Strip and reroof method statement example

Finished method statements for common jobs: the steps in order, who does each, and the emergency arrangements. Read one, download it, or build your own.

Build your own

Choose a job

Strip and reroof method statement example

Stripping and re-tiling a pitched roof from a scaffold

Lived-in house, tiles, battens and underlay off, one section made weathertight each day.

What to change

  • Company, people, site and dates
  • Slate or clay rather than concrete tile
  • Bat records and nesting birds
  • Tile loading agreed with the scaffolder
  • Fragile rooflights, conservatories or lean-tos
  • Building control and the insulation rules
  • Emergency arrangements

Sources

Checked

  1. ComplyOnSitecomplyonsite.comWORKED EXAMPLE: METHOD STATEMENTStripping and re-tiling a pitched roof from ascaffoldHollins & Reed Roofing Ltd · 12 to 23 October 2026 · In charge: Dan HollinsWorked example of a method statement. Change it to fit your job before you use it.Job detailsCompanyHollins & Reed Roofing LtdSite and work area22 Mill Lane, M33Planned dates12 to 23 October 2026CustomerMs PatelIn charge on siteDan HollinsTeamThree roofers: Dan Hollins leads and checks the forecast each morning;Tom Ellis and Priya Shah work with him. Tom is the first aider.WorkStripping and re-tiling a pitched roof from a scaffoldRisk assessmentStripping and re-tiling a pitched roof from a scaffold: worked exampleRAMS, a separate documentPrepared byDan HollinsSignatureDateWork and boundariesStrip the whole roof, fit replacement covering. Areas: Main roof, front and rear slopes; Skip andchute landing on the driveWorking arrangementAccess: a scaffold.Working height: eaves about 5 m, ridge about 8 m, from an independent scaffold on allelevations, handed over and tagged; platform within 300 mm of the eaves.Ground or floor: block paved drive and garden.Dust control when cutting: Water on the blade.Worked example of a method statement. Change it to fit your job before you use it.Page 1 of 4
  2. Example: Stripping and re-tiling a pitched roof from a scaffoldComplyOnSiteOther people will be using the area.The family stays at home; the loft and front path are closed to them. Waste goes down a rubblechute to the skip; tiles are never thrown. We strip only what can be made weathertight that day.Bats and nesting birds were checked before work. The re-roof is notified to building control. Oldbattens are not footholds or anchors unless a competent person has checked them, and boardsor nets stop falls through the opened roof. Tile loading per bay is agreed with the scaffolder.Emergency arrangementsVoice alarm on the scaffold: shout “stop”. Fall from the eaves or through the opened roof: stopwork; Tom Ellis climbs by the bay 3 ladder with the kit; we do not wait for 999 to reach someone ona roof, in the loft or on a lift. Do not move someone with a back or neck injury unless they are indanger. Sudden wind or rain: sheet down and secured, or leave it and get off the roof. Bat found:stop in that area, leave it, ring the National Bat Helpline and the office. Water coming into rooms: tellthe householder, power off to those circuits, sheet up. Tile or debris hits anyone: stop, first aid, keepthe path shut. First aid kit in the van cab. Priya Shah rings 999, gives 22 Mill Lane, M33, and meetsthe crew on the drive.Planned method1Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active workarea. Keep entrances and escape routes clear.2Keep people clear of the workAgree how people get past or around the work while it is going on. Put barriers or signs wherea route crosses the work. Do not leave open work unattended.3Plan the strip in sectionsWrite down the layers being removed, the order and the points where the team will stop andcheck. Brief who holds each piece, where it goes and how the area below stays protected.4Check for asbestos before you disturb anythingCheck the asbestos survey covers exactly what you will disturb, to the full depth. Register only,or nothing: get a refurbishment survey or a sample first. Read what it says about the old roofcovering, underlay and insulation. No survey, or a material you do not recognise: stop and getit checked.5Find and isolate hidden servicesFind cables and pipes before you disturb anything: drawings, then a detector. Mark what youfind. Not sure what is there? Turn the supply off, or do not start. Have cables and gas isolatedby the right person and prove them dead before you start.6Check the weather before you startDo not lift or fix roof coverings and temporary sheeting in strong wind. Stop in heavy rain, iceor lightning.Worked example of a method statement. Change it to fit your job before you use it.Page 2 of 4
  3. Example: Stripping and re-tiling a pitched roof from a scaffoldComplyOnSite7Check the roof build-up before opening itConfirm the covering, underlay, battens and supports match the information for the job. Stop ifthe layer or support is different from what was expected.8Stop things falling on people belowKeep people out of the area below the work so nobody walks under the roof coverings, toolsand waste. Keep toe boards and guards in place on any platform, and lanyard tools where youcan.9Work from the scaffoldCheck the scaffold tag or handover shows an inspection within the last 7 days. Use only thelifts and access that were handed over. Keep materials within the loading the scaffold was builtfor. Keep off in high wind or ice, or when sheeting has come loose.10Use the hoistCheck the hoist's thorough examination report is in date and it can take the weight. Keeppeople out from underneath while a load is up.11Protect the area belowClose and segregate the area below, or put the planned temporary protection in place beforestripping. Keep the protection in place until the section is closed and the waste is down.12Strip one roof section at a timeWork in the agreed sequence and keep the remaining roof supported while each section isopened. Remove loose pieces before moving to the next section.13Weatherproof each open sectionRe-cover the section the same day or fix the planned temporary sheeting before leaving it.Check the cover is secure and will not let rain into the building.14Take off lead flashings with lead controlsHandle old lead flashings in gloves and disposable overalls. Wash your hands and face beforeeating, drinking or smoking.15Lower and stack stripped materialsLower tiles, slates, battens and waste by the agreed route; never throw them from the roof.Stack reusable material safely and keep waste clear of edges and access routes.16Brief the roof teamConfirm the covering, roof-system instructions, access and handover checks before layingstarts. Stop if the supplied system differs from the brief.17Check the prepared roof supportsCheck the rafters, support lines and fixing points before fitting the new roof system. Stop if thesupports are damaged, loose or different from the design.18Lay the underlayInstall the specified underlay before the battens. Keep the eaves and ridge layout to the roofsystem.Worked example of a method statement. Change it to fit your job before you use it.Page 3 of 4
  4. Example: Stripping and re-tiling a pitched roof from a scaffoldComplyOnSite19Fix the battens to the designSet out the batten gauge from the eaves to the ridge. Fix battens to the prepared rafters asspecified.20Load out the tiles evenlySpread the tiles in small stacks along the battens and the scaffold. Keep within the loadingagreed with the scaffolder and what the roof can carry.21Control the dust when cuttingCut tiles in one set area on a sacrificial board, never dry. Wear an APF 20 mask (FFP3 or P3)when you cut: fit tested and clean-shaven. Keep other people out of the dust.22Wet cuttingThis job is wet cutting: keep water on and collect the slurry.23Use the grinder or disc cutter safelyCheck the disc is the right type and speed for the tool and the material. Keep the guard on andboth hands on the tool. Wear impact-rated eye protection.24Limit noise and vibrationWear ear defenders when cutting. Note how long each person's hands are on each tool while itruns. Take the tool's vibration figure from the maker or HSE's table and check it fits how youuse it. Points per hour times hours on the trigger, added up for the day, gives the exposure:100 points is the action value, 400 is the limit. HSE's vibration calculator does the sum. Over100, cut it with lower-vibration kit or less time, and never pass 400. Write the result down.Sharing the work does not replace this. Keep the tools maintained.25Lay the covering from the eavesStart at the eaves and work in the specified rows. Use the product's fixing method as eachcourse is laid.26Fit the flashingsFit lead flashings at every abutment and chimney, to the roof system and the design. Handlelead in gloves and wash before eating, drinking or smoking.27Check alignment, overlap and edgesCheck each course against the roof lines and specified overlap. Complete the ridge, verge andeaves details before handover.28Clear the gutters and sign the roof offCheck the roof is weathertight, clear the gutters and take down any hoist. Sign the roof off withthe customer, and with building control where the job needs it, then hand the scaffold back forstriking.29Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell thecustomer or whoever runs the site when the work is complete.Worked example of a method statement. Change it to fit your job before you use it.Page 4 of 4

The same sheet as text

Worked example of a method statement. Change it to fit your job before you use it.

Stripping and re-tiling a pitched roof from a scaffold

Job details

  1. CompanyHollins & Reed Roofing Ltd
  2. Site and work area22 Mill Lane, M33
  3. Planned dates12 to 23 October 2026
  4. CustomerMs Patel
  5. In charge on siteDan Hollins
  6. TeamThree roofers: Dan Hollins leads and checks the forecast each morning; Tom Ellis and Priya Shah work with him. Tom is the first aider.
  7. WorkStripping and re-tiling a pitched roof from a scaffold
  8. Risk assessmentStripping and re-tiling a pitched roof from a scaffold: worked example RAMS, a separate document

Work and boundaries

  1. Strip the whole roof, fit replacement covering. Areas: Main roof, front and rear slopes; Skip and chute landing on the drive

Working arrangement

  1. Access: a scaffold.
  2. Working height: eaves about 5 m, ridge about 8 m, from an independent scaffold on all elevations, handed over and tagged; platform within 300 mm of the eaves.
  3. Ground or floor: block paved drive and garden.
  4. Dust control when cutting: Water on the blade.
  5. Other people will be using the area.
  6. The family stays at home; the loft and front path are closed to them. Waste goes down a rubble chute to the skip; tiles are never thrown. We strip only what can be made weathertight that day. Bats and nesting birds were checked before work. The re-roof is notified to building control. Old battens are not footholds or anchors unless a competent person has checked them, and boards or nets stop falls through the opened roof. Tile loading per bay is agreed with the scaffolder.

Emergency arrangements

  1. Voice alarm on the scaffold: shout “stop”. Fall from the eaves or through the opened roof: stop work; Tom Ellis climbs by the bay 3 ladder with the kit; we do not wait for 999 to reach someone on a roof, in the loft or on a lift. Do not move someone with a back or neck injury unless they are in danger. Sudden wind or rain: sheet down and secured, or leave it and get off the roof. Bat found: stop in that area, leave it, ring the National Bat Helpline and the office. Water coming into rooms: tell the householder, power off to those circuits, sheet up. Tile or debris hits anyone: stop, first aid, keep the path shut. First aid kit in the van cab. Priya Shah rings 999, gives 22 Mill Lane, M33, and meets the crew on the drive.

Planned method

  1. 1. Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active work area. Keep entrances and escape routes clear.
  2. 2. Keep people clear of the workAgree how people get past or around the work while it is going on. Put barriers or signs where a route crosses the work. Do not leave open work unattended.
  3. 3. Plan the strip in sectionsWrite down the layers being removed, the order and the points where the team will stop and check. Brief who holds each piece, where it goes and how the area below stays protected.
  4. 4. Check for asbestos before you disturb anythingCheck the asbestos survey covers exactly what you will disturb, to the full depth. Register only, or nothing: get a refurbishment survey or a sample first. Read what it says about the old roof covering, underlay and insulation. No survey, or a material you do not recognise: stop and get it checked.
  5. 5. Find and isolate hidden servicesFind cables and pipes before you disturb anything: drawings, then a detector. Mark what you find. Not sure what is there? Turn the supply off, or do not start. Have cables and gas isolated by the right person and prove them dead before you start.
  6. 6. Check the weather before you startDo not lift or fix roof coverings and temporary sheeting in strong wind. Stop in heavy rain, ice or lightning.
  7. 7. Check the roof build-up before opening itConfirm the covering, underlay, battens and supports match the information for the job. Stop if the layer or support is different from what was expected.
  8. 8. Stop things falling on people belowKeep people out of the area below the work so nobody walks under the roof coverings, tools and waste. Keep toe boards and guards in place on any platform, and lanyard tools where you can.
  9. 9. Work from the scaffoldCheck the scaffold tag or handover shows an inspection within the last 7 days. Use only the lifts and access that were handed over. Keep materials within the loading the scaffold was built for. Keep off in high wind or ice, or when sheeting has come loose.
  10. 10. Use the hoistCheck the hoist's thorough examination report is in date and it can take the weight. Keep people out from underneath while a load is up.
  11. 11. Protect the area belowClose and segregate the area below, or put the planned temporary protection in place before stripping. Keep the protection in place until the section is closed and the waste is down.
  12. 12. Strip one roof section at a timeWork in the agreed sequence and keep the remaining roof supported while each section is opened. Remove loose pieces before moving to the next section.
  13. 13. Weatherproof each open sectionRe-cover the section the same day or fix the planned temporary sheeting before leaving it. Check the cover is secure and will not let rain into the building.
  14. 14. Take off lead flashings with lead controlsHandle old lead flashings in gloves and disposable overalls. Wash your hands and face before eating, drinking or smoking.
  15. 15. Lower and stack stripped materialsLower tiles, slates, battens and waste by the agreed route; never throw them from the roof. Stack reusable material safely and keep waste clear of edges and access routes.
  16. 16. Brief the roof teamConfirm the covering, roof-system instructions, access and handover checks before laying starts. Stop if the supplied system differs from the brief.
  17. 17. Check the prepared roof supportsCheck the rafters, support lines and fixing points before fitting the new roof system. Stop if the supports are damaged, loose or different from the design.
  18. 18. Lay the underlayInstall the specified underlay before the battens. Keep the eaves and ridge layout to the roof system.
  19. 19. Fix the battens to the designSet out the batten gauge from the eaves to the ridge. Fix battens to the prepared rafters as specified.
  20. 20. Load out the tiles evenlySpread the tiles in small stacks along the battens and the scaffold. Keep within the loading agreed with the scaffolder and what the roof can carry.
  21. 21. Control the dust when cuttingCut tiles in one set area on a sacrificial board, never dry. Wear an APF 20 mask (FFP3 or P3) when you cut: fit tested and clean-shaven. Keep other people out of the dust.
  22. 22. Wet cuttingThis job is wet cutting: keep water on and collect the slurry.
  23. 23. Use the grinder or disc cutter safelyCheck the disc is the right type and speed for the tool and the material. Keep the guard on and both hands on the tool. Wear impact-rated eye protection.
  24. 24. Limit noise and vibrationWear ear defenders when cutting. Note how long each person's hands are on each tool while it runs. Take the tool's vibration figure from the maker or HSE's table and check it fits how you use it. Points per hour times hours on the trigger, added up for the day, gives the exposure: 100 points is the action value, 400 is the limit. HSE's vibration calculator does the sum. Over 100, cut it with lower-vibration kit or less time, and never pass 400. Write the result down. Sharing the work does not replace this. Keep the tools maintained.
  25. 25. Lay the covering from the eavesStart at the eaves and work in the specified rows. Use the product's fixing method as each course is laid.
  26. 26. Fit the flashingsFit lead flashings at every abutment and chimney, to the roof system and the design. Handle lead in gloves and wash before eating, drinking or smoking.
  27. 27. Check alignment, overlap and edgesCheck each course against the roof lines and specified overlap. Complete the ridge, verge and eaves details before handover.
  28. 28. Clear the gutters and sign the roof offCheck the roof is weathertight, clear the gutters and take down any hoist. Sign the roof off with the customer, and with building control where the job needs it, then hand the scaffold back for striking.
  29. 29. Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell the customer or whoever runs the site when the work is complete.

What a finished method statement says

  • The job and its boundariesWhat is being done, where, and what is not your work.
  • How the work area is set upAccess, shared spaces and who else is around.
  • The steps, in the order they happenOne action to a step, from arrival to sign-off.
  • Who does each stepThe people in charge and the skills each step needs.
  • What happens if something goes wrongWho to call, where to go and how help gets in.

Method statement or risk assessment: which one is this?

This is the method statement: how the job is done, step by step. The risk assessment says what could go wrong and what controls it.

See both together in the Strip and reroof RAMS example.

Method statement example questions

Are these real jobs?

No. Every job, company, person and address here is made up, and every page says so.

Can I send one as it is?

No. Your site, your people and your emergency arrangements will be different. Change it to fit your job first.

Where is the risk assessment that goes with it?

In the Strip and reroof RAMS example. The method statement names it on page one.

Word or PDF?

Both. Word if you will change the wording yourself, PDF to read or print. Or press Use this and edit it in the builder.

Does a method statement need a risk assessment?

A method statement names the risk assessment it rests on. CDM 2015 does not set a form for either document.

Where is the blank?

On the method statement template page. These examples are all filled in.