RAMS examples

Worked examples for common jobs, written with our builder. Read, download, adapt.

Build your own

Choose a job

Electrical RAMS example

Electrical second fix and testing in a house refurbishment

Lived-in 1970s house, accessories and consumer unit fitted, one circuit dead at a time, tested dead then live before handover.

What to change

  • Company, people, site and dates
  • Whether power must stay on for anyone
  • The supply and earthing arrangement
  • Bathrooms and other special locations
  • How it is notified where you are
  • The BS 7671 edition on the certificate
  • Emergency arrangements

Sources

Checked

  1. ComplyOnSitecomplyonsite.comWORKED EXAMPLE: RISK ASSESSMENT AND METHOD STATEMENTElectrical second fix and testing in a houserefurbishmentHollins & Reed Electrical Ltd · 12 to 14 October 2026 · In charge: Dan HollinsWorked example. Change it to fit your job before you use it.Job detailsCompanyHollins & Reed Electrical LtdSite and work area14 Elm Road, M21Planned dates12 to 14 October 2026CustomerMr and Mrs ShawIn charge on siteDan HollinsTeamTwo people: Dan Hollins, electrician, leads and tests; Priya Shah,electrician, stays with him for every live test.WorkElectrical second fix and testing in a house refurbishmentPrepared byDan HollinsSignatureDateWork and boundariesAlter or replace electrical equipment, replace a consumer unit, inspect or test a fixed installation.Areas: Kitchen, hall and lounge circuits; Hall cupboard: consumer unit and meter tailsWorking arrangementAccess: steps or a ladder.Working height: ceiling lights at about 2.4 m.Ground or floor: level timber floors under dust sheets.Other people will be using the area.Mr and Mrs Shaw stay at home; we agree what goes off and when, each morning. Other tradesstay off a circuit while it is under test. Tools run on 110 V or battery. Labels are not trusted: eachcircuit is identified before it is isolated. The asbestos survey covers the old board and theWorked example. Change it to fit your job before you use it.Page 1 of 7
  2. Example: Electrical second fix and testing in a house refurbishmentComplyOnSitetextured ceilings. Records: Electrical Installation Certificate with the schedule of test results, andnotification through our competent person scheme.Emergency arrangementsThere is no site alarm and the smoke alarms may be off while we work, so shout “fire”. Get out bythe front door and meet at the gate of No. 14. Count Mr and Mrs Shaw and the dog. Electric shock:do not touch the person until the supply is off; main switch at the consumer unit in the hallcupboard. First aider: Priya Shah, kit in the van. Check you have a mobile signal on day one. PriyaShah rings 999, gives 14 Elm Road, M21, and meets the crew at the gate; if she is the one hurt, DanHollins does. Problem at the cut-out: ring the network operator on the number on the job sheet.Planned method1Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active workarea. Keep entrances and escape routes clear.2Keep people clear of the workAgree how people get past or around the work while it is going on. Put barriers or signs wherea route crosses the work. Do not leave open work unattended.3List the rooms and circuits to finishList the rooms and circuits you are finishing, on the cables run at first fix. Check the design orproduct instructions for what you are fitting.4Assess the existing installationCheck the existing equipment, circuits, earthing and bonding before fitting the new unit.Record any defects, and anything you could not check.5Agree the test boundaryWrite down the circuits to be tested and who tests them. Keep other trades off a circuit while itis under test.6Check for asbestos before you disturb anythingCheck the asbestos survey covers exactly what you will disturb, to the full depth. Register only,or nothing: get a refurbishment survey or a sample first. Read what it says about walls, ceilings,boards and service routes. No survey, or a material you do not recognise: stop and get itchecked.7Use the ladder or stepsCheck the ladder or steps before use. Place them on firm, level ground. Keep three points ofcontact while climbing. Reposition them instead of overreaching. Do not carry loose tools ortins up; hand them up or use a belt.8Arrange supply-side isolationConfirm who can isolate the incoming supply before removing the old unit. Treat supply-sideconductors as live until that isolation is complete.Worked example. Change it to fit your job before you use it.Page 2 of 7
  3. Example: Electrical second fix and testing in a house refurbishmentComplyOnSite9Isolate and prove deadFind every supply that feeds the work, switch it off and lock it off before you open or touchanything. Prove your tester on a known live supply, test every conductor at the work point,then prove the tester again.10Keep it locked off while it is openKeep the supply locked off while the item is open, so nobody can put it back on. Test at thework point again before you touch it.11Keep dangerous circuits offReview each affected circuit before reconnection. Keep a circuit safely out of service if itsdefect creates danger.12Use suitable test equipmentCheck the instrument, leads, probes, ratings and settings before connecting. Keep tips andconnections controlled at the test points.13Label and replace the unitIdentify every circuit before disconnection. Install the agreed assembly and reconnect only thecircuits in scope.14Fix and terminate the sockets, switches and lightsFix the accessories and light fittings, and terminate each one on the cables run at first fix.Check every terminal, protect the cable where it enters each box, and close every enclosure.15Inspect the change before it goes liveInspect the completed work and arrange the testing it needs before it goes back on. Recordanything left disconnected or out of service.16Do dead tests firstApply safe isolation to the agreed circuit boundary and prove it dead before dead tests. Test inthis order: continuity of protective conductors and ring finals, insulation resistance, polarity. Ifone fails, correct it and repeat the tests before it. Protect or disconnect sensitive equipmentand record temporary disconnections.17Control a justified energised testComplete dead checks first and define the test boundary and precautions. Test live only as faras you need to: Ze, polarity at the origin and RCD operation. Do not work alone. Keep peopleout while the test is energised, then re-isolate before adjustment.18Inspect and test the new unitComplete the inspection and testing the unit needs before it goes back into service. Update thecircuit schedule.19Record actual results and limitsRecord readings, defects, tests not completed, temporary disconnections and actions required.The tester decides from the actual results whether it can go back into service.Worked example. Change it to fit your job before you use it.Page 3 of 7
  4. Example: Electrical second fix and testing in a house refurbishmentComplyOnSite20Finish the tests and functional checksComplete the required tests and functional checks. Check covers, guards, labels, fire stoppingand connections. Give actual results, defects and restrictions to the customer or site contact.Do not certify unchecked work.21Issue the certificateIssue the Electrical Installation Certificate and its schedules from the actual results, and givethem to the customer with the labels. Notify the work through the scheme or building controlwhere it needs it.22Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell thecustomer or whoever runs the site when the work is complete.Risk assessmentHazardWho might beharmed and howControls in placePeople entering thework area or trippingover materialsStep 1Workers,occupants andvisitorsMark or barrier the active work area. Store tools and materialsaway from access routes.People using thebuilding or passingby walking into thework or over what itleavesStep 2Occupants,visitors, membersof the public andworkersKeep the barriers and signs up while the work is active. Givepeople a clear way round where their normal route is blocked.The wrong circuit oran unsuitableaccessory causesshock, fire or loss ofprotectionStep 3Electricians andpeople in thebuildingStay inside the agreed scope. Stop for an unexpectedarrangement or missing information.A hidden defect orinadequate supplymakes thereplacementdangerousStep 4The electrician andhouseholdersUse a competent pre-work assessment. Hold the replacementwhere a safety defect remains unresolved.Someone works onor energises a circuitthat is under testStep 5The tester, othertrades and peoplein the buildingCheck the list of circuits against the design. Record any circuityou could not test.Worked example. Change it to fit your job before you use it.Page 4 of 7
  5. Example: Electrical second fix and testing in a house refurbishmentComplyOnSiteHazardWho might beharmed and howControls in placeBreathing asbestosfibres from oldboards, sheets,sealants or insulationStep 6The team andanyone in thebuildingDo not cut, drill or break any material until it is confirmedasbestos free. Licensed work is not for this method; hand it toa licensed contractor.Falling from theladder or steps; toolsor tins dropped onpeople belowStep 7The personworking from it, ifthe feet slip orthey overreach toone side. Anyonepassing or workingunder the ladderwhile it is in use.Secure the equipment where it could move. Keep the base andarea below clear.Incoming tails remainlive when the mainswitch is offStep 8The electricianArrange the authorised supply isolation in advance. Do notremove a supplier seal or improvise the isolation.A live conductor orbackfeed causeselectric shock, burnsor an unexpectedstartStep 9The electrician andanyone near theworkLock off the supply and put your own tag on it. Stop if youcannot find every supply or cannot get a dead reading.A live conductorcauses electric shockor burns duringremovalStep 10The electricianUse the safe isolation steps for this installation. Leave yourlock and warning tag on while the work goes on.A known dangerouscircuit is energisedafter the boardchangeStep 11Householders andanyone using theinstallationLabel every circuit left disconnected. Tell the customer whatremains unsafe and why.Unsuitable orwrongly setequipment causesarcing, shock or afalse resultStep 12Tester and peoplenear the testUse equipment suited to the actual installation. Do not continueif it is damaged or its rating is unclear.A crossed circuit,wrong device or poortermination causesshock, fire or loss ofsupplyStep 13The electrician andhouseholdersKeep circuit identity through removal and reconnection. Followthe assembly instructions and supplied design.Worked example. Change it to fit your job before you use it.Page 5 of 7
  6. Example: Electrical second fix and testing in a house refurbishmentComplyOnSiteHazardWho might beharmed and howControls in placeA loose, wrong ordamaged terminationoverheats or leavesthe installationunsafeStep 14The electrician andpeople in thebuildingUse the specified component and termination method. Keepcovers, cable restraint and protective connections complete.Unverified work or anincomplete circuit isreturned to useStep 15The electrician andeveryone usingthe installationDo not energise work that has failed verification. Tell thecustomer or site contact about defects and restrictions.Unexpected voltageor a damagedconnected itemcauses shock, fire orequipment damageStep 16Tester and anyonenear theinstallationKeep the boundary secured throughout the dead tests.Discharge stored energy where the test requires it.Someone reaches acircuit while it isenergised for the testStep 17Tester, occupantsand other tradesUse a temporary test area with barriers or supervision. Stop ifthe safe test arrangement cannot be maintained.Unverifiedreconnection ormissing restrictionsmisleads the nextuserStep 18The electrician andhouseholdersRecord actual results, defects and circuits left off. Do notinvent readings or certification.Copied or inventedresults hide dangerand return an unsafecircuit to useStep 19Tester, client andfuture maintainersWrite only what was inspected or measured. Keep records withthe actual results and restrictions.Incomplete orunverified work isreturned to use andleaves people orproperty unprotectedStep 20The electrician,the customer orsite contact andpeople using thebuildingRecord what was tested, what remains out of service and whoaccepted the hand-back. Do not energise or certify a failed orincomplete installation.The customer has notrue record of whatwas installed andtestedStep 21The customer andfuture electriciansDo not issue a certificate for anything not tested. Write in anycircuit left off.Worked example. Change it to fit your job before you use it.Page 6 of 7
  7. Example: Electrical second fix and testing in a house refurbishmentComplyOnSiteHazardWho might beharmed and howControls in placeDebris, tools orunfinished work leftin the areaStep 22Workers,occupants andvisitorsRemove waste by the agreed route. Record and protect anyunfinished work.Worked example. Change it to fit your job before you use it.Page 7 of 7

Method statement and risk assessment, side by side

Method statement The work in order, step by step.
Risk assessment Each hazard, who could be harmed, the controls in place and any further action.

Use an example, then make it yours

HSE says not to just copy an example and put your company name on it: that would not satisfy the law or protect your people.

The builder asks about your site and rewrites the hazards and steps.

RAMS example questions

Are these real jobs?

No. Every job, company, person and address here is made up. Each one is a worked example written with our builder, and every page says so.

Can I use one as it is?

No. Your site, your people and your emergency arrangements will be different. Change it to fit your job before anyone works to it.

Why do they carry ComplyOnSite branding?

They are made with our builder and printed in its standard design. A RAMS you build yourself carries your company name.

Word or PDF?

Both. Word if you will change the wording yourself, PDF to read or print. Or press Use this and edit it in the builder, then download your own copy.

Where is the blank?

On the RAMS template page. These examples are all filled in.

How were they checked?

Each one is read against published guidance, mainly from HSE, for its facts, the order of the work and its emergency arrangements. The sources are listed beside it. If a document changes, it comes off this page until it has been checked again. The check covers the example, not your job.