Skip to content

Drylining RAMS Builder

Drylining risk assessment and method statement

Prepare the Drylining RAMS

Checking this browser for your work…

RAMS review

Check a RAMS
A RAMS page with passages highlighted and numbered review comments beside them

Drylining RAMS template

A blank drylining RAMS to fill in: job details, method statement, risk assessment and briefing record.

Risk assessment and method statement

Drylining RAMS

Company
left blank to fill in
Site and work area
left blank to fill in
Planned dates
left blank to fill in
In charge on site
left blank to fill in
Team
left blank to fill in

Method statement

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6

Risk assessment

HazardWho might be harmed and howControls in placeFurther action

Drylining RAMS example

The same RAMS, filled in for one job.

Risk assessment and method statement

Drylining, Second floor offices, 14 Mill Street, Stockport

Risk assessment

  • People entering the work area or tripping over materials

    Workers, occupants and visitors

    Mark or barrier the active work area. Store tools and materials away from access routes.

  • People using the building or passing by walking into the work or over what it leaves

    Occupants, visitors, members of the public and workers

    Keep the barriers and signs up while the work is active. Give people a clear way round where their normal route is blocked.

  • Breathing asbestos fibres from old boards, sheets, sealants or insulation

    The team and anyone in the building

    Do not cut, drill or break any material until it is confirmed asbestos free. Licensed work is not for this method; hand it to a licensed contractor.

  • Hitting a live cable or gas pipe causes shock, fire or gas escape

    The person doing the work and everyone nearby

    Check again wherever the work moves. If you hit something, stop, keep clear and report it.

  • Materials and tools falling onto people below

    People below

    Bring waste down by hand or in bags. Never throw it. Keep the exclusion zone up until the last item is down.

  • Falling from the access equipment; tools or materials falling from the platform

    The person on the platform, if it is set up on an unsuitable surface and shifts under them. Anyone passing or working underneath.

    Place access equipment on a firm, level surface. Keep tools and materials secure while working above ground.

  • Back and shoulder injury from carrying heavy or long items

    Everyone handling materials

    Use a trolley or sack truck on the flat where the load suits one. Where the work is up a level, hand items up or hoist them. Never carry them up a ladder.

  • An unsupported opening weakens the partition or drops material

    Partition fixers and people nearby

    Check the set-out before fixing the frame. Do not improvise support for a structural opening.

  • A loose frame moves, falls or cannot support the boards

    Partition fixers and people nearby

    Use fixings suitable for the structure. Do not load an incomplete frame.

  • A service, support or fire detail is hidden and cannot be corrected later

    Other trades and building users

    Use the system detail for openings and penetrations. Keep heavy services off the frame unless the detail allows it.

  • The partition fails its fire, sound or robustness performance

    Building users and partition fixers

    Follow the system detail for board direction and fixing spacing. Record the system reference for rated work.

  • Sharp waste, hidden defects or incomplete fire and service work being handed over

    Partition fixers and following trades

    Leave the area clear and keep unresolved checks visible. Do not cover an open check with the next layer.

  • Debris, tools or unfinished work left in the area

    Workers, occupants and visitors

    Remove waste by the agreed route. Record and protect any unfinished work.

Drylining, Second floor offices, 14 Mill Street, Stockport

Company
Hollins & Reed Fitout Ltd
Site and work area
Second floor offices, 14 Mill Street, Stockport
Planned dates
12 to 14 October 2026
In charge on site
Dan Hollins
Team
Two fitters: Dan Hollins leads and sets out; Priya Shah works with him.

Method statement

  1. 1Set up the work areaConfirm the work area and scope before starting. Keep other people outside the active work area. Keep entrances and escape routes clear.
  2. 2Keep people clear of the workAgree how people get past or around the work while it is going on. Put barriers or signs where a route crosses the work. Do not leave open work unattended.
  3. 3Check for asbestos before you disturb anythingCheck the asbestos survey covers exactly what you will disturb, to the full depth. Register only, or nothing: get a refurbishment survey or a sample first. Read what it says about old boards, coatings, ceiling voids and linings. No survey, or a material you do not recognise: stop and get it checked.
  4. 4Find and isolate hidden servicesFind cables and pipes before you disturb anything: drawings, then a detector. Mark what you find. Not sure what is there? Turn the supply off, or do not start. Have cables and gas isolated by the right person and prove them dead before you start.
  5. 5Stop things falling on people belowKeep people out of the area below the work so nobody walks under the materials and tools. Keep toe boards and guards in place on any platform, and lanyard tools where you can.
  6. 6Set up access equipmentUse access equipment suited to the task and work area. Check the equipment before use. Keep the area below the work controlled.
  7. 7Carry the materials and equipment safelyPlan the route, clear it, and get help with anything long or heavy. Store materials close to the work so nobody carries further than they need to.
  8. 8Set out the partition and openingsMark the partition line and the positions of doors, access openings and heavy fittings. Use the approved non-loadbearing system detail and stop if an opening needs structural design.
  9. 9Fix the partition frameFix base and head channels and fit the studs to the system detail. Check the frame is stable before boarding.
  10. 10Check the cavity before closing itFix services and insulation in their planned positions before boarding the second face. Check the cavity and all openings before it is hidden.
  11. 11Fix the boards correctlyUse the specified boards, screws and layers and set screw heads flush. Do not break the paper or gypsum core or swap a component that looks similar.
  12. 12Hand back the finished partitionRemove offcuts, sharp fixings and dust. Tell the site what is complete and what remains open before the next trade starts.
  13. 13Clear and hand back the areaRemove tools, waste and unused materials. Check the area is clean and ready to use. Tell the customer or whoever runs the site when the work is complete.

What a drylining RAMS covers

Building metal-stud partitions, boarding walls and frames, adhesive board linings, taping and jointing, and MF ceilings. Not covered: stripping out existing partitions or ceilings.

  • Board partition
  • Adhesive board lining
  • Joint
  • MF boarded ceiling

Suggested steps and hazards for drylining

Suggested for board partition before any questions are answered.

  1. Stop things falling on people below

    • Keep people out of the area below the work so nobody walks under the materials and tools.
    • Keep toe boards and guards in place on any platform, and lanyard tools where you can.

    Hazard

    Materials and tools falling onto people below

    Who might be harmed and how

    People below

    Controls in place

    • Bring waste down by hand or in bags. Never throw it.
    • Keep the exclusion zone up until the last item is down.

    Falling objects are a leading cause of harm to the public near construction.

    HSE: Protecting the public
  2. Set out the partition and openings

    • Mark the partition line and the positions of doors, access openings and heavy fittings.
    • Use the approved non-loadbearing system detail and stop if an opening needs structural design.

    Hazard

    An unsupported opening weakens the partition or drops material

    Who might be harmed and how

    Partition fixers and people nearby

    Controls in place

    • Check the set-out before fixing the frame.
    • Do not improvise support for a structural opening.

    Openings and heavy fittings need their support planned before the partition is boarded.

    White Book - GypWall Single Frame
  3. Fix the partition frame

    • Fix base and head channels and fit the studs to the system detail.
    • Check the frame is stable before boarding.

    Hazard

    A loose frame moves, falls or cannot support the boards

    Who might be harmed and how

    Partition fixers and people nearby

    Controls in place

    • Use fixings suitable for the structure.
    • Do not load an incomplete frame.

    The frame must be stable before it carries the boards.

    GypWall Single Frame internal partition system A206099

What the builder asks about drylining

Your answers decide which steps, hazards and controls it suggests.

The job

  • Does the partition have a fire or sound rating?
  • What will hold the ceiling?
  • What is the wall behind the board?
  • What finish does the joint need?
  • What will the lining support?
  • What does the partition need to make room for?
  • Does this ceiling have a rating?

Where

  • Is the building older than the year 2000? Older buildings can have asbestos in them.
  • What pipes or cables run behind or through the wall, floor or ceiling?

How it’s done

  • What will you stand on to reach the work?
  • Which jointing compound will you use?
  • What will be hidden in the cavity?
  • What will go in the cavity?
  • How will you control sanding dust?

What your drylining RAMS includes

Method statement

The work in order, step by step.

Risk assessment

Each hazard, who could be harmed, the controls in place and any further action.

PDF

The method statement and risk assessment in one A4 PDF. Your logo on Pro and Team.

What the law asks for

What a RAMS is

A risk assessment and method statement. The risk assessment records what could cause harm on the job, who could be harmed and how, and the controls that keep the risk down. The method statement sets out how the work will be done, step by step, in the order it happens.

A client or main contractor will usually ask for one before you start. RAMS is a site term, not a legal one: the law asks for the risk assessment and for the work to be planned, and a method statement is the usual way to show that plan for one job.

Learning to write one

The RAMS guide works through one trench job. It shows how to say which job it covers, name who each step could harm and put each control before the work it protects.

What the law asks for

  • Employers, and self-employed people doing construction work, must make a suitable and sufficient assessment of the risks to their own people and to anyone else affected by the work (Management of Health and Safety at Work Regulations 1999, regulation 3).
  • An employer with five or more employees must record the significant findings and any group of employees it finds especially at risk. The assessment must be reviewed if there is reason to think it is no longer valid, or the work has changed significantly.
  • Every contractor must plan, manage and monitor its work so that, so far as is reasonably practicable, it is done without risks to health and safety, and must give its workers the information and instructions they need, including the hazards the risk assessment found (Construction (Design and Management) Regulations 2015, regulation 15).

HSE guidance: the steps to manage risk and what contractors must do under CDM. This is the law in Great Britain; Northern Ireland has its own equivalent regulations.

What the builder does

You choose the work and answer questions about how the job will be done, such as what you will stand on and what else is going on nearby. Your answers decide which steps, hazards and controls it suggests.

Many suggestions link to the HSE guidance they draw on. Your work is kept in this browser and, signed in, on your account with its photos; the PDF is made on your device. A briefing you send to phones goes through your account.

Separate documents

A COSHH assessment, lifting plan, permit to work, asbestos survey and the principal contractor’s construction phase plan are separate from the RAMS.

Reviewing a RAMS before work starts

RAMS review reads a RAMS PDF, yours before you send it or one a subcontractor sends you, and lists the points to raise, each marked on the page it comes from. Quick reviews are free.