Simple day site diary template
Choose a design
Thirteen site diary sheets, daily and weekly
A daily page suits a busy site, where each day needs room for labour, deliveries and delays. A weekly sheet suits a small job, with a few lines a day. Hour by hour suits work that runs to the clock, such as a pour, a crane day or a shutdown.

Simple day
Work done, who was on site and hold-ups, with room to write
Use this layout
Hour by hour
A line for each hour, from 06:00 to 22:00
Use this layout
Day with labour
Each trade and its numbers, then the work done
Use this layout
Landscape day
One wide page of work done, with the hours on site
Use this layout
Week at a glance
Each day’s work, labour and weather across one page
Use this layout
Labour return
Each trade’s headcount by day, totalled for the week
Use this layout
The gate log and the labour return are not diaries: one records the deliveries and visitors at the gate, the other each trade’s numbers across the week.
What a site diary records

Weather
Morning and afternoon, with the temperature, so a day lost to rain or wind shows on the page.
Labour
Each trade, its company, how many were on site and their hours. The labour return adds these up for the week.
Work done
Each area, then the work carried out there, with the times and quantities, such as a slab’s area and depth.
Deliveries
The time, what arrived, from whom and the ticket number, so a short load or a late wagon can be traced.
Delays
What stopped work, when and for how long, and what it cost in hours.
The same page holds the plant on site, the visitors and the instructions received, each with a time and a name. Write it on the day and sign it at the end of the day. A page written up a week later is harder to rely on when a delay or a variation is argued over.
No law names a site diary. A principal contractor must plan, manage and monitor the construction phase (CDM 2015, regulation 13), and a dated page for each day is a plain way to show it.
Three site diary examplesSite diary questions
Is it free?
Yes. There is no account and no email to give. The files are made in your browser.
What should a site diary record?
Who was on site, the weather, the work done, delays and instructions, deliveries, visitors, and any accidents or near misses. Write it on the day, with times.
Daily or weekly site diary?
A daily page suits a busy site, where each day needs room for labour, deliveries and delays. A weekly diary suits a small job, with a few lines a day.
Can I change it after downloading?
Yes. The Excel and Word files open with the same title, boxes and sections, ready to edit. Each prints on A4, and a sheet with more rows runs on to a second page.
Is my logo uploaded?
No. It is read and resized on this device and goes only into the files you download, or save to your own Drive or OneDrive. The last design, logo included, is kept in this browser for next time.
Do I have to keep a site diary?
No law names a site diary. Where there is a principal contractor, CDM 2015 regulation 13 says they must plan, manage and monitor the construction phase. A dated record of each day is a plain way to show it.