Retail unit fit-out construction phase plan example
All 2 examplesStrip-out and fit-out of a vacant single-storey retail unit
Four contractors strip an empty shop back to the landlord’s shell and fit it out. Notified to HSE.
Sources
- HSE: Managing health and safety in construction (L153), Appendix 3
- Construction (Design and Management) Regulations 2015: regulations 5, 6, 12, 13 and 30 to 32, Schedules 2 and 3
- HSE: Fire safety in construction (HSG168)
- HSE: Provision of welfare facilities during construction work (CIS59)
- HSE: Construction dust (CIS36)
- Control of Substances Hazardous to Health Regulations 2002: regulation 11
Worked example of a made-up job. Not a plan for a real site.
Refurbishment construction phase plan
Revisions
- Rev 0, 19 December 2025First issue. Dan Hollins
- Rev 1, 7 January 2026Cabins moved to the rear yard. Deliveries by the rear doors. Dan Hollins
- Rev 2, 9 February 2026Rear doors repaired one leaf at a time 10 to 13 February, so the exit stays open: board deliveries held to 16 February. Dan Hollins
The project
- CompanyHollins & Reed Contracting Ltd
- ClientThornley Vale Estates Ltd
- Site addressUnit 7, Tanhouse Retail Park, Stockport
- Description of the workStrip-out of a vacant, stand-alone, single-storey shop to the landlord’s shell, then fit-out with new services. Scheduled: 55 working days, 14 people at most, 560 person days.
- Principal designerGreave Street Architects Ltd, appointed in writing 3 November 2025
- Principal contractorHollins & Reed Contracting Ltd, appointed in writing 24 November 2025
- Other key team membersSite manager: Dan Hollins, 0161 496 0142. Assistant: Priya Shah. Client’s agent: Owen Tattersall, 0161 496 0188.
- Key datesStart 12 January 2026. Strip-out done 30 January. First fix done 27 February. Handover 27 March 2026.
- Notified to HSEYes, 15 December 2025. Notice on the site office wall.
Health and safety aims
- Nobody on the job is hurt or made ill by the work. Nobody from the car park gets onto the site. Anyone on site can stop work they think is unsafe, and will be backed for it.
Site rules
- Nobody works until inducted and signed in. Boots and hi-vis on site; eye protection, gloves and masks as your RAMS says. Park in the rear yard. Keep the gates shut. Radios off. No phones on a tower or steps. No smoking or vaping on site. Nobody goes on the roof. Hot works only on a permit from Dan Hollins.
Contractors and specialists
- Brinnington Soft Strip LtdTrade: Strip-out. Contact: Lee Bramhall, 0161 496 0151. Start: 12 January
- Davenport Rise Electrical LtdTrade: Lighting and power. Contact: Callum Whittle, 0161 496 0152. Start: 12 January
- Tanyard Air LtdTrade: Heating and ventilation. Contact: K Tunnicliffe, 0161 496 0153. Start: 19 January
- Offerton Interiors LtdTrade: Partitions, ceilings, floors, decorating. Contact: Mark Etchells, 0161 496 0154. Start: 2 February
Working together
- Site meeting for all contractors every Monday at 08:00, chaired by Dan Hollins. Handover at 16:30 each day: who is where tomorrow. Each contractor gives Dan Hollins its RAMS before starting, and he checks it against the work around it. Workers raise anything at the Monday meeting or with their foreman, and a note of what was done goes up on the site board in the office.
Site induction
- Given by Dan Hollins or Priya Shah before anyone starts. It covers the job, who runs it, first aid, reporting accidents, daily talks, how to raise a concern, the exits, the fire points, dust and the permit for hot works. Visitors get a short version and stay with an escort.
Induction record
- Dan HollinsCompany: Hollins & Reed Contracting Ltd. Date: 12 Jan 2026. Signed: D Hollins
- Priya ShahCompany: Hollins & Reed Contracting Ltd. Date: 12 Jan 2026. Signed: P Shah
- Reece OllertonCompany: Hollins & Reed Contracting Ltd. Date: 12 Jan 2026. Signed: R Ollerton
- Lee BramhallCompany: Brinnington Soft Strip Ltd. Date: 12 Jan 2026. Signed: L Bramhall
- Callum WhittleCompany: Davenport Rise Electrical Ltd. Date: 12 Jan 2026. Signed: C Whittle
- Owen Tattersall (visitor)Company: Thornley Vale Estates Ltd. Date: 14 Jan 2026. Signed: O Tattersall
- Kieran TunnicliffeCompany: Tanyard Air Ltd. Date: 19 Jan 2026. Signed: K Tunnicliffe
- Mark EtchellsCompany: Offerton Interiors Ltd. Date: 2 Feb 2026. Signed: M Etchells
Welfare facilities
- Hired cabins in the rear yard, on mains water and drainage, in place before 12 January: site office, two flushing toilets, basins with hot water, soap, towels, drinking water, lockers and drying, and a heated rest room with tables, chairs with backs, kettle and microwave.
Fire and emergency procedures
- The wired-in alarm stays on as long as possible; temporary linked call points and sounders go in before it comes out. Fire point at each exit. On the alarm, leave to the yard gate. Priya Shah checks the signing-in sheet. Exits stay clear. First aiders: Dan, Priya. Ring 999, then Dan.
Work involving particular risks
- Burial, engulfment or falling from a height, particularly aggravated by the work or the siteNot on this job. Single storey: no floor edge, floor void, riser or shaft. Tower and step work only. Nobody goes on the roof.
- Chemical or biological substances of particular danger, or needing health monitoringYes: drilling concrete and cutting blockwork. Extraction, masks, COSHH assessments, health checks where needed. Asbestos survey: none found. If unsure, stop.
- Ionising radiation with controlled or supervised areasNot on this job. No radiography or similar work.
- Near high voltage power linesNot on this job. No overhead lines over the unit or the yard.
- Risk of drowningNot on this job. All work is indoors, with no water nearby.
- Wells, underground earthworks and tunnelsNot on this job. Nothing is dug.
- Divers on a system of air supplyNot on this job. No work in water.
- Caissons with a compressed air atmosphereNot on this job. No caissons.
- ExplosivesNot on this job. No explosives or cartridge tools.
- Assembly or dismantling of heavy prefabricated componentsNot on this job. No crane. Everything comes through the rear doors in pieces.
Review and revision
- Dan Hollins reviews the plan after each Monday meeting, and whenever the work, the trades or the access change. A new revision goes to every contractor and to the principal designer, and the table on the cover says what changed.
Choose a job
- Two-storey rear extension on a lived-in semi A homeowner stays in the house while a builder, a roofer, a scaffolder and an electrician add two storeys at the back.
- Strip-out and fit-out of a vacant single-storey retail unit Four contractors strip an empty shop back to the landlord’s shell and fit it out. Notified to HSE.
What a finished plan looks like
This plan is five pages long. The rear extension plan is one page: the plan grows with the job.
- Revisions
- Three lines: first issue and two changes, each with its date.
- A plan that never changes was not kept up. Short lines are enough.
- The project
- The team, both written appointments, the dates and the figures for notification.
- A commercial client appoints in writing, so the dates are here. 560 person days is why the job was notified.
- Health and safety aims
- Three aims for this job.
- A slogan would fit any job. These name the car park outside.
- Site rules
- Rules for this site, such as the gates and staying off the roof.
- Four lines. Each one is a rule someone here could break.
- Contractors and specialists
- Four firms, their trade, a name and a number, and the day each starts.
- The table the client’s principal designer looks for first.
- Working together
- The Monday meeting, the daily handover and how workers raise things.
- The law asks for cooperation and for workers to be consulted: these are the arrangements.
- Site induction
- Who gives it and what it covers.
- It should be about this site, so the exits and fire points are named.
- Induction record
- One line a person, in the order they arrived. Only the first few are shown; everyone signs the same sheet.
- Shows the induction took place. The law does not set its columns.
- Welfare facilities
- What is in the cabins and where they stand.
- In place before the first day.
- Fire and emergency procedures
- How the alarm is raised through the job, where to meet, who checks the names and who to ring.
- Three lines are enough for one storey with two exits.
- Work involving particular risks
- All ten rows answered. One applies; nine say why not.
- A row left empty could mean no, or could mean nobody looked.
- Review and revision
- When the plan is reviewed and who gets a new one.
- The plan has to keep up with the job.
What the plan leaves out
Risk assessments and method statements
HSE’s guidance (L153, Appendix 3) says the plan is not generic risk assessments or detailed method statements. Keep those as their own documents. The RAMS examples show what they look like.
The health and safety file
A separate record of the finished job, for whoever works on the building next. On a project with more than one contractor the principal designer prepares it, and it goes to the client at the end.
Pre-construction information
What the client provides about the site and the work before it starts. The plan is written from it and does not replace it.