Strip and reroof RAMS example Worked examples for common jobs, written with our builder. Read, download, adapt.
Build your own Choose a job Search jobs All Electrical Plumbing and ventilation Painting Roofing Groundworks and landscaping Carpentry and glazing Interiors Brickwork Access and lifting Demolition and strip out Welding Cleaning
Electrical second fix and testing in a house refurbishment Lived-in 1970s house, accessories and consumer unit fitted, one circuit dead at a time, tested dead then live before handover. 7 pages, checked 2 November 2026 Hot works: cutting and welding in an occupied warehouse Steel brackets cut out and replaced on a live bay, with a permit for each shift and a separate fire watcher. 7 pages, checked 2 November 2026 Erecting an independent tied scaffold on a two-storey house Independent tube and fitting scaffold to a TG20 compliance sheet, family at home, rescue kit on the wagon. 6 pages, checked 2 November 2026 Stripping and re-tiling a pitched roof from a scaffold Lived-in house, tiles, battens and underlay off, one section made weathertight each day. 8 pages, checked 2 November 2026 Digging a 1.2 m trench for strip footings and a drain Beside a lived-in house, services located first, excavator then hand tools, trench sheets and props before anyone goes in. 7 pages, checked 2 November 2026 Repainting occupied offices Water-based paint from a podium, walls filled and sanded first, one bay screened off at a time while staff work on. 5 pages, checked 2 November 2026 Bathroom first and second fix in a lived-in house Only bathroom replaced, press-fit pipework under the floor and in a duct, tested before anyone closes it up, suite fitted after tiling. 8 pages, checked 2 November 2026 Tarmac resurfacing on a car park that stays partly open Old surface tested and planed off, private retail car park, laid bay block by bay block with shoppers around. 5 pages, checked 2 November 2026 Unloading a builders’ merchant delivery with a lorry loader Packs of blocks and plasterboard landed on a small building site, on a standing lift plan reviewed for this site. 6 pages, checked 2 November 2026 Cleaning the outside of a two-storey office with a water-fed pole All from the ground, in an open office set back behind its own car park, on cold November mornings. 4 pages, checked 2 November 2026 MIG welding a pump frame in a plant room MIG welding bare mild steel at floor level in a closed plant room, with on-torch extraction, while the retail park keeps trading. 5 pages, checked 2 November 2026 Stripping out a vacant single-storey workshop Office ceiling, partitions, carpet and benches out by hand, building empty, every service including the fire alarm disconnected on a certificate, lit by roof lights and a 110 V string. 7 pages, checked 2 November 2026 Skimming and patching walls in an occupied house Ground floor living room of a 2006 house, family at home, plaster mixed in the room with the door shut, from a hop-up. 5 pages, checked 2 November 2026 Building a garden wall in blockwork and facing brick A 5 m long, 1 m high wall, one brick thick, on a foundation already in, laid from the ground. 6 pages, checked 2 November 2026 Core drilling a flue hole through a cavity blockwork wall One 125 mm wet core, rig fixed to the inner leaf, through an external wall of a single-storey extension, with the core caught outside. 5 pages, checked 2 November 2026 Replacing damaged ceiling tiles and grid in an occupied office, out of hours Like-for-like tiles and tees on the existing hangers, from a podium, with the offices empty and the fire alarm left live. 4 pages, checked 2 November 2026 Clearing gutters on a bungalow from a ladder Eight ladder positions of under 15 minutes each, one hand on the ladder, with a stand-off keeping it clear of the gutter. 4 pages, checked 2 November 2026 Laying a block paved patio in a lived-in garden Dug out by hand to 250 mm, sub-base compacted, blocks laid on sand and cut wet, family at home. 6 pages, checked 2 November 2026 Hanging office doors in existing linings, out of hours in a working building Six heavy non-fire meeting room doors, trimmed and routed on trestles after the staff have gone. 4 pages, checked 2 November 2026 Strip and reroof RAMS example Stripping and re-tiling a pitched roof from a scaffold
Lived-in house, tiles, battens and underlay off, one section made weathertight each day.
What to change Company, people, site and dates Slate or clay rather than concrete tile Bat records and nesting birds Tile loading agreed with the scaffolder Fragile rooflights, conservatories or lean-tos Building control and the insulation rules Emergency arrangements Sources Checked 2 November 2026
ComplyOnSite complyonsite.com WORKED EXAMPLE: RISK ASSESSMENT AND METHOD STATEMENT Stripping and re-tiling a pitched roof from a scaffold Hollins & Reed Roofing Ltd · 12 to 23 October 2026 · In charge: Dan Hollins Worked example. Change it to fit your job before you use it. Job details Company Hollins & Reed Roofing Ltd Site and work area 22 Mill Lane, M33 Planned dates 12 to 23 October 2026 Customer Ms Patel In charge on site Dan Hollins Team Three roofers: Dan Hollins leads and checks the forecast each morning; Tom Ellis and Priya Shah work with him. Tom is the first aider. Work Stripping and re-tiling a pitched roof from a scaffold Prepared by Dan Hollins Signature Date Work and boundaries Strip the whole roof, fit replacement covering. Areas: Main roof, front and rear slopes; Skip and chute landing on the drive Working arrangement Access: a scaffold. Working height: eaves about 5 m, ridge about 8 m, from an independent scaffold on all elevations, handed over and tagged; platform within 300 mm of the eaves. Ground or floor: block paved drive and garden. Dust control when cutting: Water on the blade. Other people will be using the area. The family stays at home; the loft and front path are closed to them. Waste goes down a rubble chute to the skip; tiles are never thrown. We strip only what can be made weathertight that day. Worked example. Change it to fit your job before you use it. Page 1 of 8 Page 1 of 8
Example: Stripping and re-tiling a pitched roof from a scaffold ComplyOnSite Bats and nesting birds were checked before work. The re-roof is notified to building control. Old battens are not footholds or anchors unless a competent person has checked them, and boards or nets stop falls through the opened roof. Tile loading per bay is agreed with the scaffolder. Emergency arrangements Voice alarm on the scaffold: shout “stop”. Fall from the eaves or through the opened roof: stop work; Tom Ellis climbs by the bay 3 ladder with the kit; we do not wait for 999 to reach someone on a roof, in the loft or on a lift. Do not move someone with a back or neck injury unless they are in danger. Sudden wind or rain: sheet down and secured, or leave it and get off the roof. Bat found: stop in that area, leave it, ring the National Bat Helpline and the office. Water coming into rooms: tell the householder, power off to those circuits, sheet up. Tile or debris hits anyone: stop, first aid, keep the path shut. First aid kit in the van cab. Priya Shah rings 999, gives 22 Mill Lane, M33, and meets the crew on the drive. Planned method 1 Set up the work area Confirm the work area and scope before starting. Keep other people outside the active work area. Keep entrances and escape routes clear. 2 Keep people clear of the work Agree how people get past or around the work while it is going on. Put barriers or signs where a route crosses the work. Do not leave open work unattended. 3 Plan the strip in sections Write down the layers being removed, the order and the points where the team will stop and check. Brief who holds each piece, where it goes and how the area below stays protected. 4 Check for asbestos before you disturb anything Check the asbestos survey covers exactly what you will disturb, to the full depth. Register only, or nothing: get a refurbishment survey or a sample first. Read what it says about the old roof covering, underlay and insulation. No survey, or a material you do not recognise: stop and get it checked. 5 Find and isolate hidden services Find cables and pipes before you disturb anything: drawings, then a detector. Mark what you find. Not sure what is there? Turn the supply off, or do not start. Have cables and gas isolated by the right person and prove them dead before you start. 6 Check the weather before you start Do not lift or fix roof coverings and temporary sheeting in strong wind. Stop in heavy rain, ice or lightning. 7 Check the roof build-up before opening it Confirm the covering, underlay, battens and supports match the information for the job. Stop if the layer or support is different from what was expected. Worked example. Change it to fit your job before you use it. Page 2 of 8 Page 2 of 8
Example: Stripping and re-tiling a pitched roof from a scaffold ComplyOnSite 8 Stop things falling on people below Keep people out of the area below the work so nobody walks under the roof coverings, tools and waste. Keep toe boards and guards in place on any platform, and lanyard tools where you can. 9 Work from the scaffold Check the scaffold tag or handover shows an inspection within the last 7 days. Use only the lifts and access that were handed over. Keep materials within the loading the scaffold was built for. Keep off in high wind or ice, or when sheeting has come loose. 10 Use the hoist Check the hoist's thorough examination report is in date and it can take the weight. Keep people out from underneath while a load is up. 11 Protect the area below Close and segregate the area below, or put the planned temporary protection in place before stripping. Keep the protection in place until the section is closed and the waste is down. 12 Strip one roof section at a time Work in the agreed sequence and keep the remaining roof supported while each section is opened. Remove loose pieces before moving to the next section. 13 Weatherproof each open section Re-cover the section the same day or fix the planned temporary sheeting before leaving it. Check the cover is secure and will not let rain into the building. 14 Take off lead flashings with lead controls Handle old lead flashings in gloves and disposable overalls. Wash your hands and face before eating, drinking or smoking. 15 Lower and stack stripped materials Lower tiles, slates, battens and waste by the agreed route; never throw them from the roof. Stack reusable material safely and keep waste clear of edges and access routes. 16 Brief the roof team Confirm the covering, roof-system instructions, access and handover checks before laying starts. Stop if the supplied system differs from the brief. 17 Check the prepared roof supports Check the rafters, support lines and fixing points before fitting the new roof system. Stop if the supports are damaged, loose or different from the design. 18 Lay the underlay Install the specified underlay before the battens. Keep the eaves and ridge layout to the roof system. 19 Fix the battens to the design Set out the batten gauge from the eaves to the ridge. Fix battens to the prepared rafters as specified. Worked example. Change it to fit your job before you use it. Page 3 of 8 Page 3 of 8
Example: Stripping and re-tiling a pitched roof from a scaffold ComplyOnSite 20 Load out the tiles evenly Spread the tiles in small stacks along the battens and the scaffold. Keep within the loading agreed with the scaffolder and what the roof can carry. 21 Control the dust when cutting Cut tiles in one set area on a sacrificial board, never dry. Wear an APF 20 mask (FFP3 or P3) when you cut: fit tested and clean-shaven. Keep other people out of the dust. 22 Wet cutting This job is wet cutting: keep water on and collect the slurry. 23 Use the grinder or disc cutter safely Check the disc is the right type and speed for the tool and the material. Keep the guard on and both hands on the tool. Wear impact-rated eye protection. 24 Limit noise and vibration Wear ear defenders when cutting. Note how long each person's hands are on each tool while it runs. Take the tool's vibration figure from the maker or HSE's table and check it fits how you use it. Points per hour times hours on the trigger, added up for the day, gives the exposure: 100 points is the action value, 400 is the limit. HSE's vibration calculator does the sum. Over 100, cut it with lower-vibration kit or less time, and never pass 400. Write the result down. Sharing the work does not replace this. Keep the tools maintained. 25 Lay the covering from the eaves Start at the eaves and work in the specified rows. Use the product's fixing method as each course is laid. 26 Fit the flashings Fit lead flashings at every abutment and chimney, to the roof system and the design. Handle lead in gloves and wash before eating, drinking or smoking. 27 Check alignment, overlap and edges Check each course against the roof lines and specified overlap. Complete the ridge, verge and eaves details before handover. 28 Clear the gutters and sign the roof off Check the roof is weathertight, clear the gutters and take down any hoist. Sign the roof off with the customer, and with building control where the job needs it, then hand the scaffold back for striking. 29 Clear and hand back the area Remove tools, waste and unused materials. Check the area is clean and ready to use. Tell the customer or whoever runs the site when the work is complete. Worked example. Change it to fit your job before you use it. Page 4 of 8 Page 4 of 8
Example: Stripping and re-tiling a pitched roof from a scaffold ComplyOnSite Risk assessment Hazard Who might be harmed and how Controls in place People entering the work area or tripping over materials Step 1 Workers, occupants and visitors Mark or barrier the active work area. Store tools and materials away from access routes. People using the building or passing by walking into the work or over what it leaves Step 2 Occupants, visitors, members of the public and workers Keep the barriers and signs up while the work is active. Give people a clear way round where their normal route is blocked. An unplanned strip destabilises the roof or exposes people to uncontrolled debris Step 3 Roofers, other trades and the public Use a written method from a competent person. Stop if the roof build-up differs from the method. Breathing asbestos fibres from old boards, sheets, sealants or insulation Step 4 The team and anyone in the building Do not cut, drill or break any material until it is confirmed asbestos free. Licensed work is not for this method; hand it to a licensed contractor. Hitting a live cable or gas pipe causes shock, fire or gas escape Step 5 The person doing the work and everyone nearby Check again wherever the work moves. If you hit something, stop, keep clear and report it. Wind catches the roof coverings and temporary sheeting or blows someone off balance at height Step 6 The team and people below Agree a wind limit for this work and check the forecast before you start. Tie down or take in loose materials before you leave. An unexpected layer or weak support fails when the roof is opened Step 7 Roofers and people below Check a small area before committing to the strip. Do not alter the structure as part of this method. Roof coverings, tools and waste falling onto people below Step 8 People below Bring waste down by hand, in bags or by the chute. Never throw it. Keep the exclusion zone up until the last item is down. Worked example. Change it to fit your job before you use it. Page 5 of 8 Page 5 of 8
Example: Stripping and re-tiling a pitched roof from a scaffold ComplyOnSite Hazard Who might be harmed and how Controls in place Falling from a scaffold that has been altered; materials falling from the scaffold Step 9 Anyone working on the lift, where a guardrail, board or tie has been taken out to get the work done. Anyone passing or working underneath, including the public where the scaffold is over a footpath. Never remove boards, ties, guardrails or bracing; ask the scaffolding contractor to alter it. Report damage or a missing tag and keep off until it is checked. Fit brick guards or netting where materials could fall on people below. A load falls from the hoist onto someone below Step 10 People below the hoist Secure the roof materials before the lift. One person controls the lift and everyone can hear them. Debris, water or tools enter the area below the open roof Step 11 People in the building and people below Keep people out of the drop area. Stop if the protection below is missing or damaged. Loose roof materials fall or the remaining roof becomes unstable Step 12 Roofers and people below Keep the edge protection and exclusion area in place. Do not leave loose tiles, slates or battens at the roof edge. Rain enters the building or wind lifts temporary sheeting Step 13 Roofers and building occupants Check the forecast before opening the roof. Stop if the temporary cover cannot be fixed securely. Swallowing lead from dust on hands and clothing Step 14 The roofers handling the flashings Keep food and drink away from the work. Take the overalls off before going to the van. Roof waste falls or heavy materials cause injury during handling Step 15 Roofers, labourers and people below Use the planned lifting aid and exclusion zone. Keep the route clear before each load moves. A worker uses the wrong method or works without the required roof protection Step 16 Roofers and people below Use trained and competent workers. Keep the agreed roof protection in place. Worked example. Change it to fit your job before you use it. Page 6 of 8 Page 6 of 8
Example: Stripping and re-tiling a pitched roof from a scaffold ComplyOnSite Hazard Who might be harmed and how Controls in place The new covering lacks support or its fixings fail Step 17 Roofers and building occupants Get a repair or support decision before covering damaged areas. Do not guess a fixing into a weak support. Water enters or the covering lacks its designed support Step 18 Roofers and building occupants Use the manufacturer's spacing and gauge. Do not guess a batten size or lap. Battens move or the covering has inadequate support and lap Step 19 Roofers Check the batten grade, gauge and fixing before laying. Stop if the prepared supports do not match the roof system. Stacked tiles overload a scaffold bay or the roof, or slide off Step 20 Roofers and people below Do not stack over the toe board without brick guards. Keep the stacks clear of the edge. Silica dust from power cutting damages the lungs Step 21 The person cutting and anyone downwind Cut in one place, away from other trades. Collect any slurry while it is wet. Clear any dry dust with an H or M Class vacuum, not a brush. Silica dust if the water stops, and slipping on slurry Step 22 The person cutting and anyone nearby Stop cutting if the water stops. A disc bursts or the tool kicks back and cuts the user Step 23 The person cutting Only someone trained to change discs fits them. Stop and swap any cracked or worn disc. Hearing damage and hand-arm vibration from power tools Step 24 The person cutting Use sharp blades and discs, which cut faster with less vibration. Warn people nearby before you start cutting. Tiles or slates slip, fall or leave gaps that admit water Step 25 Roofers and people below Keep the roof access and edge protection in place. Do not leave loose units where wind can move them. A gap at an abutment or chimney lets water into the building Step 26 Roofers and building occupants Check nothing taken off in the strip has been left off. Do not close a section with a flashing still missing. Worked example. Change it to fit your job before you use it. Page 7 of 8 Page 7 of 8
Example: Stripping and re-tiling a pitched roof from a scaffold ComplyOnSite Hazard Who might be harmed and how Controls in place A misaligned or under-lapped covering leaks or is lifted by wind Step 27 Roofers and building occupants Use the specified overlap and fixing schedule. Record any incomplete detail instead of handing back the roof. Blocked gutters or an unchecked roof leak after the scaffold has gone Step 28 Building occupants and the roofers Keep the scaffold up until the roof is signed off. Record anything left to finish. Debris, tools or unfinished work left in the area Step 29 Workers, occupants and visitors Remove waste by the agreed route. Record and protect any unfinished work. Worked example. Change it to fit your job before you use it. Page 8 of 8 Page 8 of 8
Method statement and risk assessment, side by side Method statement The work in order, step by step.Example: Stripping and re-tiling a pitched roof from a scaffold ComplyOnSite Bats and nesting birds were checked before work. The re-roof is notified to building control. Old battens are not footholds or anchors unless a competent person has checked them, and boards or nets stop falls through the opened roof. Tile loading per bay is agreed with the scaffolder. Emergency arrangements Voice alarm on the scaffold: shout “stop”. Fall from the eaves or through the opened roof: stop work; Tom Ellis climbs by the bay 3 ladder with the kit; we do not wait for 999 to reach someone on a roof, in the loft or on a lift. Do not move someone with a back or neck injury unless they are in danger. Sudden wind or rain: sheet down and secured, or leave it and get off the roof. Bat found: stop in that area, leave it, ring the National Bat Helpline and the office. Water coming into rooms: tell the householder, power off to those circuits, sheet up. Tile or debris hits anyone: stop, first aid, keep the path shut. First aid kit in the van cab. Priya Shah rings 999, gives 22 Mill Lane, M33, and meets the crew on the drive. Planned method 1 Set up the work area Confirm the work area and scope before starting. Keep other people outside the active work area. Keep entrances and escape routes clear. 2 Keep people clear of the work Agree how people get past or around the work while it is going on. Put barriers or signs where a route crosses the work. Do not leave open work unattended. 3 Plan the strip in sections Write down the layers being removed, the order and the points where the team will stop and check. Brief who holds each piece, where it goes and how the area below stays protected. 4 Check for asbestos before you disturb anything Check the asbestos survey covers exactly what you will disturb, to the full depth. Register only, or nothing: get a refurbishment survey or a sample first. Read what it says about the old roof covering, underlay and insulation. No survey, or a material you do not recognise: stop and get it checked. 5 Find and isolate hidden services Find cables and pipes before you disturb anything: drawings, then a detector. Mark what you find. Not sure what is there? Turn the supply off, or do not start. Have cables and gas isolated by the right person and prove them dead before you start. 6 Check the weather before you start Do not lift or fix roof coverings and temporary sheeting in strong wind. Stop in heavy rain, ice or lightning. 7 Check the roof build-up before opening it Confirm the covering, underlay, battens and supports match the information for the job. Stop if the layer or support is different from what was expected. Worked example. Change it to fit your job before you use it. Page 2 of 8 Risk assessment Each hazard, who could be harmed, the controls in place and any further action.Example: Stripping and re-tiling a pitched roof from a scaffold ComplyOnSite Risk assessment Hazard Who might be harmed and how Controls in place People entering the work area or tripping over materials Step 1 Workers, occupants and visitors Mark or barrier the active work area. Store tools and materials away from access routes. People using the building or passing by walking into the work or over what it leaves Step 2 Occupants, visitors, members of the public and workers Keep the barriers and signs up while the work is active. Give people a clear way round where their normal route is blocked. An unplanned strip destabilises the roof or exposes people to uncontrolled debris Step 3 Roofers, other trades and the public Use a written method from a competent person. Stop if the roof build-up differs from the method. Breathing asbestos fibres from old boards, sheets, sealants or insulation Step 4 The team and anyone in the building Do not cut, drill or break any material until it is confirmed asbestos free. Licensed work is not for this method; hand it to a licensed contractor. Hitting a live cable or gas pipe causes shock, fire or gas escape Step 5 The person doing the work and everyone nearby Check again wherever the work moves. If you hit something, stop, keep clear and report it. Wind catches the roof coverings and temporary sheeting or blows someone off balance at height Step 6 The team and people below Agree a wind limit for this work and check the forecast before you start. Tie down or take in loose materials before you leave. An unexpected layer or weak support fails when the roof is opened Step 7 Roofers and people below Check a small area before committing to the strip. Do not alter the structure as part of this method. Roof coverings, tools and waste falling onto people below Step 8 People below Bring waste down by hand, in bags or by the chute. Never throw it. Keep the exclusion zone up until the last item is down. Worked example. Change it to fit your job before you use it. Page 5 of 8
RAMS example questions Are these real jobs? No. Every job, company, person and address here is made up. Each one is a worked example written with our builder, and every page says so.
Can I use one as it is? No. Your site, your people and your emergency arrangements will be different. Change it to fit your job before anyone works to it.
Why do they carry ComplyOnSite branding? They are made with our builder and printed in its standard design. A RAMS you build yourself carries your company name.
Word or PDF? Both. Word if you will change the wording yourself, PDF to read or print. Or press Use this and edit it in the builder , then download your own copy.
Where is the blank? On the RAMS template page. These examples are all filled in.
How were they checked? Each one is read against published guidance, mainly from HSE, for its facts, the order of the work and its emergency arrangements. The sources are listed beside it. If a document changes, it comes off this page until it has been checked again. The check covers the example, not your job.
Template Examples Builder