Office fit-out handover snag list example
Filled snagging lists from real kinds of job. Read one, download it, or open it in Site Issues.
Start your own listChoose a job
- End-of-job walk on a kitchen and bathroom refitOne walk through both rooms before the customer takes the house back.48 snags · Checked 1 November 2026
- Trade sheet for second-fix joinery on a house extensionOne sheet for the joiner: doors, skirtings, stairs and window boards.42 snags · Checked 1 November 2026
- Handover list for an office fit-outThe walk with the client, room by room, with documents still to come. The client signs.43 snags · Checked 1 November 2026
- Plastering and decorating snags on a new-build plotThe contractor’s own walk, in daylight from 2 m, before the plot goes to the customer.40 snags · Checked 1 November 2026
- External works and landscaping snagsDrives, paths, drainage, fences and planting across six plots.48 snags · Checked 1 November 2026
Office fit-out handover snag list example
Handover list for an office fit-out
The walk with the client, room by room, with documents still to come. The client signs.
What to change
- Locations
- Trades on your job
- Who signs for the contractor and for the client
Sources
- Fieldpie: construction snag list guide
- Hampstead Renovations: the snagging process explained
- Designing Buildings: snagging construction works
Checked
The same sheet as text
- Paint touch-ups needed beside the entrance doorReception · Decorator · Low
- Manifestation missing on the glazed screenReception · Signage · High
- Company sign wrong, needs replacingReception · Signage · Medium
- Scratch on the glazed screenReception · Glazier · Medium
- Mastic around the screen frame not completeReception · Glazier · Low
- Joints not tight, cabinet doors not levelReception desk · Joiner · Medium
- Two ceiling tiles misalignedOpen-plan office, by windows · Ceiling fixer · Low
- Ceiling tile damagedOpen-plan office, bay 3 · Ceiling fixer · Low
- Carpet seam showingOpen-plan office, bay 4 · Floor layer · Medium
- Floor covering not bondedOpen-plan office, doorway · Floor layer · Medium
- Transition strip missingTea point threshold · Floor layer · Medium
- Skirting not tight to the wallOpen-plan office, east wall · Joiner · Low
- Lighting sensor not workingOpen-plan office, bay 2 · Electrician · Medium
- Lighting control not workingMeeting room 2 · Electrician · Medium
- Sockets set out of squareOpen-plan office, south wall · Electrician · Low
- Socket not workingOpen-plan office, column C · Electrician · High
- Heating and cooling out of balanceOpen-plan office, bay 5 · Mechanical · Medium
- Door does not latch first timeMeeting room 1 · Joiner · Medium
- Handle not fittedMeeting room 1 · Joiner · Medium
- Wall panel joinery out of alignmentMeeting room 2 · Joiner · Low
- Paint runs on the door frameMeeting room 2 · Decorator · Low
- Scratch on the factory-finished door, seen at 0.5 mDirector’s office · Joiner · High
- Sheen varies on the window wallDirector’s office · Decorator · Medium
- Timber veneer varies between panelsDirector’s office · Joiner · Low
- Self-closer does not fully close the fire doorCorridor · Joiner · High
- Fire door gap over 3 mmCorridor · Joiner · High
- Emergency lighting not testedCorridor · Electrician · High
- Worktop joint not tightTea point · Joiner · Medium
- Grout not finished behind the tapTea point · Tiler · Low
- Silicone not complete at the sinkTea point · Tiler · Low
- Hot water flow not tested at the tapTea point · Plumber · Medium
- WC does not operateWCs, cubicle 2 · Plumber · High
- Cubicle lock not workingWCs, cubicle 3 · Joiner · Medium
- Extract fan not workingWCs · Mechanical · Medium
- Fire alarm not yet certifiedWhole floor · Fire alarm engineer · High
- M&E commissioning not completeWhole floor · Mechanical · High
- BMS demonstration not givenWhole floor · Mechanical · Medium
- Final clean not doneWhole floor · Cleaner · Medium
- O&M manuals not receivedHandover documents · Site team · High
- As-built drawings not issuedHandover documents · Site team · High
- Test and commissioning certificates not collatedHandover documents · Site team · High
- Warranties not registeredHandover documents · Site team · Medium
- Keys and spares not handed overHandover documents · Site team · Medium
What a good snag entry says
A photo reference beats a paragraph.
Where
Room, wall or grid line, so someone who missed the walk can find it.
What, in one line
What is wrong, as you would say it to the person fixing it.
Who puts it right
The trade or company that owns it.
When and who checks
A date to finish by, and who sees it done.
Two ways to keep your snag list
- Print the blank and walk the job
- Hand each trade its own sheet
- Photos stay on someone’s phone
On your phone with Site Issues
- Each snag keeps its number
- Photos stay with the snag
- One list per project
Snag list questions
Are these real jobs?
No. The company, project and rows are made up. The kinds of snag come from published snagging checklists and warranty tolerances.
Can I use one as it is?
No. Walk your own job and write down what you find. Use an example to see the level of detail, then change the locations, trades and people.
Snag list or snagging list?
The same thing. UK sites use both, and some call it a snag sheet or a defects list.
What goes on a handover list?
Everything still open at the walk with the client, room by room, plus documents still to come, such as O&M manuals and as-built drawings. A signed list records that walk. It is not a practical completion certificate.
Excel or Word?
Excel if you want to sort or filter by trade. Word if you want to edit the page as it prints. Both open with the same rows as the PDF.
Where is the blank?
On the snag list template, with your logo and columns.