Skip to content

Hot works RAMS example

Worked examples for common jobs, written with our builder. Read, download, adapt.

Build your own

Choose a job

Hot works RAMS example

Hot works: cutting and welding in an occupied warehouse

Steel brackets cut out and replaced on a live bay, with a permit for each shift and a separate fire watcher.

What to change

  • Company, people, site and dates
  • Who issues the permit, and who is fire watcher
  • What is stored and how it burns
  • Detector and sprinkler zones
  • Indoors or outdoors: fume control changes
  • Hot works finish time against site closing time
  • Emergency arrangements

Sources

Checked

  1. ComplyOnSitecomplyonsite.comWORKED EXAMPLE: RISK ASSESSMENT AND METHOD STATEMENTHot works: cutting and welding in an occupiedwarehouseHollins & Reed Fabrications Ltd · 12 to 14 October 2026 · In charge: Dan HollinsWorked example. Change it to fit your job before you use it.Job detailsCompanyHollins & Reed Fabrications LtdSite and work areaUnit 3, Canal Side Business Park, Stockport: Bay 6Planned dates12 to 14 October 2026CustomerThornley Vale Estates LtdIn charge on siteDan HollinsTeamThree people: Dan Hollins leads and welds; Tom Ellis cuts and grinds;Priya Shah is the fire watcher and does no hot work.WorkHot works: cutting and welding in an occupied warehousePrepared byDan HollinsSignatureDateWork and boundariesGrind/cold cut, fuel-gas cut, arc weld. Areas: Bay 6, steel beam over grid lines 12 to 16; The floorbelow and around the work, and the far side of the Bay 6 partitionWorking arrangementAccess: a podium.Working height: brackets at about 2.5 m.Ground or floor: level concrete slab.Gas set: Oxygen and propane.Other people will be using the area.The warehouse keeps trading; Bay 6 is closed to trucks and staff, behind barriers and screens,while we work. The engineer’s drawing rules out bolting the new brackets, so heat is needed forthis work and no other. Hot work runs only on the shift manager’s permit for this bay and thisWorked example. Change it to fit your job before you use it.Page 1 of 7
  2. Example: Hot works: cutting and welding in an occupied warehouseComplyOnSiteshift, shown at the work. It stops two hours before the end of the working day. Two extinguishersstay at the work. The fire watcher stays for at least an hour after the last hot work, and there isone more check two hours after it. Which detectors go off, and who puts them back on andwhen, is agreed with the shift manager first.Emergency arrangementsFire: break the glass at call point CP14, by the Bay 6 door, and leave. Priya Shah raises the alarmfirst and tackles a fire only if it is safe; while the zone’s detectors are off she is the detection for thatzone. Gas off at the cylinder if you can do it safely. Muster at Yard B and report to the shift manager.Tell the fire service the cylinders are on the trolley at Bay 6. First aid: J. Patel, goods-in office,including burns. Priya Shah rings 999; J. Patel meets the crew at gate 2 and goods-in stops alltrucks.Planned method1Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active workarea. Keep entrances and escape routes clear.2Keep people clear of the workAgree how people get past or around the work while it is going on. Put barriers or signs wherea route crosses the work. Do not leave open work unattended.3Check the wheel and guardCheck the wheel type, speed and mounting before use. Fit the guard and side handle; stop ifthe guard cannot stay between you and the wheel.4Check the welding equipmentInspect the machine, leads, holder, torch and connectors before plugging in. Withdrawdamaged equipment from use.5Check for asbestos before you disturb anythingCheck the asbestos survey covers exactly what you will disturb, to the full depth. Register only,or nothing: get a refurbishment survey or a sample first. Read what it says about old lagging,boards and panels around the steel and pipework. No survey, or a material you do notrecognise: stop and get it checked.6Find and isolate hidden servicesFind cables and pipes before you disturb anything: drawings, then a detector. Mark what youfind. Not sure what is there? Turn the supply off, or do not start. Have cables and gas isolatedby the right person and prove them dead before you start.7Stop things falling on people belowKeep people out of the area below the work so nobody walks under the tools, hot metal andslag. Keep toe boards and guards in place on any platform, and lanyard tools where you can.Worked example. Change it to fit your job before you use it.Page 2 of 7
  3. Example: Hot works: cutting and welding in an occupied warehouseComplyOnSite8Set up access equipmentUse access equipment suited to the task and work area. Check the equipment before use.Keep the area below the work controlled.9Carry the steel, tools and metal parts safelyPlan the route, clear it, and get help with anything long or heavy. Store materials close to thework so nobody carries further than they need to.10Check and clean the metal before cuttingRemove dirt and grease where the method allows. Do not flame cut a former fuel or chemicalcontainer without safe certification.11Prove it dead before you cut into itMetalwork often carries cables, conduit or trunking. Get the circuit switched off, locked off andproved dead first. Do not cut, grind or weld on anything still live.12Clear combustibles before hot workWalk the area with the site contact. Check around the work, below it and on the other side ofany partition. Move combustible material away, or cover it with flame-resistant covers. Protectopenings with non-combustible board. Agree which detector zone is isolated, who isolates itand who puts it back on. Place at least two suitable extinguishers at the work and post a firewatcher who is not doing the hot work.13Assess vibration from the grinderNote how long each person's hands are on each tool while it runs. Take the tool's vibrationfigure from the maker or HSE's table and check it fits how you use it. Points per hour timeshours on the trigger, added up for the day, gives the exposure: 100 points is the action value,400 is the limit. HSE's vibration calculator does the sum. Over 100, cut it with lower-vibrationkit or less time, and never pass 400. Write the result down. Sharing the work does not replacethis.14Check the gas set before lightingBring only the cylinders the job needs, secured upright on a trolley, and check the torch,hoses, regulators and connections. Keep oxygen fittings free from oil and grease.15Fit flashback arrestersFit the correct arresters to the oxygen and fuel hoses near the regulators. Check the torch,hoses and arresters before use.16Check for gas leaks safelyTest suspected leaks with leak fluid, never with a flame. Keep hose runs protected from hotmetal, sharp edges and traffic.17Control the flame and slag pathWork out where the flame, slag and sparks can go, including the far side and lower levels.Protect openings with non-combustible board before the torch is lit.18Set up the cut safelyClamp the piece so it cannot twist or close on the blade. Support the offcut before the final partof the cut.Worked example. Change it to fit your job before you use it.Page 3 of 7
  4. Example: Hot works: cutting and welding in an occupied warehouseComplyOnSite19Protect eyes and control sparksWear suitable eye protection and keep people out of the spark and fragment line. Keep thesparks inside the cleared area.20Clamp the return to clean work metalClamp the current return close to the weld on clean metal. Do not use a handrail, pipe orbuilding frame unless it is the workpiece.21Screen the arc from other peopleSet a welding screen around the work before striking the arc. Wear the correct welding filterand covering clothing.22Capture welding fume at sourcePosition LEV at the arc and keep your head out of the plume. Where LEV cannot provideenough control, as is often the case outdoors, wear RPE with an APF of at least 20. Tight-fittingRPE needs a face fit test and a clean shave.23Get the hot-work permit for this place and shiftGet a permit for this location and this shift, once the area is cleared and the fire cover is inplace. It states the place, the times, the precautions, how to raise the alarm, who is in controland who authorised it. Keep a copy on display at the work.24Work under the permitDo only the cutting, grinding, welding or heating the permit covers. Grinding sparks are hotwork too. Keep the fire watcher on duty during the work and through every break. Stop hotwork two hours before the end of the working day.25Shut down the gas setShut off the gas at the cylinder when the cutting finishes. Purge the hoses, then stow thecylinders.26Complete the fire watch before handbackKeep a continuous fire watch for at least an hour after hot work stops, then make at least onemore check two hours after finishing. Inspect behind walls, below floors and in voids beforeclosing the permit. Have the detector zone put back on as soon as the work stops, and sign offthe permit.27Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell thecustomer or whoever runs the site when the work is complete.Risk assessmentHazardWho might beharmed and howControls in placePeople entering thework area or trippingover materialsStep 1Workers,occupants andvisitorsMark or barrier the active work area. Store tools and materialsaway from access routes.Worked example. Change it to fit your job before you use it.Page 4 of 7
  5. Example: Hot works: cutting and welding in an occupied warehouseComplyOnSiteHazardWho might beharmed and howControls in placePeople using thebuilding or passingby walking into thework or over what itleavesStep 2Occupants,visitors, membersof the public andworkersKeep the barriers and signs up while the work is active. Givepeople a clear way round where their normal route is blocked.A wrong or badlymounted wheelbreaks and throwsfragmentsStep 3The operator andanyone nearbyUse the wheel only for the work it is designed to do. Have atrained person change damaged or worn wheels.Electric shock, burnsor a failed weldingreturn circuitStep 4The welder andnearby workersUse equipment suitable for the task and in good condition.Report defects before the arc is struck.Breathing asbestosfibres from oldboards, sheets,sealants or insulationStep 5The team andanyone in thebuildingDo not cut, drill or break any material until it is confirmedasbestos free. Licensed work is not for this method; hand it toa licensed contractor.Hitting a live cable orgas pipe causesshock, fire or gasescapeStep 6The person doingthe work andeveryone nearbyCheck again wherever the work moves. If you hit something,stop, keep clear and report it.Tools, hot metal andslag falling ontopeople belowStep 7People belowBring waste down by hand or in bags. Never throw it. Keep theexclusion zone up until the last item is down.Falling from theaccess equipment;tools or materialsfalling from theplatformStep 8The person on theplatform, if it is setup on anunsuitable surfaceand shifts underthem. Anyonepassing or workingunderneath.Place access equipment on a firm, level surface. Keep toolsand materials secure while working above ground.Back and shoulderinjury from carryingheavy or long itemsStep 9Everyone handlingmaterialsUse a trolley or sack truck on the flat where the load suits one.Where the work is up a level, hand items up or hoist them.Never carry them up a ladder.Worked example. Change it to fit your job before you use it.Page 5 of 7
  6. Example: Hot works: cutting and welding in an occupied warehouseComplyOnSiteHazardWho might beharmed and howControls in placeExplosive vapour ortoxic fume comesfrom contaminationor former contentsStep 10The operator andanyone nearbyStop if the former contents are unknown or unsafe. Use theagreed fume control and RPE for the metal.Cutting into a livecable or conduitgives a shock, a flashburn or starts a fireStep 11The person cuttingand anyonenearbyOnly the person who locked it off takes the lock off. Prove thetester on a known live source before and after.Sparks, hot metal orslag starts a fireStep 12Everyone in andnear the work areaSparks can travel a long way and start fires in other rooms:check the routes they can take. Put a cold method first if thejob can be done without heat.Hand-arm vibrationfrom the grinderStep 13The persongrindingKeep the tools maintained and hands warm. Gloves do not stopvibration. Give health checks to anyone above the action value.Fire or explosionfrom an unsafe gassetStep 14The operator andnearby workersUse the correct hose, regulator and coupler for each gas.Withdraw damaged equipment from use.Flashback travelsthrough the hoses tothe cylindersStep 15The operator andeveryone nearbyStop and evacuate if a flashback makes a cylinder hot orvibrate. Use the arresters specified for the gas equipment.Leaking fuel gas oroxygen causes fire orexplosionStep 16The operator andnearby workersClose the cylinders and repair the defect before use. Do notuse oil or grease on oxygen fittings.Flame or hot slagburns someone orlands out of sightStep 17The operator, firewatch and peoplenearbyKeep the hot-work route under control. Keep the hose runclear of the slag path.Kickback, trappedfingers or an offcutdropping as it comesfreeStep 18The operator andanyone below ornearbyKeep both hands on the tool where its design allows. Stop ifthe part is loaded or the support is not clear.Fragments, sparks orhot swarf injuresomeone nearbyStep 19The operator andeveryone near theworkWear hearing protection and a face shield for grinding. Stop ifsparks reach anything that was not cleared.Worked example. Change it to fit your job before you use it.Page 6 of 7
  7. Example: Hot works: cutting and welding in an occupied warehouseComplyOnSiteHazardWho might beharmed and howControls in placeStray welding currentcauses shock, burnsor property damageStep 20The welder andpeople touchingnearby metalKeep the return path short. Stop if the return cannot attachsafely to the workpiece.Arc-eye, burns andharmful lightreaching peoplenearbyStep 21The welder,passers-by andnearby workersKeep unprotected people outside the screened area. Use asuitable welding curtain or screen.Breathing weldingfume that candamage the lungsStep 22The welder andpeople nearbyGeneral ventilation alone does not control welding fume. Keeppeople out of lingering fume.Hot work startsbefore the fireprecautions are inplaceStep 23Everyone in andnear the work areaNo permit, no hot work. A new shift or a new place needs anew permit.A fire takes holdunseen during thework or a breakStep 24Everyone in andnear the work areaThe fire watcher raises the alarm first, and tackles a fire only ifit is safe. Stop and get the permit changed if the job or theplace changes.Gas left underpressure leaks orfeeds a fireStep 25The operator andeveryone nearbyTell the fire service on arrival where any cylinders are. Do notmove a cylinder involved in a fire.A smouldering firedevelops after thework stopsStep 26Everyone in andnear the work areaTell the site when the work and watch are finished. Keep to alonger watch if the site requires one.Debris, tools orunfinished work leftin the areaStep 27Workers,occupants andvisitorsRemove waste by the agreed route. Record and protect anyunfinished work.Worked example. Change it to fit your job before you use it.Page 7 of 7

Method statement and risk assessment, side by side

Method statement The work in order, step by step.
Risk assessment Each hazard, who could be harmed, the controls in place and any further action.

Use an example, then make it yours

HSE says not to just copy an example and put your company name on it: that would not satisfy the law or protect your people.

The builder asks about your site and rewrites the hazards and steps.

RAMS example questions

Are these real jobs?

No. Every job, company, person and address here is made up. Each one is a worked example written with our builder, and every page says so.

Can I use one as it is?

No. Your site, your people and your emergency arrangements will be different. Change it to fit your job before anyone works to it.

Why do they carry ComplyOnSite branding?

They are made with our builder and printed in its standard design. A RAMS you build yourself carries your company name.

Word or PDF?

Both. Word if you will change the wording yourself, PDF to read or print. Or press Use this and edit it in the builder, then download your own copy.

Where is the blank?

On the RAMS template page. These examples are all filled in.

How were they checked?

Each one is read against published guidance, mainly from HSE, for its facts, the order of the work and its emergency arrangements. The sources are listed beside it. If a document changes, it comes off this page until it has been checked again. The check covers the example, not your job.