Painting and decorating method statement example

Finished method statements for common jobs: the steps in order, who does each, and the emergency arrangements. Read one, download it, or build your own.

Build your own

Choose a job

Painting and decorating method statement example

Repainting occupied offices

Water-based paint from a podium, walls filled and sanded first, one bay screened off at a time while staff work on.

What to change

  • Company, people, site and dates
  • Occupied hours or out of hours
  • Paint and its safety data sheet
  • Age of the building and old paint
  • Ventilation
  • Escape routes, especially in a single-stair building
  • Emergency arrangements

Sources

Checked

  1. ComplyOnSitecomplyonsite.comWORKED EXAMPLE: METHOD STATEMENTRepainting occupied officesHollins & Reed Decorating Ltd · 12 to 14 October 2026 · In charge: Dan HollinsWorked example of a method statement. Change it to fit your job before you use it.Job detailsCompanyHollins & Reed Decorating LtdSite and work areaSecond floor offices, 14 Mill Street, StockportPlanned dates12 to 14 October 2026CustomerThornley Vale Estates LtdIn charge on siteDan HollinsTeamTwo decorators: Dan Hollins leads and agrees each room with the officemanager; Priya Shah works with him.WorkRepainting occupied officesRisk assessmentRepainting occupied offices: worked example RAMS, a separatedocumentPrepared byDan HollinsSignatureDateWork and boundariesPrepare surfaces, paint by brush or roller. Areas: Meeting rooms 1 and 2; Open-plan office; CorridorWorking arrangementAccess: a podium.Working height: rooms about 2.7 m.Ground or floor: level, carpeted.Sanding dust: On-tool extraction.Paint: water-based matt emulsion, data sheet with the office manager.Other people will use parts of the area at times.Offices stay in use; each bay is screened off and released to us by the office manager, one at atime, and desks are moved only with staff agreement. Fire doors are never wedged; corridorsWorked example of a method statement. Change it to fit your job before you use it.Page 1 of 3
  2. Example: Repainting occupied officesComplyOnSiteand stairs stay clear. Only the day’s paint comes to the work, lids on; tins and wash water go bythe agreed waste route. The older paint was tested with a lead test kit: no lead found. Theasbestos survey covers the textured ceilings: none found. A detector head goes off only with thebuilding manager’s agreement: the second decorator checks that area while it is off, and it isback on before we leave.Emergency arrangementsFire bell: stop, close the tins and leave by Stair B. Do not use the lifts. Muster at Car Park C andreport to the floor marshal. Fall from the podium: stop, do not move someone with a back or neckinjury unless they are in danger. Spill or anyone unwell from the paint: open up, move staff away,stop using the product and bring the data sheet; tell the building manager at once. First aid:Reception, ext 200. Priya Shah rings 999; Reception meets the crew at the Mill Street door.Planned method1Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active workarea. Keep entrances and escape routes clear.2Keep people clear of the workAgree how people get past or around the work while it is going on. Put barriers or signs wherea route crosses the work. Do not leave open work unattended.3Check the paint informationRead each label and safety data sheet before opening or mixing paint. Keep the product nameswith the RAMS.4Check preparation productsRead labels and safety data sheets for cleaners, fillers and strippers. Set skin, eye andventilation controls before use.5Check the surface as you goCompare the surface with the agreed description before scraping, filling or stripping. Stop ifthe material, coating or damage is different.6Check for asbestos before you disturb anythingCheck the asbestos survey covers exactly what you will disturb, to the full depth. Register only,or nothing: get a refurbishment survey or a sample first. Read what it says about old paint,textured coatings, boards and walls. No survey, or a material you do not recognise: stop andget it checked.7Set up access equipmentUse access equipment suited to the task and work area. Check the equipment before use.Keep the area below the work controlled.8Set fresh air before paintingOpen doors and windows where the site allows it. Use the ventilation named by the productassessment.Worked example of a method statement. Change it to fit your job before you use it.Page 2 of 3
  3. Example: Repainting occupied officesComplyOnSite9Keep paint tins closedClose tins and containers when they are not being used. Clean spills with the agreed wastemethod.10Control sanding dustUse the sanding dust method named in this document, and stop if it fails. Wear an APF 20mask (FFP3 or P3) for dusty sanding: fit tested and clean-shaven.11Apply the specified paintUse the specified brush or roller and follow the product order and drying instructions.12Keep people away from wet paintMark or barrier wet areas and protect floors and fittings. Only hand the area back when theproduct allows it.13Wash before leaving the jobWash hands after painting and before eating, drinking or smoking. Change contaminatedclothing where the assessment requires it.14Clean up without raising dustUse a suitable vacuum for settled dust and collect wet waste safely. Do not dry sweep or blowdust into the room.15Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell thecustomer or whoever runs the site when the work is complete.Worked example of a method statement. Change it to fit your job before you use it.Page 3 of 3

The same sheet as text

Worked example of a method statement. Change it to fit your job before you use it.

Repainting occupied offices

Job details

  1. CompanyHollins & Reed Decorating Ltd
  2. Site and work areaSecond floor offices, 14 Mill Street, Stockport
  3. Planned dates12 to 14 October 2026
  4. CustomerThornley Vale Estates Ltd
  5. In charge on siteDan Hollins
  6. TeamTwo decorators: Dan Hollins leads and agrees each room with the office manager; Priya Shah works with him.
  7. WorkRepainting occupied offices
  8. Risk assessmentRepainting occupied offices: worked example RAMS, a separate document

Work and boundaries

  1. Prepare surfaces, paint by brush or roller. Areas: Meeting rooms 1 and 2; Open-plan office; Corridor

Working arrangement

  1. Access: a podium.
  2. Working height: rooms about 2.7 m.
  3. Ground or floor: level, carpeted.
  4. Sanding dust: On-tool extraction.
  5. Paint: water-based matt emulsion, data sheet with the office manager.
  6. Other people will use parts of the area at times.
  7. Offices stay in use; each bay is screened off and released to us by the office manager, one at a time, and desks are moved only with staff agreement. Fire doors are never wedged; corridors and stairs stay clear. Only the day’s paint comes to the work, lids on; tins and wash water go by the agreed waste route. The older paint was tested with a lead test kit: no lead found. The asbestos survey covers the textured ceilings: none found. A detector head goes off only with the building manager’s agreement: the second decorator checks that area while it is off, and it is back on before we leave.

Emergency arrangements

  1. Fire bell: stop, close the tins and leave by Stair B. Do not use the lifts. Muster at Car Park C and report to the floor marshal. Fall from the podium: stop, do not move someone with a back or neck injury unless they are in danger. Spill or anyone unwell from the paint: open up, move staff away, stop using the product and bring the data sheet; tell the building manager at once. First aid: Reception, ext 200. Priya Shah rings 999; Reception meets the crew at the Mill Street door.

Planned method

  1. 1. Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active work area. Keep entrances and escape routes clear.
  2. 2. Keep people clear of the workAgree how people get past or around the work while it is going on. Put barriers or signs where a route crosses the work. Do not leave open work unattended.
  3. 3. Check the paint informationRead each label and safety data sheet before opening or mixing paint. Keep the product names with the RAMS.
  4. 4. Check preparation productsRead labels and safety data sheets for cleaners, fillers and strippers. Set skin, eye and ventilation controls before use.
  5. 5. Check the surface as you goCompare the surface with the agreed description before scraping, filling or stripping. Stop if the material, coating or damage is different.
  6. 6. Check for asbestos before you disturb anythingCheck the asbestos survey covers exactly what you will disturb, to the full depth. Register only, or nothing: get a refurbishment survey or a sample first. Read what it says about old paint, textured coatings, boards and walls. No survey, or a material you do not recognise: stop and get it checked.
  7. 7. Set up access equipmentUse access equipment suited to the task and work area. Check the equipment before use. Keep the area below the work controlled.
  8. 8. Set fresh air before paintingOpen doors and windows where the site allows it. Use the ventilation named by the product assessment.
  9. 9. Keep paint tins closedClose tins and containers when they are not being used. Clean spills with the agreed waste method.
  10. 10. Control sanding dustUse the sanding dust method named in this document, and stop if it fails. Wear an APF 20 mask (FFP3 or P3) for dusty sanding: fit tested and clean-shaven.
  11. 11. Apply the specified paintUse the specified brush or roller and follow the product order and drying instructions.
  12. 12. Keep people away from wet paintMark or barrier wet areas and protect floors and fittings. Only hand the area back when the product allows it.
  13. 13. Wash before leaving the jobWash hands after painting and before eating, drinking or smoking. Change contaminated clothing where the assessment requires it.
  14. 14. Clean up without raising dustUse a suitable vacuum for settled dust and collect wet waste safely. Do not dry sweep or blow dust into the room.
  15. 15. Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell the customer or whoever runs the site when the work is complete.

What a finished method statement says

  • The job and its boundariesWhat is being done, where, and what is not your work.
  • How the work area is set upAccess, shared spaces and who else is around.
  • The steps, in the order they happenOne action to a step, from arrival to sign-off.
  • Who does each stepThe people in charge and the skills each step needs.
  • What happens if something goes wrongWho to call, where to go and how help gets in.

Method statement or risk assessment: which one is this?

This is the method statement: how the job is done, step by step. The risk assessment says what could go wrong and what controls it.

See both together in the Painting and decorating RAMS example.

Method statement example questions

Are these real jobs?

No. Every job, company, person and address here is made up, and every page says so.

Can I send one as it is?

No. Your site, your people and your emergency arrangements will be different. Change it to fit your job first.

Where is the risk assessment that goes with it?

In the Painting and decorating RAMS example. The method statement names it on page one.

Word or PDF?

Both. Word if you will change the wording yourself, PDF to read or print. Or press Use this and edit it in the builder.

Does a method statement need a risk assessment?

A method statement names the risk assessment it rests on. CDM 2015 does not set a form for either document.

Where is the blank?

On the method statement template page. These examples are all filled in.