Scaffolding method statement example

Finished method statements for common jobs: the steps in order, who does each, and the emergency arrangements. Read one, download it, or build your own.

Build your own

Choose a job

Scaffolding method statement example

Erecting an independent tied scaffold on a two-storey house

Independent tube and fitting scaffold to a TG20 compliance sheet, family at home, rescue kit on the wagon.

What to change

  • Company, people, site and dates
  • Lifts, height and what the users will load on it
  • Wall construction and ties
  • Pavement or road: licence and public protection
  • Overhead lines
  • Rescue plan and kit
  • Emergency arrangements

Sources

Checked

  1. ComplyOnSitecomplyonsite.comWORKED EXAMPLE: METHOD STATEMENTErecting an independent tied scaffold on atwo-storey houseHollins & Reed Scaffolding Ltd · 12 to 13 October 2026 · In charge: Dan HollinsWorked example of a method statement. Change it to fit your job before you use it.Job detailsCompanyHollins & Reed Scaffolding LtdSite and work area7 Orchard Close, StockportPlanned dates12 to 13 October 2026CustomerMr and Mrs BarlowIn charge on siteDan HollinsTeamThree scaffolders: Dan Hollins leads and checks the scaffold beforehandover; Tom Ellis and Priya Shah work with him.WorkErecting an independent tied scaffold on a two-storey houseRisk assessmentErecting an independent tied scaffold on a two-storey house: workedexample RAMS, a separate documentPrepared byDan HollinsSignatureDateWork and boundariesErecting. Areas: Front and gable elevations, ground to eaves, two lifts; Pavement outside No. 7, keptbehind barriersWorking arrangementErection fall protection: Advance guardrail system.Other people will be using the area.Independent tied scaffold to a TG20 compliance sheet: two lifts, general purpose 2 kN/m², nosheeting. The family stays at home; the front door stays clear as their way out. The exclusionzone and public protection go up before anything comes off the wagon. The highway licence forWorked example of a method statement. Change it to fit your job before you use it.Page 1 of 3
  2. Example: Erecting an independent tied scaffold on a two-storey houseComplyOnSitethe pavement is held. Overhead lines were checked on the survey. The first-lift ladder comes offout of hours.Emergency arrangementsFall into a harness: Tom Ellis and Priya Shah recover the person from the lift above, using the rescuekit on the wagon. 999 comes second: do not wait for them to do the rescue. Anyone hurt on the pathor road: stop work, keep people away, close the bay. Scaffold touching an overhead line: stay clear,nobody touches the tube, ring the line owner. Scaffold moving or collapsing: everyone off and keeppeople away. Fire in the house: the family leaves by the front door. First aider: Tom Ellis, kit on thewagon. Dan Hollins rings 999, gives 7 Orchard Close, and meets the crew at the main road junction.Planned method1Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active workarea. Keep entrances and escape routes clear.2Keep people clear of the workAgree how people get past or around the work while it is going on. Put barriers or signs wherea route crosses the work. Do not leave open work unattended.3Check the sheet or design firstKeep the TG20 sheet, maker instructions or design on site. Brief the gang on the build orderand how they will stay protected.4Set the boundary before work startsFence off the base and the area below the work. Protect any public route, traffic route oroverhead line beside it.5Check for asbestos before you disturb anythingCheck the asbestos survey covers exactly what you will disturb, to the full depth. Register only,or nothing: get a refurbishment survey or a sample first. Read what it says about old boards,soffits, sealants or insulation where ties and fixings go. No survey, or a material you do notrecognise: stop and get it checked.6Find and isolate hidden servicesFind cables and pipes before you disturb anything: drawings, then a detector. Mark what youfind. Not sure what is there? Turn the supply off, or do not start. Have cables and gas isolatedby the right person and prove them dead before you start.7Check the weather before you startDo not lift or fix scaffold and loose materials in strong wind. Stop in heavy rain, ice or lightning.8Stop things falling on people belowKeep people out of the area below the work so nobody walks under the tubes, boards, fittingsand tools. Keep toe boards and guards in place on any platform, and lanyard tools where youcan.Worked example of a method statement. Change it to fit your job before you use it.Page 2 of 3
  3. Example: Erecting an independent tied scaffold on a two-storey houseComplyOnSite9Unload and stack on the agreed areaTake nothing off the wagon until the boundary is up. Stack it on the agreed area and protectthe pavement.10Set a firm, level basePut sole boards and base plates under every standard where the ground needs support. Checkthe ground or supporting structure before building up.11Build the base lift with fall protectionNobody steps onto a new lift until the fall method in this document is in place. Board the lift andfit guardrails and toe boards before it is used. Anyone within 1 m of an unprotected edge clipson.12Use advance guardrailsFit the advance guardrail from the lift below before anyone steps onto the new lift. Keep it inplace until the lift is boarded and its own guardrails are in.13Tie and brace the base liftInstall the planned ties and bracing in the order shown on the sheet or design. Keep every tiewithin its stated safe working load.14Fit the access ladder and secure itFit it once the base lift is tied, before anyone works from that lift. It goes 1 m above the landing,at 65 to 75 degrees, and is tied. Out of hours, remove the bottom ladder or board it off.15Use the hoistCheck the hoist's thorough examination report is in date and it can take the weight. Keeppeople out from underneath while a load is up.16Repeat for each liftFor every lift, raise the materials by the agreed route, fit the fall protection, board it, then tieand brace it. Take the ladder up with the build, so nobody climbs the frame.17Block off what is not finishedMark any part that is not finished and physically block the way onto it. Do this before leavingsite, as well as during the work.18Inspect before handing it overCheck the finished scaffold, access, boards, guardrails, ties, toe boards and loadingarrangements. Record the inspection and hand it over with the current tag or record visible.19Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell thecustomer or whoever runs the site when the work is complete.Worked example of a method statement. Change it to fit your job before you use it.Page 3 of 3

The same sheet as text

Worked example of a method statement. Change it to fit your job before you use it.

Erecting an independent tied scaffold on a two-storey house

Job details

  1. CompanyHollins & Reed Scaffolding Ltd
  2. Site and work area7 Orchard Close, Stockport
  3. Planned dates12 to 13 October 2026
  4. CustomerMr and Mrs Barlow
  5. In charge on siteDan Hollins
  6. TeamThree scaffolders: Dan Hollins leads and checks the scaffold before handover; Tom Ellis and Priya Shah work with him.
  7. WorkErecting an independent tied scaffold on a two-storey house
  8. Risk assessmentErecting an independent tied scaffold on a two-storey house: worked example RAMS, a separate document

Work and boundaries

  1. Erecting. Areas: Front and gable elevations, ground to eaves, two lifts; Pavement outside No. 7, kept behind barriers

Working arrangement

  1. Erection fall protection: Advance guardrail system.
  2. Other people will be using the area.
  3. Independent tied scaffold to a TG20 compliance sheet: two lifts, general purpose 2 kN/m², no sheeting. The family stays at home; the front door stays clear as their way out. The exclusion zone and public protection go up before anything comes off the wagon. The highway licence for the pavement is held. Overhead lines were checked on the survey. The first-lift ladder comes off out of hours.

Emergency arrangements

  1. Fall into a harness: Tom Ellis and Priya Shah recover the person from the lift above, using the rescue kit on the wagon. 999 comes second: do not wait for them to do the rescue. Anyone hurt on the path or road: stop work, keep people away, close the bay. Scaffold touching an overhead line: stay clear, nobody touches the tube, ring the line owner. Scaffold moving or collapsing: everyone off and keep people away. Fire in the house: the family leaves by the front door. First aider: Tom Ellis, kit on the wagon. Dan Hollins rings 999, gives 7 Orchard Close, and meets the crew at the main road junction.

Planned method

  1. 1. Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active work area. Keep entrances and escape routes clear.
  2. 2. Keep people clear of the workAgree how people get past or around the work while it is going on. Put barriers or signs where a route crosses the work. Do not leave open work unattended.
  3. 3. Check the sheet or design firstKeep the TG20 sheet, maker instructions or design on site. Brief the gang on the build order and how they will stay protected.
  4. 4. Set the boundary before work startsFence off the base and the area below the work. Protect any public route, traffic route or overhead line beside it.
  5. 5. Check for asbestos before you disturb anythingCheck the asbestos survey covers exactly what you will disturb, to the full depth. Register only, or nothing: get a refurbishment survey or a sample first. Read what it says about old boards, soffits, sealants or insulation where ties and fixings go. No survey, or a material you do not recognise: stop and get it checked.
  6. 6. Find and isolate hidden servicesFind cables and pipes before you disturb anything: drawings, then a detector. Mark what you find. Not sure what is there? Turn the supply off, or do not start. Have cables and gas isolated by the right person and prove them dead before you start.
  7. 7. Check the weather before you startDo not lift or fix scaffold and loose materials in strong wind. Stop in heavy rain, ice or lightning.
  8. 8. Stop things falling on people belowKeep people out of the area below the work so nobody walks under the tubes, boards, fittings and tools. Keep toe boards and guards in place on any platform, and lanyard tools where you can.
  9. 9. Unload and stack on the agreed areaTake nothing off the wagon until the boundary is up. Stack it on the agreed area and protect the pavement.
  10. 10. Set a firm, level basePut sole boards and base plates under every standard where the ground needs support. Check the ground or supporting structure before building up.
  11. 11. Build the base lift with fall protectionNobody steps onto a new lift until the fall method in this document is in place. Board the lift and fit guardrails and toe boards before it is used. Anyone within 1 m of an unprotected edge clips on.
  12. 12. Use advance guardrailsFit the advance guardrail from the lift below before anyone steps onto the new lift. Keep it in place until the lift is boarded and its own guardrails are in.
  13. 13. Tie and brace the base liftInstall the planned ties and bracing in the order shown on the sheet or design. Keep every tie within its stated safe working load.
  14. 14. Fit the access ladder and secure itFit it once the base lift is tied, before anyone works from that lift. It goes 1 m above the landing, at 65 to 75 degrees, and is tied. Out of hours, remove the bottom ladder or board it off.
  15. 15. Use the hoistCheck the hoist's thorough examination report is in date and it can take the weight. Keep people out from underneath while a load is up.
  16. 16. Repeat for each liftFor every lift, raise the materials by the agreed route, fit the fall protection, board it, then tie and brace it. Take the ladder up with the build, so nobody climbs the frame.
  17. 17. Block off what is not finishedMark any part that is not finished and physically block the way onto it. Do this before leaving site, as well as during the work.
  18. 18. Inspect before handing it overCheck the finished scaffold, access, boards, guardrails, ties, toe boards and loading arrangements. Record the inspection and hand it over with the current tag or record visible.
  19. 19. Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell the customer or whoever runs the site when the work is complete.

What a finished method statement says

  • The job and its boundariesWhat is being done, where, and what is not your work.
  • How the work area is set upAccess, shared spaces and who else is around.
  • The steps, in the order they happenOne action to a step, from arrival to sign-off.
  • Who does each stepThe people in charge and the skills each step needs.
  • What happens if something goes wrongWho to call, where to go and how help gets in.

Method statement or risk assessment: which one is this?

This is the method statement: how the job is done, step by step. The risk assessment says what could go wrong and what controls it.

See both together in the Scaffolding RAMS example.

Method statement example questions

Are these real jobs?

No. Every job, company, person and address here is made up, and every page says so.

Can I send one as it is?

No. Your site, your people and your emergency arrangements will be different. Change it to fit your job first.

Where is the risk assessment that goes with it?

In the Scaffolding RAMS example. The method statement names it on page one.

Word or PDF?

Both. Word if you will change the wording yourself, PDF to read or print. Or press Use this and edit it in the builder.

Does a method statement need a risk assessment?

A method statement names the risk assessment it rests on. CDM 2015 does not set a form for either document.

Where is the blank?

On the method statement template page. These examples are all filled in.