External works and landscaping snag list example
Filled snagging lists from real kinds of job. Read one, download it, or open it in Site Issues.
Start your own listChoose a job
- End-of-job walk on a kitchen and bathroom refitOne walk through both rooms before the customer takes the house back.48 snags · Checked 1 November 2026
- Trade sheet for second-fix joinery on a house extensionOne sheet for the joiner: doors, skirtings, stairs and window boards.42 snags · Checked 1 November 2026
- Handover list for an office fit-outThe walk with the client, room by room, with documents still to come. The client signs.43 snags · Checked 1 November 2026
- Plastering and decorating snags on a new-build plotThe contractor’s own walk, in daylight from 2 m, before the plot goes to the customer.40 snags · Checked 1 November 2026
- External works and landscaping snagsDrives, paths, drainage, fences and planting across six plots.48 snags · Checked 1 November 2026
External works and landscaping snag list example
External works and landscaping snags
Drives, paths, drainage, fences and planting across six plots.
What to change
- Locations
- Trades on your job
- Who checks and signs off each snag
Sources
- New-builds.co.uk: driveway and garage snagging
- New-builds.co.uk: external works snagging
- LABC Warranty Technical Manual: tolerances
Checked
The same sheet as text
- Over 10 mm out under a 2 m straight edgePlot 4 drive · Surfacing · Medium
- Standing water an hour after rain, over 5 mm deepPlot 4 drive · Surfacing · High
- Standing water at the entrance doorPlot 5 path · Groundworker · High
- Falls towards the buildingPlot 5 drive · Groundworker · High
- Block rocking by the garage doorPlot 6 drive · Paving · Medium
- Blocks cracked and chippedPlot 6 drive · Paving · Medium
- Block joints not filled to the surfacePlot 6 drive · Paving · Low
- Pattern not consistent across the drivePlot 7 drive · Paving · Low
- Rough cuts around the manholePlot 7 drive · Paving · Low
- Edge blocks not haunched and not firmPlot 7 drive · Paving · Medium
- Kerb loosePlot 8 frontage · Groundworker · Medium
- Roller marks in the tarmacPlot 8 drive · Surfacing · Low
- Loose aggregate on the surfacePlot 8 drive · Surfacing · Low
- Ridge at the joint between two laying sessionsPlot 8 drive · Surfacing · Medium
- Tarmac cracking at the thresholdPlot 9 drive · Surfacing · Medium
- Tyre marks and indentations from plantPlot 9 drive · Surfacing · Medium
- Trench reinstatement does not match the surfacePlot 9 frontage · Surfacing · Medium
- Oil stain on the blocksShared drive · Paving · Low
- Mortar splashes on the pavingPlot 5 drive · Paving · Low
- Temporary signage and cable ties leftPlot 4 frontage · Site team · Low
- Slab raised, trip hazardShared path · Paving · High
- Dropped kerb step over 6 mmShared drive entrance · Groundworker · High
- Drain cover not in line with the ground, rocksPlot 7 drive · Drainage · High
- Gully full of debrisPlot 4 frontage · Drainage · Medium
- Gully slow to drainPlot 6 frontage · Drainage · Medium
- Surface water does not reach the gully, bucket testShared drive · Groundworker · Medium
- Permeable paving does not soak throughVisitor bays · Paving · Medium
- Inlet blocked by overgrown plantingSuDS feature · Landscaper · Medium
- Fence panel leaningPlots 4 and 5 boundary · Fencing · Medium
- Fence post loosePlots 5 and 6 boundary · Fencing · Medium
- Gravel board missingPlot 6 boundary · Fencing · Low
- Gap under the fencePlot 7 boundary · Fencing · Low
- Fence not in the position shown on the planPlot 8 boundary · Fencing · High
- Gate will not latch shutPlot 9 side gate · Fencing · Medium
- Timber not protectedPlot 9 side gate · Fencing · Low
- Retaining wall crackedPlot 8 rear · Groundworker · High
- Turf not evenly laid, gaps showingPlot 4 rear garden · Landscaper · Medium
- Bare soil where turf should bePlot 5 rear garden · Landscaper · Medium
- Dip in the turfPlot 6 rear garden · Landscaper · Low
- Two shrubs deadPlot 7 front garden · Landscaper · Medium
- Planting differs from the approved planSite entrance · Landscaper · Medium
- Tree root flare buried by mulchSite entrance · Landscaper · Medium
- Outdoor light not workingPlot 5 rear · Electrician · Medium
- Patio slabs rock underfootPlot 6 rear · Paving · Medium
- Step at the entrance, bins cannot be wheeled outBin store · Groundworker · Medium
- Meter box door will not shutPlot 8 side · Site team · Low
- Bay markings missingVisitor bays · Surfacing · Low
- Builder’s materials leftPlot 7 rear garden · Site team · Low
What a good snag entry says
A photo reference beats a paragraph.
Where
Room, wall or grid line, so someone who missed the walk can find it.
What, in one line
What is wrong, as you would say it to the person fixing it.
Who puts it right
The trade or company that owns it.
When and who checks
A date to finish by, and who sees it done.
Two ways to keep your snag list
- Print the blank and walk the job
- Hand each trade its own sheet
- Photos stay on someone’s phone
On your phone with Site Issues
- Each snag keeps its number
- Photos stay with the snag
- One list per project
Snag list questions
Are these real jobs?
No. The company, project and rows are made up. The kinds of snag come from published snagging checklists and warranty tolerances.
Can I use one as it is?
No. Walk your own job and write down what you find. Use an example to see the level of detail, then change the locations, trades and people.
Snag list or snagging list?
The same thing. UK sites use both, and some call it a snag sheet or a defects list.
What goes on a handover list?
Everything still open at the walk with the client, room by room, plus documents still to come, such as O&M manuals and as-built drawings. A signed list records that walk. It is not a practical completion certificate.
Excel or Word?
Excel if you want to sort or filter by trade. Word if you want to edit the page as it prints. Both open with the same rows as the PDF.
Where is the blank?
On the snag list template, with your logo and columns.