Bricklaying method statement example

Finished method statements for common jobs: the steps in order, who does each, and the emergency arrangements. Read one, download it, or build your own.

Build your own

Choose a job

Bricklaying method statement example

Building a garden wall in blockwork and facing brick

A 5 m long, 1 m high wall, one brick thick, on a foundation already in, laid from the ground.

What to change

  • Company, people, site and dates
  • Wall height and thickness against your area
  • Foundation depth and who poured it
  • Mortar class and bag
  • Block and brick weights
  • Who is at home
  • Emergency arrangements

Sources

Checked

  1. ComplyOnSitecomplyonsite.comWORKED EXAMPLE: METHOD STATEMENTBuilding a garden wall in blockwork and facingbrickHollins & Reed Brickwork Ltd · 12 to 15 October 2026 · In charge: Dan HollinsWorked example of a method statement. Change it to fit your job before you use it.Job detailsCompanyHollins & Reed Brickwork LtdSite and work area31 Ash Grove, Altrincham WA14 2RL: rear gardenPlanned dates12 to 15 October 2026CustomerMr and Mrs GrantIn charge on siteDan HollinsTeamThree people: Dan Hollins leads, lays and is the first aider; Priya Shahlays and is his deputy; Tom Reed mixes, cuts and barrows.WorkBuilding a garden wall in blockwork and facing brickRisk assessmentBuilding a garden wall in blockwork and facing brick: worked exampleRAMS, a separate documentPrepared byDan HollinsSignatureDateWork and boundariesBuild a blockwork and facing brick garden wall from the ground. Areas: Rear garden wall betweenthe patio and the lawnNot our work:The foundation, the patio, the lawn and the boundary fences. Nothing is dug and nothing is builtoff the house.Working arrangementAccess: the floor or ground.Dust control when cutting: Water on the blade.Worked example of a method statement. Change it to fit your job before you use it.Page 1 of 4
  2. Example: Building a garden wall in blockwork and facing brickComplyOnSiteThe work area will be kept clear of other people.The Grants are at home. The back garden is closed to them and their dog while we work, andthey use the front door. We use their cloakroom toilet and basin. The wall runs across the gardenbetween the patio and the lawn, on their land and away from every boundary. The drawing showsit 5 m long, 215 mm thick and 1 m high above the lawn including the coping, under the 1,075 mmlimit for a one-brick wall in the most exposed zone, so no piers and no engineer. It tops out at 1m, so it is laid from the ground with no trestle or hop-up. It is English garden wall bond in F2facing bricks with a brick-on-edge coping on a damp proof course and one movement joint in thecoping at the middle. The customer’s groundworker poured the foundation on 5 October 2026,650 mm wide and down to 650 mm, with its top 225 mm below the lawn. The customer’sgroundworker fills both sides once the wall has set. Until then the slots stay boarded. No pipe orcable crossed the open trench. The packs come on to the drive, and everything goes through theside gate by barrow on boards. Materials: 12 aircrete blocks at 16 kg, about 600 facing bricks atabout 2.3 kg and 36 bags of Cemex M12 mortar at 25 kg, each mix used within 120 minutes. Themixer stands on the patio and it and the cutter run from a 110 V transformer in the garage.Washings go into a tub beside the mixer, and the settled solids, offcuts and packaging leave inour van.Emergency arrangementsPriya Shah rings 999 and gives 31 Ash Grove, WA14 2RL; Dan Hollins does if Priya is the one hurt.Dan is the first aider and the kit is in the van on the drive, and an eyewash bottle stands by themixer. Whoever is nearest stays with the casualty, and Tom Reed goes to the front and brings thecrew through the side gate, kept unlocked and clear. Mortar in the eye: wash it out with clean waterstraight away, keep washing, and get to A&E. Wet mortar trapped on the skin: wash it off at once.Planned method1Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active workarea. Keep entrances and escape routes clear.2Check the foundation and the wall sizeCheck the concrete has set and matches the drawing for line, width and depth. Check the wallheight against the published limit for its thickness in your area. Too tall means piers, a thickerwall or an engineer.3Check the mix before tippingRead the bag, specification or delivery docket before adding anything. Mix only the materialand amount approved for the receiving work.4Carry the materials safelyPlan the route, clear it, and get help with anything long or heavy. Store materials close to thework so nobody carries further than they need to.5Set down units close to the wallPut packs on firm level ground near the point of use. Keep the route and working area clearbefore moving the next pack.Worked example of a method statement. Change it to fit your job before you use it.Page 2 of 4
  3. Example: Building a garden wall in blockwork and facing brickComplyOnSite6Keep the work face tidyKeep mortar, tools and units within easy reach without blocking the access route. Clear brokenunits and mortar before they become trip hazards.7Set up a firm mixing pointPut the board, tub or mixer on firm level ground with a clear route around it. Keep bags andwater where they can be reached without twisting or stepping over leads.8Use premix where the job allowsUse pre-mixed mortar when it is approved for the work. Keep bags dry and use them beforethe shelf date.9Control the cement powderTip bags low and steadily into the mixer, standing upwind.10Keep hands out of a mixerSet the mixer on firm level ground and check its guard, lead and plug. Switch off and unplugbefore clearing a jam or cleaning.11Keep wet mortar off your skinWear long-cuffed waterproof gloves and eye protection for all mixing and laying. Trousers goover boots, and kneeling boards stay dry. Wash off any mortar straight away, and wash at thebasin at breaks. The COSHH assessment for cement and mortar goes with this method.12Control the dust when cuttingNever cut dry in the open. Wear an APF 20 mask (FFP3 or P3) when you cut: fit tested andclean-shaven. Keep other people out of the dust.13Wet cuttingThis job is wet cutting: keep water on and collect the slurry.14Use the grinder or disc cutter safelyCheck the disc is the right type and speed for the tool and the material. Keep the guard on andboth hands on the tool. Wear impact-rated eye protection.15Limit noise and vibrationWear ear defenders when cutting. Note how long each person's hands are on each tool while itruns. Take the tool's vibration figure from the maker or HSE's table and check it fits how youuse it. Points per hour times hours on the trigger, added up for the day, gives the exposure:100 points is the action value, 400 is the limit. HSE's vibration calculator does the sum. Over100, cut it with lower-vibration kit or less time, and never pass 400. Write the result down.Sharing the work does not replace this. Keep the tools maintained.16Use the specified amount of waterMeasure water and add it as the product instructions say. Do not add water later to revivemortar that has started to set.17Lay the block course from the trench edgeOne course of 215 mm aircrete blocks brings the wall up to lawn level. At 16 kg each they areunder the 20 kg line, and there are only 12. Kneel on a board at the edge. Nobody stands in thetrench. Cut a block by hand with a masonry saw.Worked example of a method statement. Change it to fit your job before you use it.Page 3 of 4
  4. Example: Building a garden wall in blockwork and facing brickComplyOnSite18Build the wall to the drawingBuild the bond, line and level the drawing shows, and finish with the coping on its damp proofcourse. Keep any movement joint the drawing shows open and clear of mortar.19Keep the fresh wall safeDo not lean boards, sheets or materials against fresh masonry. Cover the top at the end ofeach day and whenever rain is due. Stop building if wind makes the wall unsafe.20Check the wall before leaving itCheck the last course for line and level and that the cover is tied down. Leave materials wherethey cannot strike or load the fresh wall. Leave the area taped off until the wall has set, and tellthe customer what must stay clear and until when.21Wash out at the agreed pointClean boards, tubs and mixers at the site washout point. Keep cement washings out of drainsand clear settled solids as waste.22Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell thecustomer or whoever runs the site when the work is complete.Worked example of a method statement. Change it to fit your job before you use it.Page 4 of 4

The same sheet as text

Worked example of a method statement. Change it to fit your job before you use it.

Building a garden wall in blockwork and facing brick

Job details

  1. CompanyHollins & Reed Brickwork Ltd
  2. Site and work area31 Ash Grove, Altrincham WA14 2RL: rear garden
  3. Planned dates12 to 15 October 2026
  4. CustomerMr and Mrs Grant
  5. In charge on siteDan Hollins
  6. TeamThree people: Dan Hollins leads, lays and is the first aider; Priya Shah lays and is his deputy; Tom Reed mixes, cuts and barrows.
  7. WorkBuilding a garden wall in blockwork and facing brick
  8. Risk assessmentBuilding a garden wall in blockwork and facing brick: worked example RAMS, a separate document

Work and boundaries

  1. Build a blockwork and facing brick garden wall from the ground. Areas: Rear garden wall between the patio and the lawn
  2. Not our work: The foundation, the patio, the lawn and the boundary fences. Nothing is dug and nothing is built off the house.

Working arrangement

  1. Access: the floor or ground.
  2. Dust control when cutting: Water on the blade.
  3. The work area will be kept clear of other people.
  4. The Grants are at home. The back garden is closed to them and their dog while we work, and they use the front door. We use their cloakroom toilet and basin. The wall runs across the garden between the patio and the lawn, on their land and away from every boundary. The drawing shows it 5 m long, 215 mm thick and 1 m high above the lawn including the coping, under the 1,075 mm limit for a one-brick wall in the most exposed zone, so no piers and no engineer. It tops out at 1 m, so it is laid from the ground with no trestle or hop-up. It is English garden wall bond in F2 facing bricks with a brick-on-edge coping on a damp proof course and one movement joint in the coping at the middle. The customer’s groundworker poured the foundation on 5 October 2026, 650 mm wide and down to 650 mm, with its top 225 mm below the lawn. The customer’s groundworker fills both sides once the wall has set. Until then the slots stay boarded. No pipe or cable crossed the open trench. The packs come on to the drive, and everything goes through the side gate by barrow on boards. Materials: 12 aircrete blocks at 16 kg, about 600 facing bricks at about 2.3 kg and 36 bags of Cemex M12 mortar at 25 kg, each mix used within 120 minutes. The mixer stands on the patio and it and the cutter run from a 110 V transformer in the garage. Washings go into a tub beside the mixer, and the settled solids, offcuts and packaging leave in our van.

Emergency arrangements

  1. Priya Shah rings 999 and gives 31 Ash Grove, WA14 2RL; Dan Hollins does if Priya is the one hurt. Dan is the first aider and the kit is in the van on the drive, and an eyewash bottle stands by the mixer. Whoever is nearest stays with the casualty, and Tom Reed goes to the front and brings the crew through the side gate, kept unlocked and clear. Mortar in the eye: wash it out with clean water straight away, keep washing, and get to A&E. Wet mortar trapped on the skin: wash it off at once.

Planned method

  1. 1. Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active work area. Keep entrances and escape routes clear.
  2. 2. Check the foundation and the wall sizeCheck the concrete has set and matches the drawing for line, width and depth. Check the wall height against the published limit for its thickness in your area. Too tall means piers, a thicker wall or an engineer.
  3. 3. Check the mix before tippingRead the bag, specification or delivery docket before adding anything. Mix only the material and amount approved for the receiving work.
  4. 4. Carry the materials safelyPlan the route, clear it, and get help with anything long or heavy. Store materials close to the work so nobody carries further than they need to.
  5. 5. Set down units close to the wallPut packs on firm level ground near the point of use. Keep the route and working area clear before moving the next pack.
  6. 6. Keep the work face tidyKeep mortar, tools and units within easy reach without blocking the access route. Clear broken units and mortar before they become trip hazards.
  7. 7. Set up a firm mixing pointPut the board, tub or mixer on firm level ground with a clear route around it. Keep bags and water where they can be reached without twisting or stepping over leads.
  8. 8. Use premix where the job allowsUse pre-mixed mortar when it is approved for the work. Keep bags dry and use them before the shelf date.
  9. 9. Control the cement powderTip bags low and steadily into the mixer, standing upwind.
  10. 10. Keep hands out of a mixerSet the mixer on firm level ground and check its guard, lead and plug. Switch off and unplug before clearing a jam or cleaning.
  11. 11. Keep wet mortar off your skinWear long-cuffed waterproof gloves and eye protection for all mixing and laying. Trousers go over boots, and kneeling boards stay dry. Wash off any mortar straight away, and wash at the basin at breaks. The COSHH assessment for cement and mortar goes with this method.
  12. 12. Control the dust when cuttingNever cut dry in the open. Wear an APF 20 mask (FFP3 or P3) when you cut: fit tested and clean-shaven. Keep other people out of the dust.
  13. 13. Wet cuttingThis job is wet cutting: keep water on and collect the slurry.
  14. 14. Use the grinder or disc cutter safelyCheck the disc is the right type and speed for the tool and the material. Keep the guard on and both hands on the tool. Wear impact-rated eye protection.
  15. 15. Limit noise and vibrationWear ear defenders when cutting. Note how long each person's hands are on each tool while it runs. Take the tool's vibration figure from the maker or HSE's table and check it fits how you use it. Points per hour times hours on the trigger, added up for the day, gives the exposure: 100 points is the action value, 400 is the limit. HSE's vibration calculator does the sum. Over 100, cut it with lower-vibration kit or less time, and never pass 400. Write the result down. Sharing the work does not replace this. Keep the tools maintained.
  16. 16. Use the specified amount of waterMeasure water and add it as the product instructions say. Do not add water later to revive mortar that has started to set.
  17. 17. Lay the block course from the trench edgeOne course of 215 mm aircrete blocks brings the wall up to lawn level. At 16 kg each they are under the 20 kg line, and there are only 12. Kneel on a board at the edge. Nobody stands in the trench. Cut a block by hand with a masonry saw.
  18. 18. Build the wall to the drawingBuild the bond, line and level the drawing shows, and finish with the coping on its damp proof course. Keep any movement joint the drawing shows open and clear of mortar.
  19. 19. Keep the fresh wall safeDo not lean boards, sheets or materials against fresh masonry. Cover the top at the end of each day and whenever rain is due. Stop building if wind makes the wall unsafe.
  20. 20. Check the wall before leaving itCheck the last course for line and level and that the cover is tied down. Leave materials where they cannot strike or load the fresh wall. Leave the area taped off until the wall has set, and tell the customer what must stay clear and until when.
  21. 21. Wash out at the agreed pointClean boards, tubs and mixers at the site washout point. Keep cement washings out of drains and clear settled solids as waste.
  22. 22. Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell the customer or whoever runs the site when the work is complete.

What a finished method statement says

  • The job and its boundariesWhat is being done, where, and what is not your work.
  • How the work area is set upAccess, shared spaces and who else is around.
  • The steps, in the order they happenOne action to a step, from arrival to sign-off.
  • Who does each stepThe people in charge and the skills each step needs.
  • What happens if something goes wrongWho to call, where to go and how help gets in.

Method statement or risk assessment: which one is this?

This is the method statement: how the job is done, step by step. The risk assessment says what could go wrong and what controls it.

See both together in the Bricklaying RAMS example.

Method statement example questions

Are these real jobs?

No. Every job, company, person and address here is made up, and every page says so.

Can I send one as it is?

No. Your site, your people and your emergency arrangements will be different. Change it to fit your job first.

Where is the risk assessment that goes with it?

In the Bricklaying RAMS example. The method statement names it on page one.

Word or PDF?

Both. Word if you will change the wording yourself, PDF to read or print. Or press Use this and edit it in the builder.

Does a method statement need a risk assessment?

A method statement names the risk assessment it rests on. CDM 2015 does not set a form for either document.

Where is the blank?

On the method statement template page. These examples are all filled in.