeting room doors, trimmed and routed on trestles after the staff have gone. 4 pages, checked 2 November 2026 Electrical RAMS example Electrical second fix and testing in a house refurbishment
Lived-in 1970s house, accessories and consumer unit fitted, one circuit dead at a time, tested dead then live before handover.
What to change Company, people, site and dates Whether power must stay on for anyone The supply and earthing arrangement Bathrooms and other special locations How it is notified where you are The BS 7671 edition on the certificate Emergency arrangements Sources Checked 2 November 2026
ComplyOnSite complyonsite.com WORKED EXAMPLE: RISK ASSESSMENT AND METHOD STATEMENT Electrical second fix and testing in a house refurbishment Hollins & Reed Electrical Ltd · 12 to 14 October 2026 · In charge: Dan Hollins Worked example. Change it to fit your job before you use it. Job details Company Hollins & Reed Electrical Ltd Site and work area 14 Elm Road, M21 Planned dates 12 to 14 October 2026 Customer Mr and Mrs Shaw In charge on site Dan Hollins Team Two people: Dan Hollins, electrician, leads and tests; Priya Shah, electrician, stays with him for every live test. Work Electrical second fix and testing in a house refurbishment Prepared by Dan Hollins Signature Date Work and boundaries Alter or replace electrical equipment, replace a consumer unit, inspect or test a fixed installation. Areas: Kitchen, hall and lounge circuits; Hall cupboard: consumer unit and meter tails Working arrangement Access: steps or a ladder. Working height: ceiling lights at about 2.4 m. Ground or floor: level timber floors under dust sheets. Other people will be using the area. Mr and Mrs Shaw stay at home; we agree what goes off and when, each morning. Other trades stay off a circuit while it is under test. Tools run on 110 V or battery. Labels are not trusted: each circuit is identified before it is isolated. The asbestos survey covers the old board and the Worked example. Change it to fit your job before you use it. Page 1 of 7 Page 1 of 7
Example: Electrical second fix and testing in a house refurbishment ComplyOnSite textured ceilings. Records: Electrical Installation Certificate with the schedule of test results, and notification through our competent person scheme. Emergency arrangements There is no site alarm and the smoke alarms may be off while we work, so shout “fire”. Get out by the front door and meet at the gate of No. 14. Count Mr and Mrs Shaw and the dog. Electric shock: do not touch the person until the supply is off; main switch at the consumer unit in the hall cupboard. First aider: Priya Shah, kit in the van. Check you have a mobile signal on day one. Priya Shah rings 999, gives 14 Elm Road, M21, and meets the crew at the gate; if she is the one hurt, Dan Hollins does. Problem at the cut-out: ring the network operator on the number on the job sheet. Planned method 1 Set up the work area Confirm the work area and scope before starting. Keep other people outside the active work area. Keep entrances and escape routes clear. 2 Keep people clear of the work Agree how people get past or around the work while it is going on. Put barriers or signs where a route crosses the work. Do not leave open work unattended. 3 List the rooms and circuits to finish List the rooms and circuits you are finishing, on the cables run at first fix. Check the design or product instructions for what you are fitting. 4 Assess the existing installation Check the existing equipment, circuits, earthing and bonding before fitting the new unit. Record any defects, and anything you could not check. 5 Agree the test boundary Write down the circuits to be tested and who tests them. Keep other trades off a circuit while it is under test. 6 Check for asbestos before you disturb anything Check the asbestos survey covers exactly what you will disturb, to the full depth. Register only, or nothing: get a refurbishment survey or a sample first. Read what it says about walls, ceilings, boards and service routes. No survey, or a material you do not recognise: stop and get it checked. 7 Use the ladder or steps Check the ladder or steps before use. Place them on firm, level ground. Keep three points of contact while climbing. Reposition them instead of overreaching. Do not carry loose tools or tins up; hand them up or use a belt. 8 Arrange supply-side isolation Confirm who can isolate the incoming supply before removing the old unit. Treat supply-side conductors as live until that isolation is complete. Worked example. Change it to fit your job before you use it. Page 2 of 7 Page 2 of 7
Example: Electrical second fix and testing in a house refurbishment ComplyOnSite 9 Isolate and prove dead Find every supply that feeds the work, switch it off and lock it off before you open or touch anything. Prove your tester on a known live supply, test every conductor at the work point, then prove the tester again. 10 Keep it locked off while it is open Keep the supply locked off while the item is open, so nobody can put it back on. Test at the work point again before you touch it. 11 Keep dangerous circuits off Review each affected circuit before reconnection. Keep a circuit safely out of service if its defect creates danger. 12 Use suitable test equipment Check the instrument, leads, probes, ratings and settings before connecting. Keep tips and connections controlled at the test points. 13 Label and replace the unit Identify every circuit before disconnection. Install the agreed assembly and reconnect only the circuits in scope. 14 Fix and terminate the sockets, switches and lights Fix the accessories and light fittings, and terminate each one on the cables run at first fix. Check every terminal, protect the cable where it enters each box, and close every enclosure. 15 Inspect the change before it goes live Inspect the completed work and arrange the testing it needs before it goes back on. Record anything left disconnected or out of service. 16 Do dead tests first Apply safe isolation to the agreed circuit boundary and prove it dead before dead tests. Test in this order: continuity of protective conductors and ring finals, insulation resistance, polarity. If one fails, correct it and repeat the tests before it. Protect or disconnect sensitive equipment and record temporary disconnections. 17 Control a justified energised test Complete dead checks first and define the test boundary and precautions. Test live only as far as you need to: Ze, polarity at the origin and RCD operation. Do not work alone. Keep people out while the test is energised, then re-isolate before adjustment. 18 Inspect and test the new unit Complete the inspection and testing the unit needs before it goes back into service. Update the circuit schedule. 19 Record actual results and limits Record readings, defects, tests not completed, temporary disconnections and actions required. The tester decides from the actual results whether it can go back into service. Worked example. Change it to fit your job before you use it. Page 3 of 7 Page 3 of 7
Example: Electrical second fix and testing in a house refurbishment ComplyOnSite 20 Finish the tests and functional checks Complete the required tests and functional checks. Check covers, guards, labels, fire stopping and connections. Give actual results, defects and restrictions to the customer or site contact. Do not certify unchecked work. 21 Issue the certificate Issue the Electrical Installation Certificate and its schedules from the actual results, and give them to the customer with the labels. Notify the work through the scheme or building control where it needs it. 22 Clear and hand back the area Remove tools, waste and unused materials. Check the area is clean and ready to use. Tell the customer or whoever runs the site when the work is complete. Risk assessment Hazard Who might be harmed and how Controls in place People entering the work area or tripping over materials Step 1 Workers, occupants and visitors Mark or barrier the active work area. Store tools and materials away from access routes. People using the building or passing by walking into the work or over what it leaves Step 2 Occupants, visitors, members of the public and workers Keep the barriers and signs up while the work is active. Give people a clear way round where their normal route is blocked. The wrong circuit or an unsuitable accessory causes shock, fire or loss of protection Step 3 Electricians and people in the building Stay inside the agreed scope. Stop for an unexpected arrangement or missing information. A hidden defect or inadequate supply makes the replacement dangerous Step 4 The electrician and householders Use a competent pre-work assessment. Hold the replacement where a safety defect remains unresolved. Someone works on or energises a circuit that is under test Step 5 The tester, other trades and people in the building Check the list of circuits against the design. Record any circuit you could not test. Worked example. Change it to fit your job before you use it. Page 4 of 7 Page 4 of 7
Example: Electrical second fix and testing in a house refurbishment ComplyOnSite Hazard Who might be harmed and how Controls in place Breathing asbestos fibres from old boards, sheets, sealants or insulation Step 6 The team and anyone in the building Do not cut, drill or break any material until it is confirmed asbestos free. Licensed work is not for this method; hand it to a licensed contractor. Falling from the ladder or steps; tools or tins dropped on people below Step 7 The person working from it, if the feet slip or they overreach to one side. Anyone passing or working under the ladder while it is in use. Secure the equipment where it could move. Keep the base and area below clear. Incoming tails remain live when the main switch is off Step 8 The electrician Arrange the authorised supply isolation in advance. Do not remove a supplier seal or improvise the isolation. A live conductor or backfeed causes electric shock, burns or an unexpected start Step 9 The electrician and anyone near the work Lock off the supply and put your own tag on it. Stop if you cannot find every supply or cannot get a dead reading. A live conductor causes electric shock or burns during removal Step 10 The electrician Use the safe isolation steps for this installation. Leave your lock and warning tag on while the work goes on. A known dangerous circuit is energised after the board change Step 11 Householders and anyone using the installation Label every circuit left disconnected. Tell the customer what remains unsafe and why. Unsuitable or wrongly set equipment causes arcing, shock or a false result Step 12 Tester and people near the test Use equipment suited to the actual installation. Do not continue if it is damaged or its rating is unclear. A crossed circuit, wrong device or poor termination causes shock, fire or loss of supply Step 13 The electrician and householders Keep circuit identity through removal and reconnection. Follow the assembly instructions and supplied design. Worked example. Change it to fit your job before you use it. Page 5 of 7 Page 5 of 7
Example: Electrical second fix and testing in a house refurbishment ComplyOnSite Hazard Who might be harmed and how Controls in place A loose, wrong or damaged termination overheats or leaves the installation unsafe Step 14 The electrician and people in the building Use the specified component and termination method. Keep covers, cable restraint and protective connections complete. Unverified work or an incomplete circuit is returned to use Step 15 The electrician and everyone using the installation Do not energise work that has failed verification. Tell the customer or site contact about defects and restrictions. Unexpected voltage or a damaged connected item causes shock, fire or equipment damage Step 16 Tester and anyone near the installation Keep the boundary secured throughout the dead tests. Discharge stored energy where the test requires it. Someone reaches a circuit while it is energised for the test Step 17 Tester, occupants and other trades Use a temporary test area with barriers or supervision. Stop if the safe test arrangement cannot be maintained. Unverified reconnection or missing restrictions misleads the next user Step 18 The electrician and householders Record actual results, defects and circuits left off. Do not invent readings or certification. Copied or invented results hide danger and return an unsafe circuit to use Step 19 Tester, client and future maintainers Write only what was inspected or measured. Keep records with the actual results and restrictions. Incomplete or unverified work is returned to use and leaves people or property unprotected Step 20 The electrician, the customer or site contact and people using the building Record what was tested, what remains out of service and who accepted the hand-back. Do not energise or certify a failed or incomplete installation. The customer has no true record of what was installed and tested Step 21 The customer and future electricians Do not issue a certificate for anything not tested. Write in any circuit left off. Worked example. Change it to fit your job before you use it. Page 6 of 7 Page 6 of 7
Example: Electrical second fix and testing in a house refurbishment ComplyOnSite Hazard Who might be harmed and how Controls in place Debris, tools or unfinished work left in the area Step 22 Workers, occupants and visitors Remove waste by the agreed route. Record and protect any unfinished work. Worked example. Change it to fit your job before you use it. Page 7 of 7 Page 7 of 7
Method statement and risk assessment, side by side Method statement The work in order, step by step.Example: Electrical second fix and testing in a house refurbishment ComplyOnSite textured ceilings. Records: Electrical Installation Certificate with the schedule of test results, and notification through our competent person scheme. Emergency arrangements There is no site alarm and the smoke alarms may be off while we work, so shout “fire”. Get out by the front door and meet at the gate of No. 14. Count Mr and Mrs Shaw and the dog. Electric shock: do not touch the person until the supply is off; main switch at the consumer unit in the hall cupboard. First aider: Priya Shah, kit in the van. Check you have a mobile signal on day one. Priya Shah rings 999, gives 14 Elm Road, M21, and meets the crew at the gate; if she is the one hurt, Dan Hollins does. Problem at the cut-out: ring the network operator on the number on the job sheet. Planned method 1 Set up the work area Confirm the work area and scope before starting. Keep other people outside the active work area. Keep entrances and escape routes clear. 2 Keep people clear of the work Agree how people get past or around the work while it is going on. Put barriers or signs where a route crosses the work. Do not leave open work unattended. 3 List the rooms and circuits to finish List the rooms and circuits you are finishing, on the cables run at first fix. Check the design or product instructions for what you are fitting. 4 Assess the existing installation Check the existing equipment, circuits, earthing and bonding before fitting the new unit. Record any defects, and anything you could not check. 5 Agree the test boundary Write down the circuits to be tested and who tests them. Keep other trades off a circuit while it is under test. 6 Check for asbestos before you disturb anything Check the asbestos survey covers exactly what you will disturb, to the full depth. Register only, or nothing: get a refurbishment survey or a sample first. Read what it says about walls, ceilings, boards and service routes. No survey, or a material you do not recognise: stop and get it checked. 7 Use the ladder or steps Check the ladder or steps before use. Place them on firm, level ground. Keep three points of contact while climbing. Reposition them instead of overreaching. Do not carry loose tools or tins up; hand them up or use a belt. 8 Arrange supply-side isolation Confirm who can isolate the incoming supply before removing the old unit. Treat supply-side conductors as live until that isolation is complete. Worked example. Change it to fit your job before you use it. Page 2 of 7 Risk assessment Each hazard, who could be harmed, the controls in place and any further action.Example: Electrical second fix and testing in a house refurbishment ComplyOnSite 20 Finish the tests and functional checks Complete the required tests and functional checks. Check covers, guards, labels, fire stopping and connections. Give actual results, defects and restrictions to the customer or site contact. Do not certify unchecked work. 21 Issue the certificate Issue the Electrical Installation Certificate and its schedules from the actual results, and give them to the customer with the labels. Notify the work through the scheme or building control where it needs it. 22 Clear and hand back the area Remove tools, waste and unused materials. Check the area is clean and ready to use. Tell the customer or whoever runs the site when the work is complete. Risk assessment Hazard Who might be harmed and how Controls in place People entering the work area or tripping over materials Step 1 Workers, occupants and visitors Mark or barrier the active work area. Store tools and materials away from access routes. People using the building or passing by walking into the work or over what it leaves Step 2 Occupants, visitors, members of the public and workers Keep the barriers and signs up while the work is active. Give people a clear way round where their normal route is blocked. The wrong circuit or an unsuitable accessory causes shock, fire or loss of protection Step 3 Electricians and people in the building Stay inside the agreed scope. Stop for an unexpected arrangement or missing information. A hidden defect or inadequate supply makes the replacement dangerous Step 4 The electrician and householders Use a competent pre-work assessment. Hold the replacement where a safety defect remains unresolved. Someone works on or energises a circuit that is under test Step 5 The tester, other trades and people in the building Check the list of circuits against the design. Record any circuit you could not test. Worked example. Change it to fit your job before you use it. Page 4 of 7
RAMS example questions Are these real jobs? No. Every job, company, person and address here is made up. Each one is a worked example written with our builder, and every page says so.
Can I use one as it is? No. Your site, your people and your emergency arrangements will be different. Change it to fit your job before anyone works to it.
Why do they carry ComplyOnSite branding? They are made with our builder and printed in its standard design. A RAMS you build yourself carries your company name.
Word or PDF? Both. Word if you will change the wording yourself, PDF to read or print. Or press Use this and edit it in the builder , then download your own copy.
Where is the blank? On the RAMS template page. These examples are all filled in.
How were they checked? Each one is read against published guidance, mainly from HSE, for its facts, the order of the work and its emergency arrangements. The sources are listed beside it. If a document changes, it comes off this page until it has been checked again. The check covers the example, not your job.