Core drilling method statement example

Finished method statements for common jobs: the steps in order, who does each, and the emergency arrangements. Read one, download it, or build your own.

Build your own

Choose a job

Core drilling a flue hole through a cavity blockwork wall

One 125 mm wet core, rig fixed to the inner leaf, through an external wall of a single-storey extension, with the core caught outside.

What to change

  • Company, people, site and dates
  • What the wall is and what is in the cavity
  • Where the hole sits against lintels and the cavity tray
  • Hole size and core weight
  • The rig’s fixing for this block
  • What is under the hole outside
  • Who sleeves and seals the hole
  • Emergency arrangements

Sources

Checked

  1. ComplyOnSitecomplyonsite.comWORKED EXAMPLE: METHOD STATEMENTCore drilling a flue hole through a cavityblockwork wallHollins & Reed Diamond Drilling Ltd · 24 November 2026 (one morning) · In charge: Dan HollinsWorked example of a method statement. Change it to fit your job before you use it.Job detailsCompanyHollins & Reed Diamond Drilling LtdSite and work area6 Alma Road, Stockport: rear extensionPlanned dates24 November 2026 (one morning)CustomerThornley Vale Estates LtdIn charge on siteDan HollinsTeamTwo people: Dan Hollins fixes the rig and drills; Tom Ellis stays outsideby the cones until the outer core is down, on the phone to Dan from thefirst cut, then helps carry out.WorkCore drilling a flue hole through a cavity blockwork wallRisk assessmentCore drilling a flue hole through a cavity blockwork wall: workedexample RAMS, a separate documentPrepared byDan HollinsSignatureDateWork and boundariesCore one 125 mm flue hole from the inside, wet. Areas: Inside face of the rear extension wall, withthe floor below the hole; Paving outside under the holeWorking arrangementAccess: the floor or ground.What the hole goes through: A cavity blockwork wall.Coring machine: On a stand fixed to the structure.The work area will be kept clear of other people.Worked example of a method statement. Change it to fit your job before you use it.Page 1 of 3
  2. Example: Core drilling a flue hole through a cavity blockwork wallComplyOnSiteThe tenant stays in the house with the door to the extension shut; nobody else goes in theextension. The wall is the 2018 extension’s external wall: 100 mm dense block inside, a 100 mmcavity with mineral wool batts, 100 mm rendered block outside. The heating engineer’s drawingputs the hole centre 1.6 m above the floor, reached from the floor, 900 mm below the lintel lineand clear of the cavity tray. The extension’s socket circuit runs in the wall 600 mm from the holeon the electrician’s drawing. A cable detector on both faces agrees, and a CAT scan along thefoot of the wall outside shows nothing rising up it near the hole. The heating engineer’s drawingshows no gas or water pipe in this wall. The landlord’s electrician locks that circuit off at theconsumer unit while we drill, and puts it back on when the rig is off the wall, so the transformerruns from a hall socket on the house circuit, with the lead taped down under the door. One holetakes under an hour with the door to the garden open, so water does the work and no mask isneeded. Each core is 125 mm across, 100 mm long and about 2.5 kg, taking a dense block atabout 2,000 kg/m³. Both are lifted by hand once the bit has stopped. The heating engineersleeves and seals the hole when the flue goes in.Emergency arrangementsAnyone hurt, or an electric shock: stop the rig and switch off at the transformer, then Tom Ellis rings999, or Dan Hollins if Tom is the one hurt, and gives 6 Alma Road, rear extension. Whoever ringsstays with the casualty. Dan Hollins is the first aider, and the kit is in the van on the drive. The tenantmeets the crew at the front gate and brings them round the side path, which stays clear. Fire: leaveby the door to the garden, go round to the front gate, and ring 999.Planned method1Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active workarea. Keep entrances and escape routes clear.2Confirm the hole on the drawingTake the hole position and size from the drawing, and record who authorised it. Keep the holeaway from lintels and the cavity tray. If it has to move, stop and go back to whoever drew it.3Find and isolate the socket circuitFind the cable before you disturb anything: the drawing, then a detector on both faces of thewall. Mark what you find. Have the circuit locked off and proved dead before the rig goes on. Ifthe detector and the drawing disagree, stop.4Carry the materials and equipment safelyPlan the route, clear it, and get help with anything long or heavy. Store materials close to thework so nobody carries further than they need to.5Clear the outside before coringCone off the ground under the hole outside, and stand a catch box of sand under it to take theouter core. Keep one person outside by the cones. Nobody goes inside them until the drillersays the core is down.Worked example of a method statement. Change it to fit your job before you use it.Page 2 of 3
  3. Example: Core drilling a flue hole through a cavity blockwork wallComplyOnSite6Fix the rig to the wallFix the rig to the inner leaf with an anchor suited to dense block, as the rig’s manual and theanchor maker say. This is a horizontal hole, so add the second fixing the manual asks for, suchas a chain to an anchor. Check it cannot move before starting.7Assess vibration from the core drillNote how long each person's hands are on each tool while it runs. Take the tool's vibrationfigure from the maker or HSE's table and check it fits how you use it. Points per hour timeshours on the trigger, added up for the day, gives the exposure: 100 points is the action value,400 is the limit. HSE's vibration calculator does the sum. Over 100, cut it with lower-vibrationkit or less time, and never pass 400. Write the result down. Sharing the work does not replacethis.8Keep the water on and collect itThis job is wet coring: keep the water on from the first cut to the last. Fit the water collector tothe wall and keep a wet vacuum beside it. Sheet the floor before the water goes on. Bag theslurry and the catch box sand for disposal. It does not go down a drain.9Keep the electrics out of the waterRun the rig at 110 V from a transformer plugged into an RCD-protected socket. Test the RCDbefore each use. Stand the transformer away from the water. Check the leads, keepconnections out of the slurry, and run the lead back from the machine. Isolate before you cleara fault.10Drill the coreTurn the water on before the bit touches, and keep it on for the whole cut. Wear eye, hearingand hand protection. Stop at the cavity, draw the bit back, and take out the inner core and thepiece of batt behind it, in gloves, before you drill on. Tell the person outside beforebreak-through. The outer core drops out into the catch box.11Stop a jam safelyStop feeding the bit and turn off the rig before you look at a jam. Remove the cause beforerestarting.12Leave the hole safeTake out the cores, vacuum the slurry and dry the floor. Cover the hole on both faces withtaped board until the flue goes in.13Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell thecustomer or whoever runs the site when the work is complete.Worked example of a method statement. Change it to fit your job before you use it.Page 3 of 3

The same sheet as text

Worked example of a method statement. Change it to fit your job before you use it.

Core drilling a flue hole through a cavity blockwork wall

Job details

  1. CompanyHollins & Reed Diamond Drilling Ltd
  2. Site and work area6 Alma Road, Stockport: rear extension
  3. Planned dates24 November 2026 (one morning)
  4. CustomerThornley Vale Estates Ltd
  5. In charge on siteDan Hollins
  6. TeamTwo people: Dan Hollins fixes the rig and drills; Tom Ellis stays outside by the cones until the outer core is down, on the phone to Dan from the first cut, then helps carry out.
  7. WorkCore drilling a flue hole through a cavity blockwork wall
  8. Risk assessmentCore drilling a flue hole through a cavity blockwork wall: worked example RAMS, a separate document

Work and boundaries

  1. Core one 125 mm flue hole from the inside, wet. Areas: Inside face of the rear extension wall, with the floor below the hole; Paving outside under the hole

Working arrangement

  1. Access: the floor or ground.
  2. What the hole goes through: A cavity blockwork wall.
  3. Coring machine: On a stand fixed to the structure.
  4. The work area will be kept clear of other people.
  5. The tenant stays in the house with the door to the extension shut; nobody else goes in the extension. The wall is the 2018 extension’s external wall: 100 mm dense block inside, a 100 mm cavity with mineral wool batts, 100 mm rendered block outside. The heating engineer’s drawing puts the hole centre 1.6 m above the floor, reached from the floor, 900 mm below the lintel line and clear of the cavity tray. The extension’s socket circuit runs in the wall 600 mm from the hole on the electrician’s drawing. A cable detector on both faces agrees, and a CAT scan along the foot of the wall outside shows nothing rising up it near the hole. The heating engineer’s drawing shows no gas or water pipe in this wall. The landlord’s electrician locks that circuit off at the consumer unit while we drill, and puts it back on when the rig is off the wall, so the transformer runs from a hall socket on the house circuit, with the lead taped down under the door. One hole takes under an hour with the door to the garden open, so water does the work and no mask is needed. Each core is 125 mm across, 100 mm long and about 2.5 kg, taking a dense block at about 2,000 kg/m³. Both are lifted by hand once the bit has stopped. The heating engineer sleeves and seals the hole when the flue goes in.

Emergency arrangements

  1. Anyone hurt, or an electric shock: stop the rig and switch off at the transformer, then Tom Ellis rings 999, or Dan Hollins if Tom is the one hurt, and gives 6 Alma Road, rear extension. Whoever rings stays with the casualty. Dan Hollins is the first aider, and the kit is in the van on the drive. The tenant meets the crew at the front gate and brings them round the side path, which stays clear. Fire: leave by the door to the garden, go round to the front gate, and ring 999.

Planned method

  1. 1. Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active work area. Keep entrances and escape routes clear.
  2. 2. Confirm the hole on the drawingTake the hole position and size from the drawing, and record who authorised it. Keep the hole away from lintels and the cavity tray. If it has to move, stop and go back to whoever drew it.
  3. 3. Find and isolate the socket circuitFind the cable before you disturb anything: the drawing, then a detector on both faces of the wall. Mark what you find. Have the circuit locked off and proved dead before the rig goes on. If the detector and the drawing disagree, stop.
  4. 4. Carry the materials and equipment safelyPlan the route, clear it, and get help with anything long or heavy. Store materials close to the work so nobody carries further than they need to.
  5. 5. Clear the outside before coringCone off the ground under the hole outside, and stand a catch box of sand under it to take the outer core. Keep one person outside by the cones. Nobody goes inside them until the driller says the core is down.
  6. 6. Fix the rig to the wallFix the rig to the inner leaf with an anchor suited to dense block, as the rig’s manual and the anchor maker say. This is a horizontal hole, so add the second fixing the manual asks for, such as a chain to an anchor. Check it cannot move before starting.
  7. 7. Assess vibration from the core drillNote how long each person's hands are on each tool while it runs. Take the tool's vibration figure from the maker or HSE's table and check it fits how you use it. Points per hour times hours on the trigger, added up for the day, gives the exposure: 100 points is the action value, 400 is the limit. HSE's vibration calculator does the sum. Over 100, cut it with lower-vibration kit or less time, and never pass 400. Write the result down. Sharing the work does not replace this.
  8. 8. Keep the water on and collect itThis job is wet coring: keep the water on from the first cut to the last. Fit the water collector to the wall and keep a wet vacuum beside it. Sheet the floor before the water goes on. Bag the slurry and the catch box sand for disposal. It does not go down a drain.
  9. 9. Keep the electrics out of the waterRun the rig at 110 V from a transformer plugged into an RCD-protected socket. Test the RCD before each use. Stand the transformer away from the water. Check the leads, keep connections out of the slurry, and run the lead back from the machine. Isolate before you clear a fault.
  10. 10. Drill the coreTurn the water on before the bit touches, and keep it on for the whole cut. Wear eye, hearing and hand protection. Stop at the cavity, draw the bit back, and take out the inner core and the piece of batt behind it, in gloves, before you drill on. Tell the person outside before break-through. The outer core drops out into the catch box.
  11. 11. Stop a jam safelyStop feeding the bit and turn off the rig before you look at a jam. Remove the cause before restarting.
  12. 12. Leave the hole safeTake out the cores, vacuum the slurry and dry the floor. Cover the hole on both faces with taped board until the flue goes in.
  13. 13. Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell the customer or whoever runs the site when the work is complete.

What a finished method statement says

  • The job and its boundariesWhat is being done, where, and what is not your work.
  • How the work area is set upAccess, shared spaces and who else is around.
  • The steps, in the order they happenOne action to a step, from arrival to sign-off.
  • Who does each stepThe people in charge and the skills each step needs.
  • What happens if something goes wrongWho to call, where to go and how help gets in.

Method statement or risk assessment: which one is this?

This is the method statement: how the job is done, step by step. The risk assessment says what could go wrong and what controls it.

See both together in the Core drilling RAMS example.

Method statement example questions

Are these real jobs?

No. Every job, company, person and address here is made up, and every page says so.

Can I send one as it is?

No. Your site, your people and your emergency arrangements will be different. Change it to fit your job first.

Where is the risk assessment that goes with it?

In the Core drilling RAMS example. The method statement names it on page one.

Word or PDF?

Both. Word if you will change the wording yourself, PDF to read or print. Or press Use this and edit it in the builder.

Does a method statement need a risk assessment?

A method statement names the risk assessment it rests on. CDM 2015 does not set a form for either document.

Where is the blank?

On the method statement template page. These examples are all filled in.