Plastering RAMS example
Worked examples for common jobs, written with our builder. Read, download, adapt.
Build your ownChoose a job
- Electrical second fix and testing in a house refurbishmentLived-in 1970s house, accessories and consumer unit fitted, one circuit dead at a time, tested dead then live before handover.7 pages, checked 2 November 2026
- Hot works: cutting and welding in an occupied warehouseSteel brackets cut out and replaced on a live bay, with a permit for each shift and a separate fire watcher.7 pages, checked 2 November 2026
- Erecting an independent tied scaffold on a two-storey houseIndependent tube and fitting scaffold to a TG20 compliance sheet, family at home, rescue kit on the wagon.6 pages, checked 2 November 2026
- Stripping and re-tiling a pitched roof from a scaffoldLived-in house, tiles, battens and underlay off, one section made weathertight each day.8 pages, checked 2 November 2026
- Digging a 1.2 m trench for strip footings and a drainBeside a lived-in house, services located first, excavator then hand tools, trench sheets and props before anyone goes in.7 pages, checked 2 November 2026
- Repainting occupied officesWater-based paint from a podium, walls filled and sanded first, one bay screened off at a time while staff work on.5 pages, checked 2 November 2026
- Bathroom first and second fix in a lived-in houseOnly bathroom replaced, press-fit pipework under the floor and in a duct, tested before anyone closes it up, suite fitted after tiling.8 pages, checked 2 November 2026
- Tarmac resurfacing on a car park that stays partly openOld surface tested and planed off, private retail car park, laid bay block by bay block with shoppers around.5 pages, checked 2 November 2026
- Unloading a builders’ merchant delivery with a lorry loaderPacks of blocks and plasterboard landed on a small building site, on a standing lift plan reviewed for this site.6 pages, checked 2 November 2026
- Cleaning the outside of a two-storey office with a water-fed poleAll from the ground, in an open office set back behind its own car park, on cold November mornings.4 pages, checked 2 November 2026
- MIG welding a pump frame in a plant roomMIG welding bare mild steel at floor level in a closed plant room, with on-torch extraction, while the retail park keeps trading.5 pages, checked 2 November 2026
- Stripping out a vacant single-storey workshopOffice ceiling, partitions, carpet and benches out by hand, building empty, every service including the fire alarm disconnected on a certificate, lit by roof lights and a 110 V string.7 pages, checked 2 November 2026
- Skimming and patching walls in an occupied houseGround floor living room of a 2006 house, family at home, plaster mixed in the room with the door shut, from a hop-up.5 pages, checked 2 November 2026
- Building a garden wall in blockwork and facing brickA 5 m long, 1 m high wall, one brick thick, on a foundation already in, laid from the ground.6 pages, checked 2 November 2026
- Core drilling a flue hole through a cavity blockwork wallOne 125 mm wet core, rig fixed to the inner leaf, through an external wall of a single-storey extension, with the core caught outside.5 pages, checked 2 November 2026
- Replacing damaged ceiling tiles and grid in an occupied office, out of hoursLike-for-like tiles and tees on the existing hangers, from a podium, with the offices empty and the fire alarm left live.4 pages, checked 2 November 2026
- Clearing gutters on a bungalow from a ladderEight ladder positions of under 15 minutes each, one hand on the ladder, with a stand-off keeping it clear of the gutter.4 pages, checked 2 November 2026
- Laying a block paved patio in a lived-in gardenDug out by hand to 250 mm, sub-base compacted, blocks laid on sand and cut wet, family at home.6 pages, checked 2 November 2026
- Hanging office doors in existing linings, out of hours in a working buildingSix heavy non-fire meeting room doors, trimmed and routed on trestles after the staff have gone.4 pages, checked 2 November 2026
Skimming and patching walls in an occupied house
Ground floor living room of a 2006 house, family at home, plaster mixed in the room with the door shut, from a hop-up.
What to change
- Company, people, site and dates
- What the background is and how it takes suction
- The plaster product and its data sheet
- Where the mixing happens
- Who lives in the house
- Hop-up or other low access
- Emergency arrangements
Sources
- British Gypsum: Thistle MultiFinish product data sheet
- British Gypsum: Thistle MultiFinish safety data sheet
- British Gypsum: Thistle Bond-it product data sheet
- HSE: construction dust
- HSE: sanding taped and covered plasterboard joints
- HSE EH40/2005: workplace exposure limits
- HBF: safe use of trestles and hop-ups
- HSE HSG141: electrical safety on construction sites
- HSE: domestic clients under CDM
- CDM 2015, regulation 30: emergency procedures
Checked
Method statement and risk assessment, side by side
Use an example, then make it yours
HSE says not to just copy an example and put your company name on it: that would not satisfy the law or protect your people.
The builder asks about your site and rewrites the hazards and steps.
RAMS example questions
Are these real jobs?
No. Every job, company, person and address here is made up. Each one is a worked example written with our builder, and every page says so.
Can I use one as it is?
No. Your site, your people and your emergency arrangements will be different. Change it to fit your job before anyone works to it.
Why do they carry ComplyOnSite branding?
They are made with our builder and printed in its standard design. A RAMS you build yourself carries your company name.
Word or PDF?
Both. Word if you will change the wording yourself, PDF to read or print. Or press Use this and edit it in the builder, then download your own copy.
Where is the blank?
On the RAMS template page. These examples are all filled in.
How were they checked?
Each one is read against published guidance, mainly from HSE, for its facts, the order of the work and its emergency arrangements. The sources are listed beside it. If a document changes, it comes off this page until it has been checked again. The check covers the example, not your job.