Permit to work examples
Completed permits for common jobs: both sheets, filled in and cancelled. Read one, download it, then issue your own from the blank.
Get the blankChoose a permit
- Torch-on felt on a flat roofA propane torch on the roof of an occupied office, with a fire watch to the two-hour check.2 pages, checked 2 November 2026
- Welding a steel beam in a basementMIG welding during a refurbishment, with fume extraction and the office above checked too.2 pages, checked 2 November 2026
- A new drain in a yard, near live servicesHand digging near a cable and a gas pipe, over two days, with inspections after rain.2 pages, checked 2 November 2026
- Entering a foul manhole to join a drainTwo people in a 2.4 m manhole, with gas tests, a top person and a winch at the surface.2 pages, checked 2 November 2026
- A night fit-out in a bank branchA shopfitting team replacing a reception desk and two partitions after closing, with one intruder alarm zone off and security on site.2 pages, checked 2 November 2026
- A roof survey behind a barrierA surveyor and an assistant on a large flat felt roof with roof lights and an open edge, inside a barrier set and struck on the same permit, with wind readings throughout.2 pages, checked 2 November 2026
- Changing a sub-main boardA board with two incomers and a generator inlet, with both firms locked on through a lock-out box, proved dead before the permit was issued.2 pages, checked 2 November 2026
Roofing hot work permit example
Torch-on felt on a flat roof
A propane torch on the roof of an occupied office, with a fire watch to the two-hour check.
What to change
- Your site and exact location
- The precautions that do not apply, and why
- Who issues it and who accepts it
Sources
Checked
The same sheet as text
Worked example of a made-up job. Not a permit.
Sheet 1: Hot Work Permit
Hollins & Reed Contracting Ltd
- Permit no.HR-0417
- SiteUnit 3, Canal Side Business Park
- Exact locationFlat roof over the offices, north end
Details
- ContractorHollins & Reed
- Issued toPriya Shah
- Valid from12/10/26 08:00
- Valid to12/10/26 17:00
- RAMS refHR-RAMS-07
- Fire risk refHR-FRA-03
The work
- Hot work to be doneTorch-on felt cap sheet to 30 m² of flat roof, with parapet upstands and two outlets.
- MethodOne torch, one cylinder. Laps rolled. Upstands on low flame, gaps behind sealed first.
- Why cold methods failCold-applied sheet and a heat gun failed a test patch on 9 October. Neither bonded.
Hazards
- Combustibles in 10 mYes
- Openings and voidsYes
- Flammables nearbyYes
- Dust or lintNo
- Roof or wall liningsYes
- Below, behind wallsYes
- Sprinklers, alarmsYes
- Occupied buildingYes
Precautions
- Combustibles removed or coveredDone: yes. By: Priya Shah
- Floors swept, combustible floors coveredDone: yes. By: Priya Shah
- Openings and voids sealedDone: yes. By: Priya Shah
- Non-combustible screens upDone: no. By: Not needed. Open roof
- Detectors isolated: who restores themDone: yes. By: Dan Hollins, zone 3 only
- Gas cylinders secured and checkedDone: yes. By: Priya Shah
- Two extinguishers within reach: typeDone: yes. By: Two 9 kg dry powder
- Fire watcher named, breaks coveredDone: yes. By: Reece Ollerton
- How to raise the alarmDone: yes. By: Break glass, ring 999
- Hot work ends 2 hours before day endDone: yes
- Others shielded from arc and sparksDone: no. By: Not needed. No arc
- Fume: LEV or RPEDone: no. By: Not needed. Outdoors
- Permit shown at the workDone: yes
Equipment
- ExtinguishersYes
- Fire blanketYes
- Hose reelNo
- Gas detectorNo
- Thermal cameraYes
- Welding screensNo
Other conditions
- Cylinder on a heat-insulating base, 3 m from the torch. Never use water on a bitumen fire.
- Zone 3 goes back on for any break and when hot work ends. Client told first. Site office 0161 496 0142.
Sign-off
- Issued: precautions checkedName: Dan Hollins. Signature: signed. Date: 12/10/26. Time: 07:50
- Accepted: permit understoodName: Priya Shah. Signature: signed. Date: 12/10/26. Time: 07:55
Sheet 2: Hot Work Permit
Hollins & Reed Contracting Ltd
- Permit no.HR-0417
- SiteUnit 3, Canal Side Business Park
- Exact locationFlat roof over the offices, north end
Fire watch: continuous for 1 hour, then a check at 2 hours
- During breaksTime: 12:15 to 12:45. By: Reece Ollerton. Result: Torch off for the break. Watched roof and void. Nothing found.
- End of hot workTime: 14:45. By: Reece Ollerton. Result: Torch off, cylinder shut. Continuous watch started.
- 1 hour after the endTime: 15:45. By: Reece Ollerton. Result: Watched roof and void the whole hour. Thermal image shows no hot spots.
- 2 hours after the endTime: 16:45. By: Dan Hollins. Result: Roof and roof void checked. Nothing found.
Cancellation
- Work stopped at14:45 on 12 October. Cap sheet finished.
- Area checked, images keptRoof and roof void walked at 16:45. Three thermal images in the job file.
- Detectors restored byDan Hollins. Back on 12:15, off again 12:45, back on 14:50. Panel normal.
- Equipment removedTorch, hose and cylinder off the roof by 15:20.
Handback
- Area returned toThornley Vale Estates Ltd, site keyholder
- NotesOutlets open again. Nothing to report.
Sign-off
- Extended: new end timeName: Not extended
- Cancelled: area checkedName: Dan Hollins. Signature: signed. Date: 12/10/26. Time: 16:50
- Handed back: area returnedName: Dan Hollins. Signature: signed. Date: 12/10/26. Time: 16:55
What a completed permit shows
- Who issued it and who accepted
- What was checked first, and what did not apply
- The record while it ran (fire watch, gas tests, inspections)
- How it was cancelled and handed back
Two ways to run your permits
Keep the day’s record
Note each permit issued and cancelled in Site Diary, with photos of the area.
Open Site DiaryPermit to work example questions
Are these real permits?
No. Every job, company, person and address here is made up, and so is every reading. They show what goes in each box.
Can I issue one of these as it is?
No. A permit is written for one job, one place, one time. Issue your own from the blank, after checking the place yourself.
What makes a permit invalid?
It covers only the job, the place and the time written on it. If the time runs out or the work changes, stop, then extend it or issue a new one once it is checked as safe. HSE: HSG250.
How long does a hot work fire watch last?
At least an hour of continuous watching after the hot work ends, then at least one more check two hours after the end. HSE: HSG168.
Where is the blank?
On the permit to work template page. Add your logo, then print it or download it.