Core drilling RAMS Builder

Core drilling risk assessment and method statement

Prepare the Core drilling RAMS

Checking this browser for your work…

RAMS review

Check a RAMS
A RAMS page with passages highlighted and numbered review comments beside them

Core drilling RAMS template

A blank core drilling RAMS to fill in: job details, method statement, risk assessment and briefing record.

Risk assessment and method statement

Core drilling RAMS

Company
left blank to fill in
Site and work area
left blank to fill in
Planned dates
left blank to fill in
In charge on site
left blank to fill in
Team
left blank to fill in

Method statement

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6

Risk assessment

HazardWho might be harmed and howControls in placeFurther action

Core drilling RAMS example

The same RAMS, filled in for one job.

Risk assessment and method statement

Core drilling, Unit 3, Canal Side Business Park, Stockport

Risk assessment

  • People entering the work area or tripping over materials

    Workers, occupants and visitors

    Mark or barrier the active work area. Store tools and materials away from access routes.

  • A cut through steel or a load-bearing part weakens the structure

    Everyone using the building

    Scan or locate bars and services before setting out the hole. Stop if the hole moves from the drawing.

  • Breathing asbestos fibres from old boards, sheets, sealants or insulation

    The team and anyone in the building

    Do not cut, drill or break any material until it is confirmed asbestos free. Licensed work is not for this method; hand it to a licensed contractor.

  • Hitting a live cable or gas pipe causes shock, fire or gas escape

    The person doing the work and everyone nearby

    Check again wherever the work moves. If you hit something, stop, keep clear and report it.

  • Back and shoulder injury from carrying heavy or long items

    Everyone handling materials

    Use a trolley or sack truck on the flat where the load suits one. Where the work is up a level, hand items up or hoist them. Never carry them up a ladder.

  • The core or bit breaks through onto a person or occupied area

    The driller and people on either side

    Barrier the far side and below the work. Do not rely on somebody waiting below to catch the core.

  • The machine rotates, tips or pulls out of its support

    The driller and people nearby

    Use an anchor suited to the base material and check the fixing. Do not use an unapproved overhead vacuum fixing.

  • Hand-arm vibration from the core drill

    The driller

    Keep the tools maintained and hands warm. Gloves do not stop vibration. Give health checks to anyone above the action value.

  • Breathing silica dust or slipping on slurry

    The driller and people in the area

    Keep others out of the dust or slurry area. Stop if collection fails or water reaches the machine.

  • Silica dust if the water stops, and slipping on slurry

    The driller and people in the area

    Stop if the water or collection stops.

  • Electric shock from a wet machine, lead or connection

    The driller and anyone standing in the water

    Never bypass or disable an RCD. Stop if the water reaches the motor or a connection.

  • Water or slurry comes through onto the floor below

    People and equipment on the floor below

    Stop and shut the water off if it reaches the floor below.

  • A heavy core drops or is handled badly when it comes free

    The driller and people on the far side

    Work out the weight of the core for its size and depth before lifting it. Hold the core in place or clear the area below. Nobody catches it by hand.

  • The bit snatches or the operator loses control when it jams

    The driller

    Stop before investigating the jam. Isolate the machine before removing the core or stripping it down.

  • An open hole or loose core causes a fall or strikes someone later

    The drilling team and people using the building

    Keep the barrier up until the opening is safe. Do not leave cores or slurry where another trade can trip on them.

  • Debris, tools or unfinished work left in the area

    Workers, occupants and visitors

    Remove waste by the agreed route. Record and protect any unfinished work.

Core drilling, Unit 3, Canal Side Business Park, Stockport

Company
Hollins & Reed Contracting Ltd
Site and work area
Unit 3, Canal Side Business Park, Stockport
Planned dates
12 to 14 October 2026
In charge on site
Dan Hollins
Team
Two operatives: Dan Hollins leads and checks the area each morning; Priya Shah works with him.

Method statement

  1. 1Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active work area. Keep entrances and escape routes clear.
  2. 2Confirm what the slab is before any holeTake every hole position and size from a drawing, and record who authorised each one. Know what the slab or wall is before setting out. Do not cut reinforcement unless the engineer has agreed it.
  3. 3Check for asbestos before you disturb anythingCheck the asbestos survey covers exactly what you will disturb, to the full depth. Register only, or nothing: get a refurbishment survey or a sample first. Read what it says about old boards, coatings, ceiling voids and linings. No survey, or a material you do not recognise: stop and get it checked.
  4. 4Find and isolate hidden servicesFind cables and pipes before you disturb anything: drawings, then a detector. Mark what you find. Not sure what is there? Turn the supply off, or do not start. Have cables and gas isolated by the right person and prove them dead before you start.
  5. 5Carry the materials and equipment safelyPlan the route, clear it, and get help with anything long or heavy. Store materials close to the work so nobody carries further than they need to.
  6. 6Protect the far side before coringCheck the other side before drilling and keep people out where the bit or core can emerge. Name who controls the far side. Plan how the core will be held before the hole breaks through.
  7. 7Secure the stand or machineFix the stand or set the handheld machine exactly as its current manual requires. Check it cannot move before starting.
  8. 8Assess vibration from the core drillNote how long each person's hands are on each tool while it runs. Take the tool's vibration figure from the maker or HSE's table and check it fits how you use it. Points per hour times hours on the trigger, added up for the day, gives the exposure: 100 points is the action value, 400 is the limit. HSE's vibration calculator does the sum. Over 100, cut it with lower-vibration kit or less time, and never pass 400. Write the result down. Sharing the work does not replace this.
  9. 9Control dust and slurry for the whole coreKeep the water or extraction running from the first cut to the last. Keep collected material contained for removal.
  10. 10Wet coringThis job is wet coring: keep water on and collect the slurry.
  11. 11Keep the electrics out of the waterUse cordless or 110V kit suited to wet work, with the PRCD the machine came with. Test it before each use. Check the leads. Keep plugs and connections out of water and slurry, and run the lead back from the machine. Isolate before you clear a fault.
  12. 12Keep the water off the floor belowRoute the water away or collect it, and contain the slurry on both levels. Protect the floor around each hole before the water goes on.
  13. 13Drill each coreTurn the water or extraction on before the bit touches, and keep it on for the whole cut. Wear eye, hearing and hand protection. Near break-through keep the far side clear: the core may fall out.
  14. 14Stop a jam safelyStop downward pressure and turn off the tool before investigating a jam. Remove the cause before restarting.
  15. 15Leave the opening safeRemove the core and slurry, and cover and mark the finished hole at once. Where the slab is a fire-resisting floor, name who fire-stops the opening and when.
  16. 16Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell the customer or whoever runs the site when the work is complete.

What a core drilling RAMS covers

Diamond core drilling through an authorised opening, with the far side controlled and the core held. Not covered: sawing openings in a slab.

Suggested steps and hazards for core drilling

Suggested for core drill before any questions are answered.

  1. Confirm what the slab is before any hole

    • Take every hole position and size from a drawing, and record who authorised each one.
    • Know what the slab or wall is before setting out. Do not cut reinforcement unless the engineer has agreed it.

    Hazard

    A cut through steel or a load-bearing part weakens the structure

    Who might be harmed and how

    Everyone using the building

    Controls in place

    • Scan or locate bars and services before setting out the hole.
    • Stop if the hole moves from the drawing.

    Coring can upset the balance of a structure when steel or load-bearing parts are cut.

    PUB_5501754_000.pdf
  2. Protect the far side before coring

    • Check the other side before drilling and keep people out where the bit or core can emerge.
    • Name who controls the far side. Plan how the core will be held before the hole breaks through.

    Hazard

    The core or bit breaks through onto a person or occupied area

    Who might be harmed and how

    The driller and people on either side

    Controls in place

    • Barrier the far side and below the work.
    • Do not rely on somebody waiting below to catch the core.

    The far side needs protection before the bit or core can break through.

    PUB_5501754_000.pdf
  3. Secure the stand or machine

    • Fix the stand or set the handheld machine exactly as its current manual requires.
    • Check it cannot move before starting.

    Hazard

    The machine rotates, tips or pulls out of its support

    Who might be harmed and how

    The driller and people nearby

    Controls in place

    • Use an anchor suited to the base material and check the fixing.
    • Do not use an unapproved overhead vacuum fixing.

    The machine must not move when its support takes the drilling torque.

    PUB_5501754_000.pdf
  4. Assess vibration from the core drill

    • Note how long each person's hands are on each tool while it runs. Take the tool's vibration figure from the maker or HSE's table and check it fits how you use it. Points per hour times hours on the trigger, added up for the day, gives the exposure: 100 points is the action value, 400 is the limit. HSE's vibration calculator does the sum. Over 100, cut it with lower-vibration kit or less time, and never pass 400. Write the result down. Sharing the work does not replace this.

    Hazard

    Hand-arm vibration from the core drill

    Who might be harmed and how

    The driller

    Controls in place

    • Keep the tools maintained and hands warm. Gloves do not stop vibration.
    • Give health checks to anyone above the action value.

    Time on the tool decides the harm, so it has to be measured against the tool that is actually used.

    Construction physical ill health risks: Vibration

What the builder asks about core drilling

Your answers decide which steps, hazards and controls it suggests.

The job

  • What are you coring through?
  • How is the coring machine held?
  • Which way does the hole go?

Where

  • Is the building older than the year 2000? Older buildings can have asbestos in them.
  • What pipes or cables run behind or through the wall, floor or ceiling?

How it’s done

  • What will you stand on to reach the work?
  • How will you control the water or dust?
  • Will you cut anything on site, and with what?
  • How will the materials and equipment get to the work?

What your core drilling RAMS includes

Method statement

The work in order, step by step.

Risk assessment

Each hazard, who could be harmed, the controls in place and any further action.

PDF

The method statement and risk assessment in one A4 PDF. Your logo on Pro and Team.

What the law asks for

What a RAMS is

A risk assessment and method statement. The risk assessment records what could cause harm on the job, who could be harmed and how, and the controls that keep the risk down. The method statement sets out how the work will be done, step by step, in the order it happens.

A client or main contractor will usually ask for one before you start. RAMS is a site term, not a legal one: the law asks for the risk assessment and for the work to be planned, and a method statement is the usual way to show that plan for one job.

Learning to write one

The RAMS guide works through one trench job. It shows how to say which job it covers, name who each step could harm and put each control before the work it protects.

What the law asks for

  • Employers, and self-employed people doing construction work, must make a suitable and sufficient assessment of the risks to their own people and to anyone else affected by the work (Management of Health and Safety at Work Regulations 1999, regulation 3).
  • An employer with five or more employees must record the significant findings and any group of employees it finds especially at risk. The assessment must be reviewed if there is reason to think it is no longer valid, or the work has changed significantly.
  • Every contractor must plan, manage and monitor its work so that, so far as is reasonably practicable, it is done without risks to health and safety, and must give its workers the information and instructions they need, including the hazards the risk assessment found (Construction (Design and Management) Regulations 2015, regulation 15).

HSE guidance: the steps to manage risk and what contractors must do under CDM. This is the law in Great Britain; Northern Ireland has its own equivalent regulations.

What the builder does

You choose the work and answer questions about how the job will be done, such as what you will stand on and what else is going on nearby. Your answers decide which steps, hazards and controls it suggests.

Many suggestions link to the HSE guidance they draw on. Your work is kept in this browser and, signed in, on your account with its photos; the PDF is made on your device. A briefing you send to phones goes through your account.

Separate documents

A COSHH assessment, lifting plan, permit to work, asbestos survey and the principal contractor’s construction phase plan are separate from the RAMS.

Reviewing a RAMS before work starts

RAMS review reads a RAMS PDF, yours before you send it or one a subcontractor sends you, and lists the points to raise, each marked on the page it comes from. Quick reviews are free.